Tustin Legacy Linear Park - Phase 3 Between Armstrong to Warner (CIP No. 20083)

Agency: City of Tustin
State: California
Type of Government: State & Local
Posted Date: Oct 28, 2026
Due Date: Dec 10, 2026
Solicitation No: CIP 20083
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description


Project ID: CIP 20083

Title: Tustin Legacy Linear Park - Phase 3 Between Armstrong to Warner (CIP No. 20083)

Addenda: 0

Release Date: 10/28/2026

Due Date: 12/10/2026

Follow
Tustin Legacy Linear Park - Phase 3 Between Armstrong to Warner (CIP No. 20083)
Invitation for Bids
Public Works
Project ID: CIP 20083
Release Date: Wednesday, October 28, 2026
· Due Date: Thursday, December 10, 2026 2:00pm
Posted Wednesday, October 28, 2026 5:35pm
All dates & times in Pacific Time - Los Angeles
Draft Response Events RSVP No Bid
Time Remaining: 42 days, 20 hours, 18 minutes


Post Information

Posted At:Wed, Oct 28, 2026 5:35 PM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

NOTICE IS HEREBY GIVEN that the CITY OF TUSTIN, hereinafter referred to as City or AGENCY invites sealed bids for the above stated project and will receive sealed bids for the construction, materials, supplies, equipment and/or services set forth herein, subject to all conditions outlined in the Bid Package. Scope of Work: The work consists of furnishing all labor, tools, transportation, equipment, materials and incidentals for construction of the following, including site work and excavaion, electrical, instrumentation, landscaping / irrigation improvements, plumbing, street improvements, restoration of adjacent properties, and appurtenant work. Project scope: Main 12' multi-modal path to match existing park. Secondary 6' walking trail to match existing park. Playground, fitness pods, and art pads. Planted mounds on Armstrong Ave. and Warner Ave. side of park. Event lawn. Hardscape and planting extent as shown on hardscape plans. Other project elements include rocky bluff zone with decorative boulders and boulder seats, shade plaza with metal shade canopies. Paving includes concrete, stabilized decomposed granite for paths, PIP rubber for playground, and concrete pavers for Esplanade along Compass Ave. Planting includes trees, shrub, perennial mixes and turf sod. Stormwater strategies include planted bioretention swale. Lighting includes pedestrian lights along walkways, street lighting and tree uplights.



Background

Project Schedule (contract days): 190

Engineer’s Estimate: $ 11,100,000

Liquidated Damages: $ 8,800 per calendar day

Bid Valid (calendar days): 60

Contractor's License(s): Class A



Timeline

Advertisement/Release Project Date:
October 28, 2026
Pre-Bid Meeting (Non-Mandatory):
November 5, 2026, 10:00am
Site-Walk Through
Question Submission Deadline:
November 20, 2026, 5:00pm
Bid Opening:
December 10, 2026, 2:00pm
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Follow Cowboy Hat Stewardship IRSC - Lake Tahoe Basin Management Unit Active Contract

AGRICULTURE, DEPARTMENT OF

Due by 11/02/2026

2026 - Fire - RFP Hazard Mitigation Plan Start Date: 09/16/2026 Close Date:

City of Compton

Due by 10/29/2026

Event Name Business Unit Event ID Event Format Event Type Ends In Start

County of Sonoma

Due by 11/24/2026

Follow Request for Offer for RADMAC III Parcel E Remedial Action Active Contract

DEPT OF DEFENSE

Due by 11/03/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.