Sacramento County Department of Airports Consolidated Rental Car Facility

The Sacramento County Department of Airports (SCDA) is advancing development of a new Consolidated Rental Car Facility (ConRAC) at Sacramento International Airport (SMF) as part of the SMForward capital program.

The planned facility will create a walkable rental car experience from both Terminal A and Terminal B, reduce shuttle dependency, improve wayfinding, and provide modern customer service facilities. The project also supports sustainability goals, community workforce participation, and small business opportunities.

On April 16, 2026, the Department hosted an Industry Day to provide prospective firms with an overview of the project and an introduction to the Department's upcoming solicitation plans.

SMF ConRAC Industry Day Presentation – April 16, 2026

Attachment Preview

CONSOLIDATED RENTAL CAR FACILITY
Industry Day
Progressive Design-Build RFQ
April 16, 2026

What to Expect Today Geneveive
01 Team Introductions 06 Project Financing 02 Program Goals and Vision 07 RAC Involvement and Next Steps 03 Project Background 08 RFQ Process and Timelines 04 Progressive Design-Build -Process Overview Q&A Questions and Discussion 05 Program Enhancements After Scheduled Meetings with Airport Staff ConRACIndustry Day * April 16, 2025 * 2
ConRACIndustry Day * April 16, 2025 * 2
01 Team Introductions
06 Project Financing
02 Program Goals and Vision
07 RAC Involvement and Next Steps
03 Project Background
08 RFQ Process and Timelines
04 Progressive Design-Build -Process Overview
Q&A Questions and Discussion
05 Program Enhancements
After Scheduled Meetings with Airport Staff

What to Expect Today
Geneveive
01 Team Introductions 06 Project Financing
02 Program Goals and Vision 07 RAC Involvement and Next Steps
03 Project Background 08 RFQ Process and Timelines
04 Progressive Design-Build -Process Overview Q&A Questions and Discussion
05 Program Enhancements After Scheduled Meetings with Airport Staff
ConRACIndustry Day * April 16, 2025 * 2

Section 01
Team
Introductions

Sacramento County Department of Airports - Project Team All
Stephen Clark Genevieve Vargas Andrew Durkee PHOTO PHOTO PHOTO Deputy Director Principal Architect/Engineer Senior Airport Manager Commercial Development & Project Executive Design & Development Finance & Administration (Project Finance) Renata Daher Michael Gladwill Michael Winans PHOTO PHOTO Airport Manager -Concessions Sr. Airport Economic Dev. Specialist Sr. Airport Economic Dev. Specialist Concessions & RAC Coordination Concessions & Contracts Procurement Contact & RFQ Administrator ConRACIndustry Day * April 16, 2025 * 4
ConRACIndustry Day * April 16, 2025 * 4
Stephen Clark PHOTO Deputy Director Commercial Development & Project Executive
Genevieve Vargas PHOTO Principal Architect/Engineer Design & Development
Andrew Durkee PHOTO Senior Airport Manager Finance & Administration (Project Finance)
Renata Daher PHOTO Airport Manager -Concessions Concessions & RAC Coordination
Michael Gladwill PHOTO Sr. Airport Economic Dev. Specialist Concessions & Contracts
Michael Winans Sr. Airport Economic Dev. Specialist Procurement Contact & RFQ Administrator

Sacramento County Department of Airports - Project Team
All
Stephen Clark Genevieve Vargas Andrew Durkee
PHOTO PHOTO PHOTO
Deputy Director Principal Architect/Engineer Senior Airport Manager
Commercial Development & Project Executive Design & Development Finance & Administration (Project Finance)
Renata Daher Michael Gladwill Michael Winans
PHOTO PHOTO
Airport Manager -Concessions Sr. Airport Economic Dev. Specialist Sr. Airport Economic Dev. Specialist
Concessions & RAC Coordination Concessions & Contracts Procurement Contact & RFQ Administrator
ConRACIndustry Day * April 16, 2025 * 4

Our Consulting Team - First PDB for Sacramento County Geneveive
While this is Sacramento County's first Progressive Design-Build project, we are supported by an experienced consulting team across legal, financial, technical, and program management disciplines. Executive Program Manager Legal Counsel Accenture Kaplan Kirsch Overall project management, schedule, budget oversight and PDD development PDB contract structure, procurement law, FAA compliance Financial Advisor Technical and Contract Advisor PFM Financial Advisors Ricondo -Jim Branda CFC modeling, bond structure, project finance Contract negotiation, procurement, consortium, sizing Project Delivery Process Advisor Initial Program Study, 2018/2019 Vanir -Michael Meredith, CCM, DBIA Fellow Jacobsen Daniels PDB RFQ process, delivery method and selection owner advisor Initial program validation and development ConRACIndustry Day * April 16, 2025 * 5
ConRACIndustry Day * April 16, 2025 * 5
Executive Program Manager Accenture Overall project management, schedule, budget oversight and PDD development
Legal Counsel Kaplan Kirsch PDB contract structure, procurement law, FAA compliance
Financial Advisor PFM Financial Advisors CFC modeling, bond structure, project finance
Technical and Contract Advisor Ricondo -Jim Branda Contract negotiation, procurement, consortium, sizing
Project Delivery Process Advisor Vanir -Michael Meredith, CCM, DBIA Fellow PDB RFQ process, delivery method and selection owner advisor
Initial Program Study, 2018/2019 Jacobsen Daniels Initial program validation and development

Our Consulting Team - First PDB for Sacramento County
Geneveive
While this is Sacramento County's first Progressive Design-Build project, we are supported by an experienced consulting team across legal, financial,
technical, and program management disciplines.
Executive Program Manager Legal Counsel
Accenture Kaplan Kirsch
Overall project management, schedule, budget oversight and PDD development PDB contract structure, procurement law, FAA compliance
Financial Advisor Technical and Contract Advisor
PFM Financial Advisors Ricondo -Jim Branda
CFC modeling, bond structure, project finance Contract negotiation, procurement, consortium, sizing
Project Delivery Process Advisor Initial Program Study, 2018/2019
Vanir -Michael Meredith, CCM, DBIA Fellow Jacobsen Daniels
PDB RFQ process, delivery method and selection owner advisor Initial program validation and development
ConRACIndustry Day * April 16, 2025 * 5

Section 02
Program Goals
And Vision

Our Vision for This Project Genevieve
Airport-Led Financing A Highly 1 The County will manage project financing directly through Customer Facility Charges -we are not seeking a private capital partner. This keeps decision- Collaborative making authority and alignment of interests where it belongs: with SMF and our partners. Partnership Open Questions, Collaborative Answers 2 We have significant programming questions still to resolve. That is a feature, not a bug -it is exactly why the Progressive Design-Build model is the right We are not simply hiring a contractor. We are selecting a long- approach. We expect our partner to bring creative solutions and a term partner who shares our commitment to SMF's willingness to work through complexity together. customers, our RAC partners, and our community. Balance of Conservatism & Creativity 3 Airport retains project financing leadership. The project will require disciplined cost management and a conservative DB brings design innovation and delivery expertise. financial approach -paired with genuine design innovation. We want both, and we believe the right team can deliver both. ConRACIndustry Day * April 16, 2025 * 7
ConRACIndustry Day * April 16, 2025 * 7
1 Airport-Led Financing The County will manage project financing directly through Customer Facility Charges -we are not seeking a private capital partner. This keeps decision- making authority and alignment of interests where it belongs: with SMF and our partners.
2 Open Questions, Collaborative Answers We have significant programming questions still to resolve. That is a feature, not a bug -it is exactly why the Progressive Design-Build model is the right approach. We expect our partner to bring creative solutions and a willingness to work through complexity together.
3 Balance of Conservatism & Creativity The project will require disciplined cost management and a conservative financial approach -paired with genuine design innovation. We want both, and we believe the right team can deliver both.

Our Vision for This Project
Genevieve
Airport-Led Financing
A Highly
1 The County will manage project financing directly through Customer Facility
Charges -we are not seeking a private capital partner. This keeps decision-
Collaborative
making authority and alignment of interests where it belongs: with SMF and
our partners.
Partnership
Open Questions, Collaborative Answers
2 We have significant programming questions still to resolve. That is a feature,
not a bug -it is exactly why the Progressive Design-Build model is the right
We are not simply hiring a contractor. We are selecting a long- approach. We expect our partner to bring creative solutions and a
term partner who shares our commitment to SMF's willingness to work through complexity together.
customers, our RAC partners, and our community.
Balance of Conservatism & Creativity
3
Airport retains project financing leadership. The project will require disciplined cost management and a conservative
DB brings design innovation and delivery expertise. financial approach -paired with genuine design innovation. We want both,
and we believe the right team can deliver both.
ConRACIndustry Day * April 16, 2025 * 7

Program Goals Genevieve
Customer Experience Facility Quality * Walkable from both Terminal A and Terminal B * Meet expected passenger traffic volumes * Eliminate shuttle dependency * Architectural compatibility with SMForward program aesthetic * World-class customer service center with intuitive way finding * Scalable and adaptable to future airport growth * Reduced curbside congestion and improved air quality * Environmentally responsible Project Delivery Community Benefit * Limit County financial exposure * Strong small business participation goals * 100% CFC paid debt * Community Workforce and Training Agreement (CWTA) required * Leverage private sector innovation through Progressive Design-Build * Positive economic impact for the Airport and broader region * RAC Partner inclusivity through collaborative design choices ConRACIndustry Day * April 16, 2025 * 8
ConRACIndustry Day * April 16, 2025 * 8
Customer Experience
* Walkable from both Terminal A and Terminal B * Eliminate shuttle dependency * World-class customer service center with intuitive way finding * Reduced curbside congestion and improved air quality
Facility Quality
* Meet expected passenger traffic volumes * Architectural compatibility with SMForward program aesthetic * Scalable and adaptable to future airport growth * Environmentally responsible
Project Delivery
* Limit County financial exposure * 100% CFC paid debt * Leverage private sector innovation through Progressive Design-Build * RAC Partner inclusivity through collaborative design choices
Community Benefit
* Strong small business participation goals * Community Workforce and Training Agreement (CWTA) required * Positive economic impact for the Airport and broader region

Program Goals
Genevieve
Customer Experience Facility Quality
* Walkable from both Terminal A and Terminal B * Meet expected passenger traffic volumes
* Eliminate shuttle dependency * Architectural compatibility with SMForward program
aesthetic
* World-class customer service center with intuitive way finding
* Scalable and adaptable to future airport growth
* Reduced curbside congestion and improved air quality
* Environmentally responsible
Project Delivery Community Benefit
* Limit County financial exposure * Strong small business participation goals
* 100% CFC paid debt * Community Workforce and Training Agreement (CWTA)
required
* Leverage private sector innovation through Progressive
Design-Build * Positive economic impact for the Airport and broader region
* RAC Partner inclusivity through collaborative design choices
ConRACIndustry Day * April 16, 2025 * 8

SMF Team ConRAC Tours - Key Considerations Genevieve*Andrew * Renata * Michael
ConRACIndustry Day * April 16, 2025 * 9
ConRACIndustry Day * April 16, 2025 * 9

SMF Team ConRAC Tours - Key Considerations
Genevieve*Andrew * Renata * Michael
ConRACIndustry Day * April 16, 2025 * 9

Design Goals - Customer Experience in Detail Genevieve*Andrew * Renata * Michael
Walkability, Proximity, & Safety Premium Passenger Experience As close to Concourse A and Concourse B as the site allows. A meaningful share of our customers deplane from first class and Minimize walking distance, minimize vertical level changes, and are headed to a luxury or premium vehicle. What does that provide covered pedestrian connections. The design should experience look like? We want a design that acknowledges and consider safety as a core deliverable to reduce trips, slips, falls serves this segment. Accommodating for local community and accidents for customers and employees. renters. EV Readiness & Future-Proofing Security & Vehicle Theft Prevention EV charging infrastructure readiness: Facility design to enable EV A highly secure facility with specific design goals to reduce and charging buildouts including beam cutouts and conduit. Beyond eliminate vehicle theft. Secure entry/exit control points, clear today's technology -we want a building designed to adapt as sightlines, defined exclusive-use zones, and infrastructure for the RAC industry and customer behavior continue to evolve access control systems. rapidly. Technology integration should be a core design principle. ADA and Signage Related Considerations Technology & Focus on Future Signs should be designed with ADA in mind and for those with Designed with a clear view toward future operational and A general vision limitations. Beyond ADA minimums, our facility customer needs. What does a great customer service experience should have sitting rest areas along a customer's journey, family look like as digital phone-based check-in or similar direct to needs, and nursing rooms. vehicle service increases? ConRACIndustry Day * April 16, 2025 * 10
ConRACIndustry Day * April 16, 2025 * 10
Walkability, Proximity, & Safety As close to Concourse A and Concourse B as the site allows. Minimize walking distance, minimize vertical level changes, and provide covered pedestrian connections. The design should consider safety as a core deliverable to reduce trips, slips, falls and accidents for customers and employees.
Premium Passenger Experience A meaningful share of our customers deplane from first class and are headed to a luxury or premium vehicle. What does that experience look like? We want a design that acknowledges and serves this segment. Accommodating for local community renters.
EV Readiness & Future-Proofing EV charging infrastructure readiness: Facility design to enable EV charging buildouts including beam cutouts and conduit. Beyond today's technology -we want a building designed to adapt as the RAC industry and customer behavior continue to evolve rapidly. Technology integration should be a core design principle.
Security & Vehicle Theft Prevention A highly secure facility with specific design goals to reduce and eliminate vehicle theft. Secure entry/exit control points, clear sightlines, defined exclusive-use zones, and infrastructure for access control systems.
A ADA and Signage Related Considerations Signs should be designed with ADA in mind and for those with general vision limitations. Beyond ADA minimums, our facility should have sitting rest areas along a customer's journey, family needs, and nursing rooms.
Technology & Focus on Future Designed with a clear view toward future operational and customer needs. What does a great customer service experience look like as digital phone-based check-in or similar direct to vehicle service increases?

Design Goals - Customer Experience in Detail
Genevieve*Andrew * Renata * Michael
Walkability, Proximity, & Safety Premium Passenger Experience
As close to Concourse A and Concourse B as the site allows. A meaningful share of our customers deplane from first class and

Minimize walking distance, minimize vertical level changes, and are headed to a luxury or premium vehicle. What does that
provide covered pedestrian connections. The design should experience look like? We want a design that acknowledges and
consider safety as a core deliverable to reduce trips, slips, falls serves this segment. Accommodating for local community
and accidents for customers and employees. renters.
EV Readiness & Future-Proofing Security & Vehicle Theft Prevention
EV charging infrastructure readiness: Facility design to enable EV
A highly secure facility with specific design goals to reduce and
charging buildouts including beam cutouts and conduit. Beyond
eliminate vehicle theft. Secure entry/exit control points, clear
today's technology -we want a building designed to adapt as
sightlines, defined exclusive-use zones, and infrastructure for
the RAC industry and customer behavior continue to evolve
access control systems.
rapidly. Technology integration should be a core design principle.
ADA and Signage Related Considerations Technology & Focus on Future
Signs should be designed with ADA in mind and for those with Designed with a clear view toward future operational and
A
general vision limitations. Beyond ADA minimums, our facility customer needs. What does a great customer service experience
should have sitting rest areas along a customer's journey, family look like as digital phone-based check-in or similar direct to
needs, and nursing rooms. vehicle service increases?
ConRACIndustry Day * April 16, 2025 * 10

This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Project ID: Title: Specialty Therapeutic Bed Rental Services Addenda: 0 Release Date: 6/22/2026

County of San Mateo

Bid Due: 7/27/2026

Follow 15 passenger vans. Active Contract Opportunity Notice ID W911SG25QA016 Related Notice Department/Ind.

DEPT OF DEFENSE

Bid Due: 3/24/2028

Specification Number Description Due Time Contact Addendum B - Questions and Answers -

City of Berkeley

Bid Due: 12/01/2029

Bid Solicitation # CM-26-730 Bid Solicitation # CM-26-730 Organization Name City of Long

City of Long Beach

Bid Due: 8/18/2026