5950--NRM-CONST 528A5-24-516 - Replace 5MV Transformer
| Agency: | VETERANS AFFAIRS, DEPARTMENT OF |
|---|---|
| State: | Federal |
| Type of Government: | Federal |
| FSC Category: |
|
| NAICS Category: |
|
| Posted Date: | Jul 11, 2025 |
| Due Date: | Jul 23, 2025 |
| Solicitation No: | 36C24225B0028 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
- Contract Opportunity Type: Solicitation (Updated)
- Updated Published Date: Jul 11, 2025 09:48 am EDT
- Original Published Date: Jun 18, 2025 12:40 pm EDT
- Updated Date Offers Due: Jul 23, 2025 12:30 pm EDT
- Original Date Offers Due: Jul 16, 2025 12:30 pm EDT
- Inactive Policy: Manual
- Updated Inactive Date: Aug 22, 2025
- Original Inactive Date: Sep 14, 2025
-
Initiative:
- None
- Original Set Aside:
- Product Service Code: 5950 - COILS AND TRANSFORMERS
-
NAICS Code:
- 238210 - Electrical Contractors and Other Wiring Installation Contractors
-
Place of Performance:
Yes
Is the transformer to be replaced currently de-energized and only being used for backup?
The transformer is currently out of service pending repairs scheduled to be completed during Summer 2025. The bidding contractors shall assume the transformer will need to be de-energized prior to work start.
Is there a preferred day of the week and time of day for the transformer replacement?
There is no preference, coordination with facilities will be required to minimize impact.
What is the maximum duration for the redundant transformer to be unavailable during replacement?
1 week maximum.
Please provide specific details on how the existing transformer being replaced will be turned over. (set to the side of the yard or transported to a designated location?)
The transformer can be set to the side within the secure fence in a location to not impede access to other equipment.
Does the facility have one-line drawings, as-builts, or design drawings of any kind for the current primary switchgear, transformer, and secondary switchgear?
Refer to Attachment B _ ES107 _ Electrical Site Plan This attachment is from the original design at time of award. Actual installation of the transformer may vary slightly.
Does the facility know the correct lockout locations to isolate the transformer being replaced?
Lockout locations are in the adjacent switchgear within the secure fence area.
Please confirm no testing or new terminations are required for the existing MV cables.
Testing of new terminations is not required as the existing terminations are to be re-used. Testing may be required if the existing terminations are damaged during construction and need to be replaced.
Do you have pictures of the Medium Voltage and Low Voltage connection compartments. Just would like to see the conduit arrangement and the connections.
Refer to Attachment A _ Pictures
Are transformers in the basis of design memo what was originally purchased?Â
Yes
Is the VA looking for a direct replacement of the failed one?
Yes. Approved equal would be considered.
Is the VA looking for a direct replacement of the failed one?
Yes. Approved equal would be considered.
If Yes then in the specifications that were sent out the installation instructions 3.1.A, B, C, D.1,.2, .3 would have already been done by the initial installer of the transformer
Concrete pad, anchors, and grounding rods are all existing. The new transformer shall be mounted to the existing concrete pad using existing anchors to secure the unit. Contractor is responsible for any additional anchors that may be required to for proper installation.
3.4 - Spare parts are they required as part of this bid?
Yes
3.5 - Instruction - is this still required?
Not Needed
Q13. A previous notice described a transformer in Bath, NY as well? Is this a part of this project?
The Bath transformer was able to be replaced in-house and is not a part of this project.
- 113 HOLLAND AVE
- ALBANY , NY 12208
- USA
- Devan Bertch
- Devan.Bertch@va.gov
- Jul 11, 2025 09:48 am EDTSolicitation (Updated)
- Jun 18, 2025 12:40 pm EDT Solicitation (Original)
Related Document
| Apr 24, 2025 | [Presolicitation (Original)] 5950--528A5-24-516 - Replace 5MV Transformer |
| May 22, 2025 | [Presolicitation (Updated)] 5950--NRM-CONST 528A5-24-516 - Replace 5MV Transformer |
| Jun 18, 2025 | [Solicitation (Original)] 5950--NRM-CONST 528A5-24-516 - Replace 5MV Transformer |
| Sep 18, 2025 | [Award Notice (Original)] Y1DA--528A5-24-516 - Replace 5MV Transformer |
See Also
Follow CIRCUIT CARD ASSEMB Active Contract Opportunity Notice ID N0010426QQB96 Related Notice Department/Ind.
DEPT OF DEFENSE
Due by 10/09/2026
Follow 59--NRP,CCA,BOARD,ANALO, IN REPAIR/MODIFICATION OF Active Contract Opportunity Notice ID N0038326QNA92 Related Notice
DEPT OF DEFENSE
Due by 10/02/2026
Follow CIRCUIT CARD ASSEMB Active Contract Opportunity Notice ID N0010426QNE66 Related Notice Department/Ind.
DEPT OF DEFENSE
Due by 9/17/2026
Follow 59--ROTOR POSITIONING U, IN REPAIR/MODIFICATION OF Active Contract Opportunity Notice ID N0038326RBA39
DEPT OF DEFENSE
Due by 9/17/2026