2027 Wake Primary Resurfacing

Agency: Division of Highways
State: North Carolina
Type of Government: State & Local
Posted Date: Jul 22, 2026
Due Date: Aug 12, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description

Attachment Preview

DE00428 Wake County
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
HIGHWAY DIVISION 5
PROPOSAL
DATE AND TIME OF BID OPENING: August 12, 2026 AT 2:00 PM
CONTRACT ID: DE00428
WBS ELEMENT NO.: 2027CPT.05.01.10921
FEDERAL AID NO.: STATE FUNDED
COUNTY: Wake County
TIP NO.: N/A
MILES: 8.877
ROUTE NO.: VARIOUS
LOCATION: VARIOUS PRIMARY ROUTES IN WAKE COUNTY
TYPE OF WORK: RESURFACING
NOTICE:
ALL BIDDERS SHALL COMPLY WITH ALL APPLICABLE LAWS REGULATING THE PRACTICE OF
GENERAL CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE GENERAL STATUTES OF
NORTH CAROLINA WHICH REQUIRES THE BIDDER TO BE LICENSED BY THE N.C. LICENSING
BOARD FOR CONTRACTORS WHEN BIDDING ON ANY NON-FEDERAL AID PROJECT WHERE THE
BID IS $40,000 OR MORE, EXCEPT FOR CERTAIN SPECIALTY WORK AS DETERMINED BY THE
LICENSING BOARD. BIDDERS SHALL ALSO COMPLY WITH ALL OTHER APPLICABLE LAWS
REGULATING THE PRACTICES OF ELECTRICAL, PLUMBING, HEATING AND AIR
CONDITIONING AND REFRIGERATION CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE
GENERAL STATUTES OF NORTH CAROLINA. NOTWITHSTANDING THESE LIMITATIONS ON
BIDDING, THE BIDDER WHO IS AWARDED ANY FEDERAL - AID FUNDED PROJECT SHALL
COMPLY WITH CHAPTER 87 OF THE GENERAL STATUTES OF NORTH CAROLINA FOR
LICENSING REQUIREMENTS WITHIN 60 CALENDAR DAYS OF BID OPENING.
THIS IS A ROADWAY PROJECT. BID BOND IS REQUIRED.
NAME OF BIDDER
ADDRESS OF BIDDER

DE00428 Wake County
PROPOSAL FOR THE CONSTRUCTION OF
CONTRACT No. DE00428 IN WAKE COUNTY, NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION,
RALEIGH, NORTH CAROLINA
The Bidder has carefully examined the location of the proposed work to be known as Contract No. DE00428; has carefully
examined the plans and specifications, which are acknowledged to be part of the proposal, the special provisions, the
proposal, the form of contract, and the forms of contract payment bond and contract performance bond; and thoroughly
understands the stipulations, requirements and provisions. The undersigned bidder agrees to bound upon his execution of
the bid and subsequent award to him by the Department of Transportation in accordance with this proposal to provide the
necessary contract payment bond and contract performance bond within fourteen days after the written notice of award is
received by him. The undersigned Bidder further agrees to provide all necessary machinery, tools, labor, and other means
of construction; and to do all the work and to furnish all materials, except as otherwise noted, necessary to perform and
complete the said contract in accordance with the 2024 Standard Specifications for Roads and Structures by the dates(s)
specified in the Project Special Provisions and in accordance with the requirements of the Engineer, and at the unit or lump
sum prices, as the case may be, for the various items given on the sheets contained herein.
The Bidder shall provide and furnish all the materials, machinery, implements, appliances and tools, and perform the work
and required labor to construct and complete Contract No. DE00428 in Wake County, for the unit or lump sum prices, as
the case may be, bid by the Bidder in his bid and according to the proposal, plans, and specifications prepared by said
Department, which proposal, plans, and specifications show the details covering this project, and hereby become a part of
this contract.
The published volume entitled North Carolina Department of Transportation, Raleigh, Standard Specifications for Roads
and Structures, January 2024 with all amendments and supplements thereto, is by reference incorporated into and made
a part of this contract; that, except as herein modified, all the construction and work included in this contract is to be done
in accordance with the specifications contained in said volume, and amendments and supplements thereto, under the
direction of the Engineer.
If the proposal is accepted and the award is made, the contract is valid only when signed either by the Contract Officer or
such other person as may be designated by the Secretary to sign for the Department of Transportation. The conditions and
provisions herein cannot be changed except over the signature of the said Contract Officer or Division Engineer.
The quantities shown in the itemized proposal for the project are considered to be approximate only and are given as the
basis for comparison of bids. The Department of Transportation may increase or decrease the quantity of any item or portion
of the work as may be deemed necessary or expedient.
An increase or decrease in the quantity of an item will not be regarded as sufficient ground for an increase or decrease in the
unit prices, nor in the time allowed for the completion of the work, except as provided for the contract.
Accompanying this bid is a bid bond secured by a corporate surety, or certified check payable to the order of the Department
of Transportation, for five percent of the total bid price, which deposit is to be forfeited as liquidated damages in case this
bid is accepted and the Bidder shall fail to provide the required payment and performance bonds with the Department of
Transportation, under the condition of this proposal, within 14 calendar days after the written notice of award is received by
him, as provided in the Standard Specifications; otherwise said deposit will be returned to the Bidder.

DE00428 Wake County
TABLE OF CONTENTS
COVER SHEET
PROPOSAL SHEET
PROJECT SPECIAL PROVISIONS
BOND REQUIREMENTS: ........................................................................................................ G-1
HAUL ROADS: .......................................................................................................................... G-1
CONTRACT TIME AND LIQUIDATED DAMAGES: ........................................................... G-1
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES: ....... G-2
INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ....... G-2
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES: ....... G-1
INTERMEDIATE CONTRACT TIME NUMBER 4 AND LIQUIDATED DAMAGES: ....... G-3
PROSECUTION OF WORK:..................................................................................................... G-4
MAJOR CONTRACT ITEMS: .................................................................................................. G-4
SPECIALTY ITEMS: ................................................................................................................. G-4
FUEL PRICE ADJUSTMENT: .................................................................................................. G-4
SCHEDULE OF ESTIMATED COMPLETION PROGRESS: ................................................. G-6
MINORITY BUSINESS ENTERPRISE AND WOMEN BUSINESS ENTERPRISE
(DIVISIONS): ............................................................................................................................. G-6
RESTRICTIONS ON ITS EQUIPMENT AND SERVICES: .................................................. G-21
USE OF UNMANNED AIRCRAFT SYSTEM (UAS): .......................................................... G-22
EQUIPMENT IDLING GUIDELINES: ................................................................................... G-22
ELECTRONIC BIDDING: ....................................................................................................... G-23
OUTSOURCING OUTSIDE THE USA: ................................................................................. G-23
ROADWAY .................................................................................................................................R-1
STANDARD SPECIAL PROVISIONS
AVAILABILITY OF FUNDS - TERMINATION OF CONTRACTS ..................................SSP-1
ERRATA..................................................................................................................................SSP-2
PLANT AND PEST QUARANTINES ...................................................................................SSP-5
MINIMUM WAGES ...............................................................................................................SSP-6
TITLE VI AND NONDISCRIMINATION: ...........................................................................SSP-7
ON-THE-JOB TRAINING ....................................................................................................SSP-16
UNIT PROJECT SPECIAL PROVISIONS
TRAFFIC CONTROL .............................................................................................................. TC-1
PROPOSAL ITEM SHEET
ITEM SHEET(S)

DE00428 Wake County
INSTRUCTIONS TO BIDDERS
PLEASE READ ALL INSTRUCTIONS CAREFULLY
BEFORE PREPARING AND SUBMITTING YOUR BID.
All bids shall be prepared and submitted in accordance with the following requirements.
Failure to comply with any requirement may cause the bid to be considered irregular and
may be grounds for rejection of the bid.
For preparing and submitting the bid electronically, refer to Subarticle 102-8(B) of the Standard
Specifications.
Bidders that bid electronically on Raleigh Central-Let projects will need a separate request to bid
from the approved electronic bidding website for Division Contracts.
ELECTRONIC ON-LINE BID:
1. Plans and the proposal can be found on the Connect NCDOT website.
2. In accordance with Subarticle 102-8(B)(1) of the Standard Specifications, obtain an account
and valid Digital Signature to bid with Bid Express (bidx.com)
3. In accordance with Subarticle 102-8(B)(3) of the Standard Specifications, if bid bond is
required and bid deposit is not chosen register bond with Surety2000 or Tinubu and submit
with the online bid.
4. In accordance with Article 102-3 of the Standard Specifications, registration on the Interested
Parties List is required unless SP1 G02 Interested Parties List Not Required provision is
included in the proposal.
5. Prepare and submit a bid electronically using the approved electronic bidding provider website.
4. Electronic bidding website necessary for electronic bidding can be found on the Bid Express
website following the directions at: https://connect.ncdot.gov/letting/Pages/Electronic-
Bidding.aspx.
5. Questions should be emailed 7 calendar days prior to the bid opening to Kayla N. Cooper at
kncooper@ncdot.gov. Contact with any other NCDOT personnel concerning this project is
strictly prohibited, unless otherwise noted, and may result in bids being considered non-
responsive.

DE00428 G-1 Wake County
PROJECT SPECIAL PROVISIONS
GENERAL
BOND REQUIREMENTS:
(6-1-16)(Rev.1-16-24) 102-8, 102-10 SPD 01-420A
A Bid Bond is required in accordance with Article 102-10 of the Standard Specifications for Roads
and Structures.
Contract Payment and Performance Bonds are required in accordance with Article 103-7 of the
Standard Specifications.
HAUL ROADS:
(7-16-24) 105 SP1 G04
Revise the Standard Specifications as follows:
Page 1-45, Article 105-15 RESTRICTION OF LOAD LIMITS, line 31, add the following after
second sentence of the second paragraph:
At least 30 days prior to use, the Contractor shall notify the Engineer of any public road proposed
for use as a haul road for the project.
CONTRACT TIME AND LIQUIDATED DAMAGES:
(7-1-95) (Rev. 12-18-07) 108 SP1 G10 A
The date of availability for this contract is September 12, 2026.
The completion date for this contract is April 30, 2028.
Except where otherwise provided by the contract, observation periods required by the contract will
not be a part of the work to be completed by the completion date and/or intermediate contract times
stated in the contract. The acceptable completion of the observation periods that extend beyond
the final completion date shall be a part of the work covered by the performance and payment
bonds.
The liquidated damages for this contract are One Thousand Six Hundred Dollars ($ 1,600.00)
per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES:
(6-18-13) 108 SP1 G14 K
The Contractor shall complete the work required of NC 42 as shown on 3 and shall place and
maintain traffic on same.
The date of availability for this intermediate contract time is September 12, 2026.
The completion date for this intermediate contract time is December 15, 2026.

DE00428 G-2 Wake County
The liquidated damages are Two Thousand Five Hundred Dollars ($ 2,500.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES:
(2-20-07) 108 SP1 G14 A
The Contractor shall complete the required work of installing, maintaining, and removing the
traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The
Contractor shall not close or narrow a lane of traffic on ALL MAPS during the following time
restrictions:
DAY AND TIME RESTRICTIONS
MONDAY THRU FRIDAY
6:00AM TO 9:00AM
4:00PM TO 7:00PM
In addition, the Contractor shall not close or narrow a lane of traffic on ALL MAPS, detain and/or
alter the traffic flow on or during holidays, holiday weekends, special events, or any other time
when traffic is unusually heavy, including the following schedules:
HOLIDAY AND HOLIDAY WEEKEND LANE CLOSURE RESTRICTIONS
1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the
Engineer.
2. For New Year's Day, between the hours of 7:00PM December 31st and 6:00AM
January 2nd. If New Year's Day is on a Friday, Saturday, Sunday or Monday, then until
6:00AM the following Tuesday.
3. For Easter, between the hours of 7:00PM Thursday and 6:00AM Monday.
4. For Memorial Day, between the hours of 7:00PM Friday and 6:00AM Tuesday.
5. For Independence Day, between the hours of 7:00PM the day before Independence Day
and 6:00AM the day after Independence Day.
If Independence Day is on a Friday, Saturday, Sunday or Monday, then between the hours
of 7:00PM the Thursday before Independence Day and 6:00AM the Tuesday after
Independence Day.
6. For Labor Day, between the hours of 7:00PM Friday and 6:00AM Tuesday.
7. For Thanksgiving Day, between the hours of 7:00PM Tuesday and 6:00AM Monday.
8. For Christmas, between the hours of 7:00PM the Friday before the week of Christmas
Day and 6:00AM the following Tuesday after the week of Christmas Day.

DE00428 G-3 Wake County
Holidays and holiday weekends shall include New Year's, Easter, Memorial Day, Independence
Day, Labor Day, Thanksgiving, and Christmas. The Contractor shall schedule his work so that
lane closures will not be required during these periods, unless otherwise directed by the Engineer.
The time of availability for this intermediate contract work shall be the time the Contractor begins
to install all traffic control devices for lane closures according to the time restrictions listed herein.
The completion time for this intermediate contract work shall be the time the Contractor is required
to complete the removal of all traffic control devices for lane closures according to the time
restrictions stated above and place traffic in the existing traffic pattern.
The liquidated damages are Two Hundred Fifty Dollars ($ 250.00) per hour.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES:
(5-21-13) 108 SP1 G14 I
The Contractor shall complete the work required of installing each new inductive loop after the
removal of each existing loop by the milling, patching or resurfacing operations and shall place
and maintain traffic on same.
The date of availability for this intermediate contract time for each inductive loop installation will
be the date when the Contractor elects to disturb the existing inductive loop.
The completion date for this intermediate contract time for each inductive loop installation will be
the date which is seven (7) consecutive calendar days after the date of availability.
The liquidated damages are Five Hundred Dollars ($ 500.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 4 AND LIQUIDATED DAMAGES:
(9-21-21) 108 SP1 G14 M
For each curb ramp location on a continuous pedestrian facility, the Contractor shall complete
all work required of that curb ramp location as shown in the plans.
The date of availability for each individual intermediate contract time is the date when the
Contractor elects to sever the existing continuous pedestrian facility.
The completion date for each individual intermediate contract time is the date which is seven (7)
consecutive calendar days after and including the date of availability.
For each curb ramp location on a continuous pedestrian facility, the liquidated damages are
Two Hundred and Fifty Dollars ($ 250.00) per calendar day.

DE00428 G-4 Wake County
PROSECUTION OF WORK:
(7-1-95) (Rev. 8-21-12) 108 SP1 G15R
The Contractor will be required to prosecute the work in a continuous and uninterrupted manner
from the time he begins the work until completion and final acceptance of the project. The
Contractor will not be permitted to suspend his operations except for reasons beyond his control
or except where the Engineer has authorized a suspension of the Contractor's operations in writing.
In the event that the Contractor's operations are suspended in violation of the above provisions, the
sum of $ 500.00 will be charged the Contractor for each and every calendar day that such
suspension takes place. The said amount is hereby agreed upon as liquidated damages due to extra
engineering and maintenance costs and due to increased public hazard resulting from a suspension
of the work. Liquidated damages chargeable due to suspension of the work will be additional to
any liquidated damages that may become chargeable due to failure to complete the work on time.
MAJOR CONTRACT ITEMS:
(2-19-02)(Rev. 1-16-24) 104 SP1 G28
The following listed items are the major contract items for this contract (see Article 104-5 of the
Standard Specifications):
Line # Description
8 ASPHALT CONCRETE SURFACE COURSE, TYPE S9.5C
21 THERMOPLASTIC PAVEMENT MARKING LINES (6", 90 MILS)
SPECIALTY ITEMS:
(7-1-95)(Rev. 1-16-24) 108-6 SP1 G37
Items listed below will be the specialty items for this contract (see Article 108-6 of the
Standard Specifications).
Line # Description
21-26 Long-Life Pavement Markings
27 Permanent Pavement Markers
28 Signals/ITS System
FUEL PRICE ADJUSTMENT:
(11-15-05)(Rev. 1-16-24) 109-8 SP1 G43
Page 1-82, Article 109-8, FUEL PRICE ADJUSTMENTS, add the following:
The base index price for DIESEL #2 FUEL is $ 3.3565 per gallon. Where any of the following
are included as pay items in the contract, they will be eligible for fuel price adjustment.

Description Units Fuel Usage Factor Diesel
Unclassified Excavation Gal/CY 0.29
Borrow Excavation Gal/CY 0.29
Class IV Subgrade Stabilization Gal/Ton 0.55
Aggregate Base Course Gal/Ton 0.55
Sub-Ballast Gal/Ton 0.55
Erosion Control Stone Gal/Ton 0.55
Rip Rap, Class _____ Gal/Ton 0.55
Asphalt Concrete Base Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Intermediate Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Open-Graded Asphalt Friction Course Gal/Ton 0.90 or 2.90
Permeable Asphalt Drainage Course, Type ____ Gal/Ton 0.90 or 2.90
Sand Asphalt Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Ultra-thin Bonded Wearing Course Gal/Ton 0.90 or 2.90
Aggregate for Cement Treated Base Course Gal/Ton 0.55
Portland Cement for Cement Treated Base Course Gal/Ton 0.55
> 11" Portland Cement Concrete Pavement Gal/SY 0.327
Concrete Shoulders Adjacent to > 11" Pavement Gal/SY 0.327
9" to 11" Portland Cement Concrete Pavement Gal/SY 0.272
Concrete Shoulders Adjacent to 9" to 11" Pavement Gal/SY 0.272
< 9" Portland Cement Concrete Pavement Gal/SY 0.245
Concrete Shoulders Adjacent to < 9" Pavement Gal/SY 0.245

DE00428 G-5 Wake County
The pay items and the fuel factor used in calculating adjustments to be made will be as follows:
Description Units Fuel Usage
Factor Diesel
Unclassified Excavation Gal/CY 0.29
Borrow Excavation Gal/CY 0.29
Class IV Subgrade Stabilization Gal/Ton 0.55
Aggregate Base Course Gal/Ton 0.55
Sub-Ballast Gal/Ton 0.55
Erosion Control Stone Gal/Ton 0.55
Rip Rap, Class _____ Gal/Ton 0.55
Asphalt Concrete Base Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Intermediate Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Open-Graded Asphalt Friction Course Gal/Ton 0.90 or 2.90
Permeable Asphalt Drainage Course, Type ____ Gal/Ton 0.90 or 2.90
Sand Asphalt Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Ultra-thin Bonded Wearing Course Gal/Ton 0.90 or 2.90
Aggregate for Cement Treated Base Course Gal/Ton 0.55
Portland Cement for Cement Treated Base Course Gal/Ton 0.55
> 11" Portland Cement Concrete Pavement Gal/SY 0.327
Concrete Shoulders Adjacent to > 11" Pavement Gal/SY 0.327
9" to 11" Portland Cement Concrete Pavement Gal/SY 0.272
Concrete Shoulders Adjacent to 9" to 11" Pavement Gal/SY 0.272
< 9" Portland Cement Concrete Pavement Gal/SY 0.245
Concrete Shoulders Adjacent to < 9" Pavement Gal/SY 0.245
For the asphalt items noted in the chart as eligible for fuel adjustments, the bidder may include
the Fuel Usage Factor Adjustment Form with their bid submission if they elect to use the fuel
usage factor. The Fuel Usage Factor Adjustment Form is found at the following link:
https://connect.ncdot.gov/letting/LetCentral/Fuel%20Usage%20Factor%20Adjustment%20Form
%20-%20%20Starting%20Nov%202022%20Lettings.pdf
Select either 2.90 Gal/Ton fuel factor or 0.90 Gal/Ton fuel factor for each asphalt line item on
the Fuel Usage Factor Adjustment Form. The selected fuel factor for each asphalt item will
remain in effect for the duration of the contract.
Failure to complete the Fuel Usage Factor Adjustment Form will result in using 2.90 gallons per
ton as the Fuel Usage Factor for Diesel for the asphalt items noted above. The contractor will
not be permitted to change the Fuel Usage Factor after the bids are submitted.

Fiscal Year Progress (% of Dollar Value)
2027 (7/01/26 - 6/30/27) 60% of Total Amount Bid
2028 (7/01/27 - 6/30/28) 40% of Total Amount Bid

DE00428 G-6 Wake County
SCHEDULE OF ESTIMATED COMPLETION PROGRESS:
(7-15-08)(Rev. 6-16-26) 108-2 SP1 G58
The Contractor's attention is directed to the Standard Special Provision entitled Availability of
Funds Termination of Contracts included elsewhere in this proposal. The Department of
Transportation's schedule of estimated completion progress for this project as required by that
Standard Special Provision is as follows:
Fiscal Year Progress (% of Dollar Value)
2027 (7/01/26 - 6/30/27) 60% of Total Amount Bid
2028 (7/01/27 - 6/30/28) 40% of Total Amount Bid
The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of
the Standard Specifications. Any acceleration of the progress as shown by the Contractor's
progress schedule over the progress as shown above shall be subject to the approval of the
Engineer.
MINORITY BUSINESS ENTERPRISE AND WOMEN BUSINESS ENTERPRISE
(DIVISIONS):
(10-16-07)(Rev. 10-21-25) 102-15(J) SP1 G67
Description
The purpose of this Special Provision is to carry out the North Carolina Department of
Transportation's policy of ensuring nondiscrimination in the award and administration of contracts
financed in whole or in part with State funds.
Definitions
Additional MBE/WBE Subcontractors - Any MBE/WBE submitted at the time of bid that will not
be used to meet the Combined MBE/WBE goal. No submittal of a Letter of Intent is required.
Combined MBE/WBE Goal: A portion of the total contract, expressed as a percentage that is to
be performed by committed MBE/WBE subcontractors.
Committed MBE/WBE Subcontractor - Any MBE/WBE submitted at the time of bid that is being
used to meet the Combined MBE / WBE goal by submission of a Letter of Intent. Or any MBE
or WBE used as a replacement for a previously committed MBE or WBE firm.
Contract Goal Requirement - The approved participation at time of award, but not greater than the
advertised Combined MBE/WBE contract goal.
Goal Confirmation Letter - Written documentation from the Department to the bidder confirming
the Contractor's approved, committed participation along with a listing of the committed MBE and
WBE firms.
Manufacturer - A firm that owns (or leases) and operates or maintains a factory or establishment
that produces on the premises, the materials or supplies obtained by the Contractor. A firm that
makes minor modifications to the materials, supplies, articles, or equipment is not a manufacturer.

This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Follow Wheat DNA Library Sequencing Active Contract Opportunity Notice ID 127EAV26Q0125 Related Notice

AGRICULTURE, DEPARTMENT OF

Due by 9/21/2026

Notice of Qualifications of Bidders for Transylvania County Courthouse Courthouse Engineering RFQ Advertisement

Transylvania County

Due by 9/23/2026

Follow Wheat DNA Library Sequencing Active Contract Opportunity Notice ID 127EAV26Q0125 Related Notice

AGRICULTURE, DEPARTMENT OF

Due by 9/21/2026

Solicitation Number: SCO-24-27698-01B Project Title: NC Department of Natural and Cultural Resources Description:

State Government of North Carolina

Due by 9/29/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.