Boulder County Purchasing
1325 Pearl Street
Boulder, CO 80302
SUBMISSION INSTRUCTIONS
Reference Number: RFP-017-23
Project Name:
Southeast Community Hub Solar PV System
Background:
Boulder County is soliciting proposals from a qualified contractor to design, fabricate, deliver,
install, and maintain a rooftop utility-interactive solar photovoltaic system that shall produce a
minimum of 100 kW. Larger capacity systems that produce more than the minimum are an
alternative and will be evaluated but the proposed system shall not produce more than 150 kW.
List of Abbreviations and Acronyms
AC
alternate current
A/E
architects/engineers
ANSI
American National Standards Institute
ASCE
American Society of Civil Engineers
ASME
American Society of Mechanical Engineers
CDs
compact disks
CM
construction management
CSI
Construction Specifications Institute
DC
direct current
EPA
Environmental Protection Agency
ETL
ETL Testing Laboratories
FM
Factory Manual
IEC
International Electrotechnical Commission
1
IEEE
kWh
kW
kV
LED
MDP
MPPT
NEC
NEMA
NFPA
NRCA
POA
POI
PV
QCP
RECs
SB1
STC
TRECs
UL
WREGIS
V
Institute of Electrical and Electronics Engineers
kilowatt-hour
kilowatt
Kilovolts
light emitting diode
main distribution panel
maximum power point tracking
National Electrical Code
National Electrical Manufacturers Association
National Fire Protection Association
National Roofing Contractors Association
plane of array
point of interconnection
photovoltaic
Quality Control Plan
renewable energy certificates
California Senate Bill 1
standard test conditions
tradable renewable energy certificates
Underwriters Laboratories
Western Renewable Energy Generation Information System
volts
2
1. PROJECT IDENTIFICATION
1.1. Project: Roof Mounted, Grid Tied PV System
1.2. Location: 1755 South Public Road, Lafayette, CO 80026
2. BACKGROUND
2.1. Objective. Contractor shall provide a total “turnkey” project including all necessary
equipment, materials, design, manufacturing, and installation services for the installation of a
roof mounted utility-interactive photovoltaic system that shall produce a minimum of 100 kW.
Larger capacity systems that produce more than the minimum are an alternative and will be
evaluated but the proposed system shall not produce more than 150 kW. The contractor
should prepare system summary detailing applicable equipment/size and predicted system
energy production. This project shall meet all requirements of this Statement of Work and
other specifications included that apply.
2.2. Scope. The contractor shall perform all professional services as necessary to provide
Boulder County with a complete design package including the requirements outlined in this
Statement of Work. The contractor shall install the project such that it is operational and
compliant with all applicable standards, building codes, UTILITY interconnection requirements,
and STATE requirements. The contractor shall include specifications, calculations, and
drawings in the design package, and turn it over to Boulder County. After approval by Boulder
County of the final design package, the contractor shall provide all necessary construction to
successfully complete the photovoltaic system installation. The awarded contractor shall
research all applicable solar PV incentives, including but not limited to Colorado State
program incentives, utility program incentives, and Federal tax credits. In addition, awarded
contractor shall provide supporting documentation and apply on behalf of Boulder County for
applicable incentives. Boulder County Building Services (BCBS) has staff electricians that will
provide conduit/raceway from roof locations to electrical rooms as well as installing cabling to
electrical panels and switchgear. Cabling sizes will be determined by the contractor.
2.2.1. Design Guidelines for Roof Mounted PV System.
Design Guidelines for Rooftop PV. Contractor shall develop a design for a new photovoltaic
system at Boulder County SE Community Hub located at 1755 S. Public Road, Lafayette. See
attached drawings indicating available areas for installation and existing roof structure plans.
NOTE: There are two sets of structural plans. The original construction set, and the new
construction set which shows reinforcing installed for new rooftop equipment. Overall
building loading should be per the original construction set.
• Mounting system shall limit roof penetrations and shall be either building integrated
roof PV or fully ballasted. Mounting system design needs to meet applicable local
building code requirements with respect to snow, wind, and earthquake factors.
3
• Conduit penetrations shall be minimized.
• System layout shall meet local fire department, code, and ordinance requirements for
roof access.
2.2.2. Performance Criteria. The following performance criteria shall be met for all arrays:
• The STC-rated power value will be entered into PVWatts
(http://pvwatts.nrel.gov/) using the nearest weather file to determine
estimated energy delivery in kWh AC. A default value for the system losses of
14% shall be used.
• PV array shall mean one or more PV modules having that same orientation and
on the same maximum power point tracking (MPPT) system. Every array with
differing orientation shall have a separate MPPT system.
• All PV hardware components shall be either stainless steel or aluminum. PV
structural components shall be corrosion resistant (galvanized steel, stainless
steel, composites, or aluminum).
• The project, including supports and power conductors, shall not interfere with
roof drains, water drainage, expansion joints, air intakes, existing electrical and
mechanical equipment, existing antennas, life safety fixtures, egress paths, and
planned areas for future installation of equipment shown on drawings.
2.2.3. Production Metering. The project shall have:
• At least one production meter at POI.
2.3. Technical Requirements and Reference Materials
2.3.1. Code Compliance. Installation and equipment shall comply with applicable building,
mechanical, fire, seismic, structural, and electrical codes. Only products that are
listed, tested, identified, or labeled by UL, FM, ETL, or another Nationally Recognized
Testing Laboratory shall be used as components in the project. Non-listed products
are only permitted for use as project components when a comparable useable listed
component does not exist. Non-listed products proposed for use as components
must be identified as such in all submittals.
The contractor shall use project components that are or are made of materials that are
recyclable, contain recycled materials, and that are EPA or Energy Star rated if they are
available on the market.
• FM Approved – Fire Protection Tests for Solar Component Products
• IEC 62446 Grid Connected Photovoltaic Systems- Minimum Requirements
for System Documentation, Commissioning Tests, and Inspections
4
2.4. Roles and Responsibilities.
2.4.1. Contractor. The contractor is required to provide:
• Design concepts
• Construction documents and engineering calculations that are signed and
sealed by a licensed architect or engineer.
• Submittals for materials and products
• Construction materials, equipment, and labor (raceway, cabling and final
electrical connections by BCBS).
• Design and construction supervision / contract management
• Permitting
• Inspections and tests
• Manuals (design calculations, operation/maintenance, shop drawing, etc.)
• Commissioning of project
• Training building operating staff for operation and maintenance.
• Operation and Maintenance during first year and optional service plan after
the first year
3. PROPOSAL CONCEPT DRAWINGS AND SPECIFICATIONS SUBMISSIONS
3.1. Concept Drawings. The successful contractor shall provide Boulder County with concept
drawings with the proposal. The drawings must indicate the proposed location of the PV
array(s) and access points along with a one-line electrical diagram showing inverters,
transformers, meters, and interconnection locations. All drawings shall be submitted with
dimensions shown in English units.
3.2. Concept Information. The proposal shall include major equipment information, proposed
installation/interconnection information, applicable incentive information, and
performance characteristics of the system. Identify an appropriate location for the solar PV
inverter equipment and its related components and environmental control systems that
will meet the following criteria:
• Ease of maintenance and monitoring
• Efficient operation
• Low operating losses
• Secured location and hardware
5