2023 Water Main Replacement Project 4

Agency: San Antonio Water System
State: Federal
Type of Government: State & Local
NAICS Category:
  • 237110 - Water and Sewer Line and Related Structures Construction
Posted Date: Sep 25, 2025
Due Date: Mar 31, 2026
Solicitation No: YR
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
2023 Water Main Replacement Project 4

2023 Water Main Replacement Project 4 -2 sites(E Hildebrand & Camden & Euclid)

When Will Work Occur?
Expecting to Advertise in March 31, 2026 and Construction is currently scheduled to begin in mid-2026. It will be procured by Request for Competitive Sealed Proposal method. The estimated construction duration is 15 months and the estimated construction cost is $10.7 million.

E Hildebrand Site

This project site will install approximately 13,300 feet of 8, 10, 12, 16, and 20-inch water main at three sites. One along Camden Street from the intersection with Seymour Street to N St. Mary’s Street. Another along E Euclid Ave from the intersection with N Main Ave to a point approximately 200 feet east of the intersection with McCullough Ave. And another along Hildebrand Ave and Old Hildebrand Ave from the intersection with McCullough Ave to Devine Road. This project is part of ongoing efforts to replace deteriorating water mains that have a history of multiple failures and a high probability of failure.

What to Expect – E Hildebrand Site

  • Open cut installation of approximately 4,500LF of HDPE or DI water main up to 20-inch in diameter at depths of 5 to 10 ft..
  • Trenchless installation of approximately 40LF of water main up to 20-inch in diameter at depths up to 10 feet.
  • Installation and tie-ins/shutdowns will require close coordination with the operators of the SAWS Hildebrand Water Supply Tank.
  • Installation and tie-ins/shutdowns will require close coordination with Trinity University and businesses and residents in the project area.

Camden & Euclid Sites

These project sites will install approximately 13,300 feet of 8, 10, 12, 16, and 20-inch water main at three sites. One along Camden Street from the intersection with Seymour Street to N St. Mary’s Street. Another along E Euclid Ave from the intersection with N Main Ave to a point approximately 200 feet east of the intersection with McCullough Ave. And another along Hildebrand Ave and Old Hildebrand Ave from the intersection with McCullough Ave to Devine Road. This project is part of ongoing efforts to replace deteriorating water mains that have a history of multiple failures and a high probability of failure.

What to Expect – Camden & Euclid Sites

  • Open cut installation of approximately 8,700LF of HDPE or DI water main up to 12-inch in diameter at depths up to 16 feet.
  • Trenchless installation of approximately 160LF of water main up to 12-inch in diameter at depths up to 16 feet.
  • Installation and tie-ins/shutdowns will require close coordination with the Baptist Hospital and other medical service providers in the project area.
  • Installation and tie-ins/shutdowns will require close coordination with businesses and residents in the project area.

SAWS Contract Administration Point of Contact:

Yvonne Rodriguez, Contract Adminstrator

Email: Yvonne.Rodriguez@saws.org

210-233-3105

Notify Me


Receive updates sent straight to your inbox.
Subscribe
Plan Holders List
View plan holders list.
None
Downloads

Not logged in

Contractor Outreach Fact Sheet


Sep. 25, 2025



Questions? Please contact

Yvonne Rodriguez

at 210-233-3105 |

Receive Email Updates |
Registration Agreement

Attachment Preview

Capital Improvement Project Summary:
2023 Water Main Replacement Project 4
About the Project E Hildebrand Site
This project site will install approximately 13,300 feet of 8, 10, 12, 16, and 20-inch water main at three sites. One
along Camden Street from the intersection with Seymour Street to N St. Mary’s Street. Another along E Euclid Ave
from the intersection with N Main Ave to a point approximately 200 feet east of the intersection with McCullough
Ave. And another along Hildebrand Ave and Old Hildebrand Ave from the intersection with McCullough Ave to
Devine Road. This project is part of ongoing efforts to replace deteriorating water mains that have a history of
multiple failures and a high probability of failure.
When Will Work Occur?
Construction is currently scheduled to begin in mid-2026. The overall estimated construction duration is 15
months, and the overall estimated construction cost is $10.7 million.
What to Expect E Hildebrand Site
Open cut installation of approximately
4,500LF of HDPE or DI water main up to 20-
inch in diameter at depths of 5 to 10 ft.
Trenchless installation of approximately 40LF
of water main up to 20-inch in diameter at
depths up to 10 feet.
Installation and tie-ins/shutdowns will
require close coordination with the operators
of the SAWS Hildebrand Water Supply Tank.
Installation and tie-ins/shutdowns will
require close coordination with Trinity
University and businesses and residents in
the project area.
For more information:
Yvonne Rodriguez
SAWS Contracting
210-233-3105
Yvonne.Rodriguez@saws.org
2800 U.S. Hwy. 281 North
San Antonio, TX 78212
210-704-SAWS (7297) saws.org
Capital Improvement Project Summary:
2023 Water Main Replacement Project 4
About the Project Camden & Euclid Sites
These project sites will install approximately 13,300 feet of 8, 10, 12, 16, and 20-inch water main at three sites.
One along Camden Street from the intersection with Seymour Street to N St. Mary’s Street. Another along E Euclid
Ave from the intersection with N Main Ave to a point approximately 200 feet east of the intersection with
McCullough Ave. And another along Hildebrand Ave and Old Hildebrand Ave from the intersection with
McCullough Ave to Devine Road. This project is part of ongoing efforts to replace deteriorating water mains that
have a history of multiple failures and a high probability of failure.
When Will Work Occur?
Construction is currently scheduled to begin in mid-2026. The overall estimated construction duration is 15
months, and the overall estimated construction cost is $10.7 million.
What to Expect Camden & Euclid Sites
Open cut installation of approximately
8,700LF of HDPE or DI water main up to 12-
inch in diameter at depths up to 16 feet.
Trenchless installation of approximately
160LF of water main up to 12-inch in
diameter at depths up to 16 feet.
Installation and tie-ins/shutdowns will
require close coordination with the Baptist
Hospital and other medical service providers
in the project area.
Installation and tie-ins/shutdowns will
require close coordination with businesses
and residents in the project area.
For more information:
Yvonne Rodriguez
SAWS Contracting
210-233-3105
Yvonne.Rodriguez@saws.org
2800 U.S. Hwy. 281 North
San Antonio, TX 78212
210-704-SAWS (7297) saws.org
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

2023 Water Main Replacement Project 4 Solicitation No. CO-00907-RL Status: Currently Accepting Submissions

San Antonio Water System

Bid Due: 6/16/2026

2023 Water Main Replacement Project 4 Solicitation No. CO-00907-RL Status: Currently Accepting Submissions

San Antonio Water System

Bid Due: 6/12/2026

Follow Z1DA--Replace Electrical Primary Distribution 515-15-117 Active Contract Opportunity Notice ID 36C25025B0047 Related

VETERANS AFFAIRS, DEPARTMENT OF

Bid Due: 6/18/2026

Site Improvements at the C.A. Fredd Campus for Shelton State Community College (SSCC)

Goodwyn Mills Cawood(GMC)

Bid Due: 6/11/2026