Bid Set No. __________________
Bidder ______________________
PROJECT MANUAL
FOR
FY 2025-2026 TOWN OF STALLINGS
PAVEMENT PRESERVATION & REPAIR PROGRAM
(Formal Bid Process)
Town Council: David Scholl, Mayor Pro-Tempore
Graham Hall
Traylor-Rae Drake
Steven Ayers
Laurie Wojtowicz
Brad Richardson
Date: 12/03/2024
Mayor: Wyatt Dunn
Town Manager: Alex Sewell
SOLICITATION FOR BIDS
December 22, 2025
The Town of Stallings invites qualified construction contractors to submit bids for the Town of Stallings’
FY 2026 Pavement Preservation and Repair Program to complete micro surfacing on several roadways
located in the Town of Stallings.
Bids are due no later than 2:00 P.M. local time on Tuesday, January 6, 2026, to the following address:
FY 2026 Pavement Preservation and Repair Program Bid Package
c/o Justin Russell, Associate Engineer
Town of Stallings
Engineering Department
315 Stallings Road
Stallings, NC 28104
The bid opening will occur on Tuesday, January 6, 2026, at 2:05p.m. at the following address:
Second Floor of Stallings Town Hall
315 Stallings Road
Stallings, NC, 28104
If three bids are not received by the Tuesday, January 6, 2026, deadline, the Town will re-advertise for
bids beginning on Tuesday, January 6, 2026, with a submission deadline of Tuesday, January 13, 2026, at
2:00 p.m. The contractor(s) may choose to leave their unopened bid(s) with the Town to hold until the
second and final bid opening that will occur on Tuesday, January 13, 2026, at 2:05 p.m.
Upon verification of each bid’s accuracy and completeness, the lowest bidder shall be awarded the
contract.
For any questions related to the bid package please contact:
Kevin Parker, Engineering Director
Justin Russell
kparker@stallingsnc.org
jrussell@stallingsnc.org
704-821-0309
704-821-0321
The following Contract Special Provisions contains the formatting, content, and other
requirements for a bid. Any bids received after the date and time listed above will be rejected
and returned unopened
2
Table of Contents
CONTRACT SPECIAL PROVISIONS ........................................................................................................................1
CONTRACT PERIOD ..............................................................................................................................................1
CONTRACT TIME EXTENSION............................................................................................................................1
GUARANTEE ........................................................................................................................................................... 1
LIQUIDATED DAMAGES ......................................................................................................................................1
CONTRACT BONDS (NCDOT Section 103-7 and 103-9)......................................................................................1
DEFINITION OF TERMS ........................................................................................................................................2
INDEMNIFICATION ...............................................................................................................................................2
MINORITY/WOMEN/SMALL BUSINESS ENTERPRISE:..................................................................................3
INSURANCE REQUIREMENTS.............................................................................................................................3
E-VERIFY .................................................................................................................................................................4
TERMINATION BY THE TOWN FOR CAUSE.....................................................................................................4
TERMINATION BY THE TOWN FOR CONVENIENCE .....................................................................................5
NOTICE TO PROCEED ...........................................................................................................................................5
PRE-CONSTRUCTION CONFERENCE.................................................................................................................5
COMMUNITY NOTICE...........................................................................................................................................6
ADDITIONAL OR EXTRA WORK ........................................................................................................................6
CARE OF WORK .....................................................................................................................................................6
CLEANING UP.........................................................................................................................................................6
OSHA REQUIREMENTS.........................................................................................................................................6
HAZARDOUS MATERIALS...................................................................................................................................6
MATERIALS AND EQUIPMENT STORAGE .......................................................................................................7
METHOD AND MATERIAL ...................................................................................................................................7
INVOICING AND PERIODIC PAYMENTS...........................................................................................................7
PROJECT CLOSEOUT DOCUMENTS ...................................................................................................................7
TAX STATEMENT SUBMITTAL...........................................................................................................................7
TAXES AND LICENSES .........................................................................................................................................8
SUBLETTING........................................................................................................................................................... 8
SPECIAL CONTRACT PROVISIONS ....................................................................................................................8
ASPHALT PRESERVATION ..................................................................................................................................8
ADJUSTMENT OF STRUCTURES.......................................................................................................................14
REBUILD SHOULDERS .......................................................................................................................................14
LOAD LIMITS........................................................................................................................................................14
TRAFFIC CONTROL .............................................................................................................................................14
MOBILIZATION ....................................................................................................................................................15
QUALITY CONTROL............................................................................................................................................15
BID SCHEDULE ....................................................................................................................................................15
BONDS AND CERTIFIED POWER OF ATTORNEY .............................................................................................17
INSURANCE CERTIFICATE ....................................................................................................................................18
CONTRACTOR'S AFFIDAVIT RELEASE AND WAIVER OF CLAIM ................................................................19
STATE/COUNTY SALES & USE TAX STATEMENT............................................................................................20
Exhibit A – Roadway Maps.....................................................................................................................................21
CONTRACT SPECIAL PROVISIONS
FY 2026 Town of Stallings
Pavement Preservation Project (Formal Bid Process)
If there is any conflict between the special provision and any standard specifications the special provisions
shall take precedence.
CONTRACT PERIOD
The Contract period will begin upon the issuance of the Notice to Proceed, and the project must be
completed and fully invoiced by May 1, 2026.
CONTRACT TIME EXTENSION
(Contract Time Extensions and Apportionment of Liquidated Damages NCDOT section 108-12)
The Contractor’s attention is directed to article 108-10 through 108-13 in the NCDOT standard specifications
in respect to completion time, liquidated damages, and termination of contract. The completion date may be
extended at the written approval of the Town Engineer, due to extreme weather conditions or any delay to
utility repairs.
GUARANTEE
The Contractor shall guarantee all materials and workmanship for a period of one (1) year from the date
of acceptance by the Town and shall replace any portions that fail because of faulty materials or
workmanship at no additional cost to the Town. A six (6) month and eleven (11) month inspection will
be held during the warranty period. The Contractor shall immediately repair all defective items upon
notification. Items repaired under the provisions shall have an extended warranty period of twelve (12)
months from the date of accepted repair of the item.
The performance bond will be held as the guarantee for the one (1) year period following the completion
of the project.
LIQUIDATED DAMAGES
Bidder hereby agrees to commence work under this contract on a date to be specified in written “Notice to
Proceed” by the Town of Stallings and agrees to complete the work within the time as stipulated in the
specifications. Bidder further agrees to pay Liquidated Damages, in the sum of five hundred dollars ($500.00)
for each consecutive calendar day after the established or extended date as established by the extension
provision of this contract. The completion of the project within the contract period shall include the correction
of all deficiencies provided by the Town on punch lists during the inspections of the project.
CONTRACT BONDS (NCDOT Section 103-7 and 103-9)
The successful bidder, within 14 calendar days after the notice of award is received by him, shall provide the
Town with a contract payment bond and a contract performance bond each in an amount equal to 100% of
the amount of the contract pursuant to NCGS §44A-26. All bonds shall be in conformance with NCGS §
44A-33. The corporate surety furnishing the bonds shall be authorized to do business in the State of North
Carolina.
The successful bidder's failure to file acceptable bonds within 14 calendar days after the notice of award is
received by him shall be just cause for the forfeiture of the bid bond or bid deposit and rescinding the award
1
of the contract. Award may then be made to the next lowest responsible bidder, or the work may be
readvertised and constructed under contract or otherwise, as the Town may decide.
DEFINITION OF TERMS
Whenever the following terms are used in the Standard Specifications, in any of the Contract Documents, or
in the plans, the intended meaning of such terms shall be as follows:
“State or Department” shall be replaced by the words Town of Stallings.
“Sampling and Testing by Department” shall be replaced by the words sampling and testing by Town or its
approved testing agency.
“Inspection by Department” shall be replaced by the words inspection by the Town or its duly authorized
representative.
“Owner” shall be replaced by the words Town of Stallings with whom the Contractor has entered into the
Agreement and for whom the Work is to be provided.
“Town Standards” shall refer to the latest edition of Stallings Land Development Standards Manual or
NCDOT Standards.
INDEMNIFICATION
a. To the fullest extent allowed by law, the Contractor shall indemnify and hold harmless
the Town, its officers, officials, employees, agents, or indemnities (collectively called
“Indemnified Parties”) from and against those losses, liabilities, damages, and costs
proximately caused by, arising out of, or resulting from the negligence of the Contractor,
the Contractor’s agents, or the Contractor’s employees.
b. In matters other than those covered by subsection (a) above, and to the fullest extent
allowed by law, the Contractor shall indemnify and hold harmless the Indemnified Parties
from and against those losses, liabilities, damages, and costs caused by, arising out of,
resulting from, or in connection with the execution of the work provided for in this
contract when the fault of the Contractor or its derivative parties is a proximate cause of
the loss, liability, damage, or expense indemnified.
c. Costs and expenses shall include attorneys’ fees, litigation or arbitration expenses, or
court costs actually incurred by the Indemnified Parties to defend against third-party
claims alleged in any court, tribunal, or alternative dispute resolution procedure required
of any of the Indemnified Parties by law or by contract, only if the fault of the Contractor
or its derivative parties is a proximate cause of the attorney’s fees, litigation or arbitration
expenses, or court costs to be indemnified.
d. Only to the extent provided pursuant to a policy of insurance, the Contractor shall defend
the Indemnified Parties against claims alleged in any court, tribunal, or alternative dispute
resolution procedure if the fault of the Contractor or its derivative parties is a proximate
cause of such claims.
e. The Contractor’s duty to indemnify, defend, and hold harmless described hereinabove
shall survive the termination or expiration of this Contract.
f. Definitions:
i. For the purposes of this Section, the term “Fault” shall mean any breach of
contract; negligent, reckless, or intentional act or omission constituting a tort
under applicable statutes or common law; or violation of applicable statutes or
regulations.
ii. For the purposes of this Section, the term “Loss” or “Losses” shall include, but
not be limited to, fines, penalties, and/or judgments issued or levied by any local,
2
This page summarizes the opportunity, including an overview and a preview of the attached documents.