Sonora Regional Wastewater Treatment Facility Filter and Chlorine Basin Cover Structures

Agency: Tuolumne Utilities District
State: California
Type of Government: State & Local
NAICS Category:
  • 221320 - Sewage Treatment Facilities
  • 236220 - Commercial and Institutional Building Construction
  • 237990 - Other Heavy and Civil Engineering Construction
Posted Date: Nov 19, 2025
Due Date: Dec 12, 2025
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description

Sonora Regional Wastewater Treatment Facility Filter and Chlorine Basin Cover Structures

Project Description
Tuolumne Utilities District (TUD) is seeking qualified contractors for the construction of the Sonora Regional Wastewater Treatment Facility (SRWWTF) Filter and Chlorine Contact Basin (CCB) Cover Structures (also called the Filter and CCB Structure Project), addressed to the Tuolumne Utilities District, 18885 Nugget Boulevard, Sonora, Ca in Tuolumne County.

Mandatory Pre-Bid Meeting:
A mandatory pre-bid conference will be held at the project site at 9:00 a.m. on November 19th. Each Bidder must be represented and attend the entire meeting. Each representative shall sign an attendance sheet identifying the Bidder represented. Bids will only be accepted from Bidders represented at the pre-bid conference. Attendance by subcontractors is not mandatory, but all interested prospective subcontractors are encouraged to attend.

Proposal Due Date:
December 12, 2025, by 2:00 p.m.

Bids
Sealed Bids for the construction of the Sonora Regional Wastewater Treatment Facility (SRWWTF) Filter and Chlorine Contact Basin (CCB) Cover Structures (also called the Filter and CCB Structure Project), addressed to the Tuolumne Utilities District, 18885 Nugget Boulevard, Sonora, California 95370, will be received at the office of the District until 2:00 p.m., local time, on December 12th, and will then be publicly opened and read.

Project Documents
Contract Documents- Sonora Regional WWTF Filter and Cover Structures
Plans- CCB and Filter Cover Structures

Addendum No. 1 – Filter and CCB Cover Structure

For information concerning the proposed work, contact: Mr. Erik Johnson, District Engineer, at (209) 532-5536, extension 520 or ejohnson@tudwater.com.

Attachment Preview

CONTRACT DOCUMENTS
Sonora Regional Wastewater Treatment Facility
Filter and Chlorine Contact Basin Cover Structures
TUOLUMNE UTILITIES DISTRICT
November 2025
This page is intentionally left blank.
TABLE OF CONTENTS
PART 1
BIDDING REQUIREMENTS
Invitation to Bid ....................................................................................... B-1
Instructions to Bidders ............................................................................ B-3
Bidder's Checklist ................................................................................... B-10
Bid Form ................................................................................................. B-11
Bid Schedule........................................................................................... B-13
Bid Bond ................................................................................................. B-17
Performance Bond .................................................................................. B-19
Public Works Payment Bond................................................................... B-24
List of Subcontractors ............................................................................. B-30
Non-collusion Declaration ....................................................................... B-31
Contractor Safety Agreement.................................................................. B-32
Notice of Award ...................................................................................... B-33
PART 2
CONTRACT FORMS
Agreement .............................................................................................. CF-1
Workmen's Compensation Insurance...................................................... CF-5
Public Works Contract Conditions ........................................................... CF-6
California Labor Code: Required Provisions in Public Work Contracts .... CF-7
PART 3
CONDITIONS OF THE CONTRACT
General Conditions ................................................................................. GC-1
General Conditions Index........................................................................ GC-3
Article 1 - Definitions ............................................................................... GC-7
Article 2 - Preliminary Matters ................................................................. GC-9
Article 3 - Correlation, Interpretation & Intent of Contract Documents ..... GC-10
Article 4 - Availability of Lands; Physical Conditions; Reference Points... GC-11
Article 5 - Bonds and Insurance .............................................................. GC-13
Article 6 - Contractor’s Responsibilities ................................................... GC-14
Article 7 - Work by Others ....................................................................... GC-20
Article 8 - Owner’s Responsibilities ......................................................... GC-21
Article 9 - Engineer’s Status During Construction.................................... GC-21
Article 10 - Changes in the Work............................................................. GC-23
Article 11 - Change of Contract ............................................................... GC-24
Article 12 - Change of the Contract Time ................................................ GC-28
Article 13 - Warranty and Guarantee, Tests and Inspections, Correction,
Removal or Acceptance of Defective Work........................... GC-28
Article 14 - Payments and Completion .................................................... GC-31
Unconditional Waiver and Release Upon Final Payment ........................ GC-37
Article 15 - Suspension of Work and Termination.................................... GC-39
Article 16 - Claims/Dispute Resolution .................................................... GC-40
Article 17 - Assignment of Antitrust or Unfair Business Practices Claims
to Owner Under Public Contracts Code § 7103.5 .................. GC-40
Article 18 - Miscellaneous ....................................................................... GC-41
i-1
Supplementary Conditions ...................................................................... SC-1
1. Counterparts of the Agreement ...................................................... SC-1
2. Additional Bond .............................................................................. SC-1
3. Insurance Requirements for Contractor.......................................... SC-1
4. Specifications ................................................................................. SC-4
5. Drawings ........................................................................................ SC-4
6. Owner ............................................................................................ SC-4
7. Engineer......................................................................................... SC-4
8. Resident Project Representative .................................................... SC-5
9. Responsibility for Payment ............................................................. SC-5
10. Documentation to Accompany Applications for Payment................ SC-5
11. Retainage....................................................................................... SC-5
12. Partial Utilization ............................................................................ SC-5
13. Substantial Completion .................................................................. SC-6
14. Final Inspection and Acceptance.................................................... SC-6
15. Liquidated Damages ...................................................................... SC-6
16. Correction Period ........................................................................... SC-7
17. Overtime Work ............................................................................... SC-7
18. Legal Addresses ............................................................................ SC-7
19. Underground Installations............................................................... SC-7
20. Layout of Work ............................................................................... SC-8
21. Compaction and Concrete Testing ................................................. SC-8
22. Design Engineer............................................................................. SC-8
23. Measurement and Payment ........................................................... SC-8
24. Submittals and Proposed Equivalents ............................................ SC-9
25. Staging Area .................................................................................. SC-12
26. Construction Facilities .................................................................... SC-13
27. Work Days and Hours .................................................................... SC-14
PART 4 TECHNICAL SPECIFICATIONS
13500 Metal Buildings
i-2
This page is intentionally left blank.
i-3
This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Project ID: pf 2306; Bid 2725 Title: Community Civic Campus: Phase 3, Fire

City of South San Francisco

Due by 12/01/2026

Bid No. 008-26/27 - Asphalt Improvement Project at Multiple Sites Notice Inviting Proposal

Glendale Unified School District

Due by 11/17/2026

Follow Mather Fueling System Repairs Active Contract Opportunity Notice ID PANNWD26P028176 Related Notice

DEPT OF DEFENSE

Due by 11/20/2026

Follow Solicitation: Construct Combat Rescue Helicopter Flight Simulator Facility at Moffett ANGB Active

DEPT OF DEFENSE

Due by 11/27/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.