2026 Terminal St Pump Sta Rehab Project

Agency: City of Dubuque, IA
State: Iowa
Type of Government: State & Local
NAICS Category:
  • 236220 - Commercial and Institutional Building Construction
  • 237110 - Water and Sewer Line and Related Structures Construction
  • 237990 - Other Heavy and Civil Engineering Construction
  • 238990 - All Other Specialty Trade Contractors
Posted Date: Apr 21, 2026
Due Date: May 21, 2026
Solicitation No: 5581500023
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description

Bid Number: 5581500023
Bid Title: 2026 Terminal St Pump Sta Rehab Project
Category: Water & Resource Recovery Center
Status: Open
Publication Date/Time:
4/21/2026 5:00 PM
Closing Date/Time:
5/21/2026 2:00 PM
Related Documents:

Attachment Preview

2026 Terminal
Street Pumping
Station
Rehabilitation
IDNR SRF File:
CS1921150 01
IDNR Project:
W2024-0302A
City of (IA)\1154.105.W2024-
R:\MAD\Documents\Specifications\Active\Dubuque,
0302A.RJL\Specifications\!Mosaic Cover (Periwinkle=Wastewater).docx

PLAN HOLDER: Set No.:
PROJECT MANUAL
CITY OF DUBUQUE
DUBUQUE, IOWA
2026 TERMINAL STREET PUMPING STATION REHABILITATION
IDNR SRF FILE: CS1921150 01
IDNR PROJECT: W2024-0302A
Prepared by:
STRAND ASSOCIATES, INC.(R)
910 West Wingra Drive
Madison, WI 53715
www.strand.com
Issued for Bid
April21, 2026

SECTION 00 01 10
TABLE OF CONTENTS
CITY OF DUBUQUE
DUBUQUE, IOWA
2026 TERMINAL STREET PUMPING STATION REHABILITATION
IDNR SRF FILE: CS1921150 01
IDNR PROJECT: W2024-0302A
Pages
Through
DIVISION 00-BIDDING AND CONTRACTING REQUIREMENTS
NOTICE TO BIDDERS................................................................................................... 3
NOTICE OF HEARING................................................................................................... 1
INSTRUCTIONS TO BIDDERS...................................................................................... 00 21 13-14
BID................................................................................................................................. 00 41 00-11
BID BOND...................................................................................................................... 00 43 13- 2
BIDDER STATUS FORM................................................................................................ 00 43 14- 2
SRF REQUIRED FRONT-END SPECIFICATIONS........................................................ 21
AGREEMENT................................................................................................................. 00 52 00-11
NOTICE TO PROCEED.................................................................................................. 00 55 00- 1
PERFORMANCE, PAYMENT AND MAINTENANCE BOND........................................... 00 60 00- 5
OUT-OF-STATE CONTRACTOR BOND........................................................................ 00 60 10- 1
GENERAL CONDITIONS............................................................................................... 00 72 00-81
SALES AND USE TAX EXEMPTION CERTIFICATE...................................................... 5
INSURANCE SCHEDULE F........................................................................................... 6
SPECIFICATIONS
DIVISION 01-GENERAL REQUIREMENTS
SUMMARY OF WORK................................................................................................... 01 11 00- 6
CONTRACT CONSIDERATIONS................................................................................... 01 29 00- 2
COORDINATION, FIELD ENGINEERING, AND MEETINGS......................................... 01 31 00- 3
SUBMITTALS................................................................................................................. 01 33 00-10
REGULATORY REQUIREMENTS.................................................................................. 01 41 00- 2
REFERENCE STANDARDS AND DEFINITIONS........................................................... 01 42 00- 6
QUALITY CONTROL...................................................................................................... 01 45 00- 2
TEMPORARY FACILITIES............................................................................................. 01 50 00- 3
FIELD OFFICES AND SHEDS....................................................................................... 01 52 13- 2
TEMPORARY CONTROLS............................................................................................ 01 57 00- 2
MATERIALS AND EQUIPMENT..................................................................................... 01 60 00- 4
CUTTING, PATCHING, AND ALTERATIONS................................................................ 01 73 29- 6
CONTRACT CLOSEOUT............................................................................................... 01 77 00- 3
STARTING OF SYSTEMS.............................................................................................. 01 91 00- 7
FEDERAL WAGE RATES.............................................................................................. 9
Section 00 01 10-1
1154.105/W2024-0302A

TABLE OF CONTENTS Continued
Pages
Through
DIVISION 02-EXISTING CONDITIONS
DEMOLITION................................................................................................................. 02 41 00- 3
DIVISION 05-METALS
STRUCTURAL STEEL................................................................................................... 05 12 00- 5
HANDRAILS AND RAILINGS......................................................................................... 05 52 00- 2
FLOOR PLATES............................................................................................................. 05 53 00- 2
POST-INSTALLED ANCHORS....................................................................................... 05 56 00- 3
DIVISION 06-WOOD, PLASTICS, AND COMPOSITES
WOOD BLOCKING AND CURBING............................................................................... 06 11 10- 2
DIVISION 07-THERMAL AND MOISTURE PROTECTION
SINGLE-PLY ROOFING-FULLY ADHERED.................................................................. 07 53 00- 4
PREPARATION FOR REROOFING............................................................................... 07 56 01- 1
FLASHING AND SHEET METAL.................................................................................... 07 62 00- 3
MANUFACTURED ROOF SPECIALTIES....................................................................... 07 71 00- 2
GUTTERS AND DOWNSPOUTS................................................................................... 07 71 23- 2
CAULKING AND SEALANTS......................................................................................... 07 90 00- 2
DIVISION 08-OPENINGS
FIBERGLASS DOORS AND FRAMES........................................................................... 08 22 10- 3
DOOR HARDWARE....................................................................................................... 08 71 00- 3
DIVISION 09-FINISHES
PAINTING....................................................................................................................... 09 91 00- 8
DIVISION 26-ELECTRICAL
GENERAL ELECTRICAL REQUIREMENTS.................................................................. 26 05 00- 9
WIRE.............................................................................................................................. 26 05 19- 6
INSTRUMENT AND COMMUNICATION WIRE AND CABLE......................................... 26 05 23- 3
SECONDARY GROUNDING.......................................................................................... 26 05 26- 2
SUPPORTING DEVICES............................................................................................... 26 05 29- 2
CONDUIT....................................................................................................................... 26 05 33- 7
BOXES........................................................................................................................... 26 05 35- 3
ELECTRICAL IDENTIFICATION.................................................................................... 26 05 53- 5
MOTOR CONTROL........................................................................................................ 26 24 19- 4
WIRING DEVICES.......................................................................................................... 26 27 26- 2
OVERCURRENT PROTECTIVE DEVICES.................................................................... 26 28 00- 2
DISCONNECT SWITCHES............................................................................................ 26 28 16- 2
Section 00 01 10-2
1154.105/W2024-0302A

TABLE OF CONTENTS Continued
Pages
Through
DIVISION 33-UTILITIES
SEWER BYPASS PUMPING.......................................................................................... 33 01 31- 3
DIVISION 40-PROCESS INTERCONNECTIONS
ACTUATORS FOR PROCESS VALVES AND GATES................................................... 40 05 57- 4
SLUICE GATES.............................................................................................................. 40 05 59.20- 5
DIVISION 41-MATERIAL PROCESSING AND HANDLING EQUIPMENT
HOISTS AND CRANES.................................................................................................. 41 22 23- 4
APPENDICES (NOT PART OF CONTRACT DOCUMENTS)
ASBESTOS CONTAINING MATERIALS INSPECTION.................................................. 26
END OF SECTION
Section 00 01 10-3
1154.105/W2024-0302A

BIDDING AND CONTRACTING REQUIREMENTS

NOTICE TO BIDDERS
CITY OF DUBUQUE PUBLIC IMPROVEMENT PROJECT
2026TERMINAL STREET PUMPING STATION REHABILITATION
IDNR SRF FILE: CS1921150 01
IDNR PROJECT: W2024-0302A
Time and Place for Filing Sealed Proposals. Sealed Bids for the work
comprising each improvement as stated below must be filed before 2 P.M. on
Thursday, May 21, 2026, in the Office of the City Clerk, City Hall-First Floor,
50 West 13th Street, Dubuque, IA 52001.
Time and Place Sealed Proposals Will be Opened and Considered. Sealed
Proposals will be opened and Bids tabulated at 2 P.M. on Thursday,
May 21, 2026, at City Hall-Conference Room A, 50 West 13th Street,
Dubuque, IA, 52001, for consideration by the City Council (Council) on Monday,
June1, 2026, at theHistoric Federal Building, 350 W. 6thSt, Second Floor Council
Chambers, Dubuque, IA52001,or at such later date as may be set at said meeting.
The City of Dubuque, Iowa, reserves the right to reject any and all Bids.
Time for Commencement and Completion of Work. Work shall be commenced
after Notice to Proceed has been issued. Work on theProject shall be substantially
completed by March 26, 2027, with final completion by April 30, 2027, in
accordance with the requirements listed in the Agreement.
Bid Security. Each Bidder shall accompany its Bid with bid security as defined in
Iowa Code Section 26.8, as security that the successful Bidder will enter into a
Contract for the work bid upon. The Bidder's security shall be in the amount of
10 percent (10%) of the amount of the Contract, as fixed in the Instructions to
Bidders and shall be in the form of a cashier's check or a certified check drawn on
an FDIC insured bank in Iowa or on a FDIC insured bank chartered under the laws
of the United States; or a certified share draft drawn on a credit union in Iowa or
chartered under the laws of the United States; or a Bid Bond on the form provided
in the Contract Documents with corporate surety satisfactory to the City of
Dubuque. The Bid shall contain no condition except as provided in the
Specifications.
Contract Documents. Bids are to be addressed to the City of Dubuque, Iowa,
50 West 13th Street, Dubuque, IA 52001, and shall be marked
"Sealed Bid-2026 Terminal Street Pumping Station Rehabilitation,
IDNR SRF File: CS1921150 01; IDNR Project: W2024-0302A.
A copy of the Contract Documents may be viewed at the City Clerk's Office,
City Hall, 50 West 13th Street, Dubuque, IA 52001. Complete digital Contract
Documents will also be available, for download on the City's website at
www.cityofdubuque.org/bids.aspx. No plan deposit is required.
1of3
4908-2825-2830\2

Bidder will execute and file the Agreement and 100% Performance, Payment, and
Maintenance Bond within 15 days after the Notice of Award.
The City of Dubuque reserves the right to reject any or all Bids, to waive any
technicality, and to accept any Bid which it deems advantageous. All Bids shall
remain subject to acceptance for 60 days after the time set for receiving Bids.
Contract award shall be made based on the lowest responsive and responsible
Bidder.
Any Contract or Contracts to be awarded are expected to be funded entirely or in
part bya loan from IowaCleanWater State Revolving Fund. This procurement will
be subject to regulations contained in appropriate State Statutes and 40 CFR
Parts 31, 33, and 35 of the Federal Statutes. Award of
IDNR SRFFile:CS1921150 01;IDNRProject:W2024-0302Amaybe dependent
on loan securement.
A Federal Davis-Bacon Wage rate determination will prevail for this Project.
General Decision Numbers IA20260003 shall apply.
Women and Minority-owned businesses are encouraged to submit Bids for this
Project.
Bidders must demonstrate positive efforts to utilize women's and minority owned
businesses. This procurement will be subject to regulations contained in
40 CFR 35.3145(d), and P.L. 102-389 and 100-590. In addition, Bidder shall
comply with Executive Orders 11625, 12138, and 12432.
General Nature of Public Improvement
2026 Terminal Street Pumping Station Rehabilitation, IDNR SRF
File: CS1921150 01; IDNR Project: W2024-0302A
Project consists of the removal and replacement of the existing site roof, three
sluice gates, installation of electrical conduit associated with installation of three
motorized gate actuators, installation of a pump retrieval system, replacement of
an existing exterior door, and replacement of the existing roof.
Preference for Iowa Products and Labor. By virtue of statutory authority,
preference will be given to products and provisions grown and coal produced within
the State of Iowa. In accordance with Iowa statutes, a resident Bidder shall be
allowed a preference as against a nonresident bidder from a state or foreign
country if that state or foreign country gives or requires any preference to Bidders
from that state or foreign country, including but not limited to, any preference to
Bidders, the imposition of any type of labor force preference, or any other form of
preferential treatment toBidders or laborers from that state or foreign country. The
preference allowed shall be equal to the preference given or required by the state
or foreign country in which the nonresident Bidder is a resident. In the instance of
a resident labor force preference, a nonresident Bidder shall apply the same
resident labor force preference to a public improvement in this state as would be
2of3
4908-2825-2830\2

required in the construction of a public improvement by the state or foreign country
in which the nonresident Bidder is a resident.
Sales Tax.TheBidder should not include sales tax in itsBid.A sales tax exemption
certificate will be available for all material purchased for incorporation in the
Project.
Contact Information. The Bidders shall contact either Randy J. Langer, P.E.
(randy.langer@strand.com or 608-251-4843) at Strand Associates, Inc.(R) or
Deron Muehring (dmuehrin@cityofdubuque.org or 563-589-4176) at the City of
Dubuque, or both parties with their questions associated with this project.
Title VI-Non-Discrimination Clause. The City of Dubuque in accordance with
Title VI of the Civil Rights Act of 1964, 78 Stat.252,42U.S.C. 2000d-2000d-4and
Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A,
Officeof theSecretary,Part21,Nondiscrimination inFederallyassistedprograms
of the Department of Transportation issued pursuant to such Act, hereby notifies
allBidders that it willaffirmatively insure thatin any contract entered into pursuant
tothisadvertisement,minoritybusinessenterpriseswillbeaffordedfullopportunity
to submit Bids in response to this invitation and will not be discriminated against
onthegroundsofrace,color,nationalorigin,sex,age,ordisabilityin consideration
for an award.
On the following date, April 21, 2026 this Notice was posted at the following
locations:
1. Posted on the City of Dubuque Website: www.cityofdubuque.org/bids
2. Posted to Construction Update Network: www.mbionline.com
3of3
4908-2825-2830\2

This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Follow Air compressor with incidental installation Active Contract Opportunity Notice ID W50S7226Q7114 Related

DEPT OF DEFENSE

Due by 9/22/2026

Bid Number Bid Title Bid Type Organization Bid Issue Date Bid Close Date

City of Iowa

Due by 10/12/2026

Bid Title: Middle Road Water Main Extension Project Category: Water Status: Open Description:

City of Dubuque, IA

Due by 10/01/2026

Bid Information Type Request for Qualification Status Issued Number 0510-045-2026 (Request for Qualifications

City of West Des Moines

Due by 9/30/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.