Steven M. Clouse WRC Biosolids Upgrades

Project Description

The Steven M. Clouse Water Recycling Center (WRC), located in southeast San Antonio, is the largest of the three SAWS wastewater treatment plants and is the centralized location for handling the biosolids generated at the treatment plants.

This project will address the capacity gaps for the biosolids screening, thickening, and dewatering processes at the Steven M. Clouse WRC based on biosolids projections through 2050; replace existing equipment at the end of its useful life; prevent or mitigate higher biosolids cake management costs; and better position SAWS for possible future Class A biosolids production. The project will construct a new consolidated biosolids building that will house new biosolids screen presses, thickening, and dewatering equipment to address condition- and capacity-related needs as well as reduce the operational complexity of the existing biosolids handling system.

When Will Work Occur?

  • Construction solicitation is anticipated in the 3rd Quarter of 2026.
  • Construction is anticipated to start in the 4th Quarter of 2026.
  • Estimated construction duration is 3 years.
  • Estimated construction budget is >$100M.

What to Expect:

  • A new centralized biosolids building with new solids screen presses, thickening, and dewatering equipment sized to process current and projected 2050 biosolids loads
  • New cake storage silos
  • A new biosolids laboratory with office and storage spaces, a new parking lot, roads, and sidewalks
  • Demolition of the current belt filter press pavilion
  • Adequate levels of system automation, controls, and instrumentation to optimize plant operation and performance
  • Associated site/civil, mechanical, structural, architectural, electrical and instrumentation and controls work

For more information:

Hari Ponnekanti, P.E.

Hari.Ponnekanti@saws.org

SAWS Contract Administration Point of Contact:

Stephen Muñiz, Contract Administrator

Email: Stephen.Muniz@saws.org

Phone: 210-233-2950

Notify Me


Receive updates sent straight to your inbox.
Subscribe
Downloads

Contractor Outreach Fact Sheet


Mar. 26, 2025



Questions? Please contact

Stephen Muniz

at 210-233-2950
|

Receive Email Updates
|

Registration Agreement

Attachment Preview

Steven M. Clouse WRC Biosolids Upgrades
The Steven M. Clouse Water Recycling Center (WRC), located in southeast San Antonio, is the largest of the three
SAWS wastewater treatment plants and is the centralized location for handling the biosolids generated at the
treatment plants.
This project will address the capacity gaps for the biosolids screening, thickening, and dewatering processes at the
Steven M. Clouse WRC based on biosolids projections through 2050; replace existing equipment at the end of its
useful life; prevent or mitigate higher biosolids cake management costs; and better position SAWS for possible future
Class A biosolids production. The project will construct a new consolidated biosolids building that will house new
biosolids screen presses, thickening, and dewatering equipment to address condition- and capacity-related needs as
well as reduce the operational complexity of the existing biosolids handling system.
When Will Work Occur?
Construction solicitation is anticipated in the 3rd
Quarter of 2026.
Construction is anticipated to start in the 4th Quarter
of 2026.
Estimated construction duration is 3 years.
Estimated construction budget is >$100M.
What to Expect:
A new centralized biosolids building with new solids
screen presses, thickening, and dewatering
equipment sized to process current and projected
2050 biosolids loads
New cake storage silos
A new biosolids laboratory with office and storage
spaces, a new parking lot, roads, and sidewalks
Demolition of the current belt filter press pavilion
Adequate levels of system automation, controls, and
instrumentation to optimize plantoperation and
performance
Associated site/civil, mechanical, structural,
architectural, electrical and instrumentation and
controls work
For more information:
Hari Ponnekanti, P.E.
Hari.Ponnekanti@saws.org
210-233-2352
SAWS Contracting
Stephen Muniz
Stephen.Muniz@saws.org
210-233-2350
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Follow NSWCCD ANSYS LICENSES Active Contract Opportunity Notice ID CD-63-0073 Related Notice Department/Ind.

DEPT OF DEFENSE

Steven M. Clouse WRC Biosolids Upgrades IN-PERSON CONTRACTOR OUTREACH MEETING July 28, 2025

San Antonio Water System

Bid Due: 8/03/2026

Follow Appspace Cloud Subscription. Active Contract Opportunity Notice ID N0018926QW066 Related Notice Department/Ind.

DEPT OF DEFENSE

Follow 67--BOEM GOA VISUALIZATION RM TECH REFRESH Active Contract Opportunity Notice ID 140M0126Q0020

INTERIOR, DEPARTMENT OF THE

Bid Due: 7/10/2026