| Agency: | City of Denver |
|---|---|
| State: | Colorado |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Apr 14, 2026 |
| Due Date: | May 26, 2026 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Closing date May 26, 2026, 10:00 AM
Contract No. 202684021 – 2026 WMD Pipe Rehabilitation Phase 1
April 14, 2026
General Statement of Work
The purpose of this project is to rehabilitate approximately 10,100’ of 8” sanitary sewer pipes using Cured-In-Place-Pipe (CIPP). CIPP is a trenchless rehabilitation method used to rehabilitate existing sewer pipes without excavation by installing through the existing manholes. It involves inserting a resin-saturated liner into the existing pipe and curing it in place to form a new, structurally sound pipe within the old host pipe. This project is part of the capital maintenance sub-program in the current 2022-2027 Six-Year Water Plan.
Statement of Quantities (PDF, 17KB) (PDF)
Estimated Construction Cost: Between $360,000.00 and $450,000.00.
Virtual Pre-Bid Meeting on April 28, 2026 at 10:00 a.m.
To access the meeting, please call 720-388-6219 and enter conference ID: 697 608 946# or join via
Microsoft Teams
.
Questions Deadline: May 5, 2026 at 10:00 a.m. local time.
Bid Opening on May 26, 2026 at 10:00 a.m.
Bids will be received and accepted via the online electronic bid service, Rocky Mountain E-Purchasing (“
BidNet
”). Prospective bidders must be on the plan holders list on BidNet for bids to be accepted. To access the electronic bid form, download the required documents from BidNet and complete the Unit Item Pricing in the Documents & Items section of the solicitation. All properly uploaded bids will then be opened, witnessed and read aloud. To access the bid opening teleconference, please call 720-388-6219 and enter conference ID: 465 716 43# or join via
Microsoft Teams
.
Plans Available April 14, 2026 – Digital Download – Solicitation No. 202684021
Contract Administrator: Cheryl Booker , DOTI.Procurement@denvergov.org
Prevailing Wage and Minimum Wage: Contracts for construction, reconstruction, and remodeling are subject to the City prevailing wage rate requirements established pursuant to Section 20-76, D.R.M.C. City contracts are subject to payment of City Minimum Wage established pursuant to Section 20-82 through 20-84 D.R.M.C.
As the City’s best interests may appear, the Executive Director of the Department of Transportation and Infrastructure reserves the right to waive informalities in, and to reject any or all, submittals.
Publication Date:
April 14, 2026
Published In:
Do Business with DOTI and BidNet
Pre-Bid Meeting: April 28, 2026, at 10:00 a.m.
Questions Deadline: May 5, 2026, at 10:00 a.m. local time.
Bid Opening on May 26, 2026, at 10:00 a.m.
Publication Date: April 14, 2026
Published In: Do Business with DOTI and BidNet
| Base Bid - Base Bid | |||
|---|---|---|---|
| Item No | Description | UOM | Quantity |
| 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 | Linear Foot/Feet | ||
| 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 | Linear Foot/Feet | ||
| HYDROPHILIC END SEAL SLEEVE - SOW A.6 | Each | ||
| GRINDING - M&P 34-17.5 | Linear Foot/Feet | ||
| SEWER SERVICE REACTIVATION - M&P 34-17.6a | Each | ||
| EXTENDED TAP CUTTING - M&P 34-17.7 | Each | ||
| TRAFFIC CONTROL - M&P 41.1 | Lump-Sum | ||
| CIPP LABORATORY TESTING - M&P 45-1 | Each | ||
| MOBILIZATION - M&P 50-1 | Lump-Sum |
| Allowance Accounts - Base Bid | |||
|---|---|---|---|
| Item No | Description | UOM | Quantity |
| Add Alt #1 - ADD ALTERNATIVE | |||
|---|---|---|---|
| Item No | Description | UOM | Quantity |
| 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 | Linear Foot/Feet | ||
| 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 | Linear Foot/Feet | ||
| HYDROPHILIC END SEAL SLEEVE - SOW A.6 | Each | ||
| GRINDING - M&P 34-17.5 | Linear Foot/Feet | ||
| SEWER SERVICE REACTIVATION - M&P 34-17.6a | Each | ||
| EXTENDED TAP CUTTING - M&P 34-17.7 | Each | ||
| TRAFFIC CONTROL - M&P 41.1 | Lump-Sum | ||
| CIPP LABORATORY TESTING - M&P 45-1 | Each |
| Add Alt #2 - ADD ALTERNATIVE | |||
|---|---|---|---|
| Item No | Description | UOM | Quantity |
| 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 | Linear Foot/Feet | ||
| 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 | Linear Foot/Feet | ||
| HYDROPHILIC END SEAL SLEEVE - SOW A.6 | Each | ||
| GRINDING - M&P 34-17.5 | Linear Foot/Feet | ||
| SEWER SERVICE REACTIVATION - M&P 34-17.6a | Each | ||
| EXTENDED TAP CUTTING - M&P 34-17.7 | Each | ||
| TRAFFIC CONTROL - M&P 41.1 | Lump-Sum | ||
| CIPP LABORATORY TESTING - M&P 45-1 | Each |
Statement of Quantities
Base Bid - Base Bid
Item No Description UOM Quantity
1 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 Linear Foot/Feet 7594
2 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 Linear Foot/Feet 7594
3 HYDROPHILIC END SEAL SLEEVE - SOW A.6 Each 2
4 GRINDING - M&P 34-17.5 Linear Foot/Feet 100
5 SEWER SERVICE REACTIVATION - M&P 34-17.6a Each 162
6 EXTENDED TAP CUTTING - M&P 34-17.7 Each 10
7 TRAFFIC CONTROL - M&P 41.1 Lump-Sum 1
8 CIPP LABORATORY TESTING - M&P 45-1 Each 10
9 MOBILIZATION - M&P 50-1 Lump-Sum 1
Textura Textura Fee (reference table on BF-3) Lump-Sum 1
Allowance Accounts - Base Bid
Item No Description UOM Quantity
10 ALLOWANCE ACCOUNT - NOISE VARIANCE - SOW A.4 Lump-Sum 1
Add Alt #1 - ADD ALTERNATIVE
Item No Description UOM Quantity
11 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 Linear Foot/Feet 1105
12 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 Linear Foot/Feet 1105
13 HYDROPHILIC END SEAL SLEEVE - SOW A.6 Each 1
14 GRINDING - M&P 34-17.5 Linear Foot/Feet 50
15 SEWER SERVICE REACTIVATION - M&P 34-17.6a Each 5
16 EXTENDED TAP CUTTING - M&P 34-17.7 Each 1
17 TRAFFIC CONTROL - M&P 41.1 Lump-Sum 1
18 CIPP LABORATORY TESTING - M&P 45-1 Each 1
19 MOBILIZATION - M&P 50-1 Lump-Sum 1
Add Alt #2 - ADD ALTERNATIVE
Item No Description UOM Quantity
20 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 Linear Foot/Feet 1136
21 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 Linear Foot/Feet 1136
22 HYDROPHILIC END SEAL SLEEVE - SOW A.6 Each 1
23 GRINDING - M&P 34-17.5 Linear Foot/Feet 50
24 SEWER SERVICE REACTIVATION - M&P 34-17.6a Each 35
25 EXTENDED TAP CUTTING - M&P 34-17.7 Each 1
26 TRAFFIC CONTROL - M&P 41.1 Lump-Sum 1
27 CIPP LABORATORY TESTING - M&P 45-1 Each 1
28 MOBILIZATION - M&P 50-1 Lump-Sum 1
Contract No. 202684021 SQ-1 April 14, 2026
2026 Rehab Phase 1
| Add Alt #3 - ADD ALTERNATIVE | |||
|---|---|---|---|
| Item No | Description | UOM | Quantity |
| 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 | Linear Foot/Feet | ||
| 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 | Linear Foot/Feet | ||
| HYDROPHILIC END SEAL SLEEVE - SOW A.6 | Each | ||
| GRINDING - M&P 34-17.5 | Linear Foot/Feet | ||
| SEWER SERVICE REACTIVATION - M&P 34-17.6a | Each | ||
| EXTENDED TAP CUTTING - M&P 34-17.7 | Each | ||
| TRAFFIC CONTROL - M&P 41.1 | Lump-Sum | ||
| CIPP LABORATORY TESTING - M&P 45-1 | Each |
Statement of Quantities
Add Alt #3 - ADD ALTERNATIVE
Item No Description UOM Quantity
29 8" PRE-VIDEO INSPECTION AND CLEANING OF SEWER PIPE- M&P 34-17.1 & .2 Linear Foot/Feet 1092
30 8" DIAMETER CURED-IN-PLACE-PIPE - M&P 34-17.4 Linear Foot/Feet 1092
31 HYDROPHILIC END SEAL SLEEVE - SOW A.6 Each 1
32 GRINDING - M&P 34-17.5 Linear Foot/Feet 50
33 SEWER SERVICE REACTIVATION - M&P 34-17.6a Each 24
34 EXTENDED TAP CUTTING - M&P 34-17.7 Each 2
35 TRAFFIC CONTROL - M&P 41.1 Lump-Sum 1
36 CIPP LABORATORY TESTING - M&P 45-1 Each 1
37 MOBILIZATION - M&P 50-1 Lump-Sum 1
Contract No. 202684021 SQ-2 April 14, 2026
2026 Rehab Phase 1
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
2026 WMD Pipe and Manhole Rehabilitation, Phase 2 Closing date August 18, 2026,
City of Denver
Bid Due: 8/18/2026
Follow Grand Mesa,Uncompahgre,& Gunnison NF FY2026 Steel Culverts - Sol Amnd 1 Active
AGRICULTURE, DEPARTMENT OF
Bid Due: 8/10/2026
2026 WMD Pipe and Manhole Rehabilitation, Phase 2 Closing date August 11, 2026,
City of Denver
Bid Due: 8/11/2026
Follow Grand Mesa,Uncompahgre,& Gunnison NF FY2026 Steel Culverts - Sol Active Contract Opportunity
AGRICULTURE, DEPARTMENT OF
Bid Due: 8/10/2026