Request for Qualifications (RFQ)
Civil Engineering Services: Airfield Safety and Capacity
Program – Village Creek Relocation Design
Birmingham Airport Authority
November 2025
I. Introduction
A. Project Description
The Birmingham Airport Authority (BAA) is soliciting Statements of Qualifications (SOQ)
and Project Proposals from qualified engineering firms (firms) to perform civil engineering
services for the design phase of the following project at the Birmingham-Shuttlesworth
International Airport (BHM):
• Village Creek Relocation Design
See Exhibit A for approximate project limits.
The selected firm shall be obligated to perform the necessary work through completion
of design and construction, including providing construction ready documents for
bidding, detailed construction cost estimates, bid phase services, and construction phase
services.
B. Project Background
BHM has two intersecting airline transport category runways: Runway 6/24 and Runway
18/36. Runway 6/24, constructed in the 1950’s and extended most recently in 2007 to a
total length of 12,007 feet, is the primary runway. Runway 18/36 is the crosswind or
secondary runway, with a total length of 7,100 feet.
These runways are connected to a taxiway system that supports aircraft movement to
and from the landside aviation use areas. The most utilized and prominent of the
taxiways at BHM is Taxiway ‘A’. It extends the full length of Runway 6/24 and serves as
the runway’s primary parallel taxiway. Taxiway ‘A’ also abuts the passenger terminal
apron and provides access to the cargo ramp and a leased Maintenance, Repair, and
Overhaul (MRO) facility known as Kaiser.
The existing Runway 6/24 centerline to Taxiway ‘A’ centerline separation is 350 feet,
which does not meet FAA design standards for BHM’s current operational level. The FAA
approved the 2018 Airport Layout Plan (ALP), which depicts a standard condition wherein
Taxiway ‘A’, southwest of Taxiway ‘B’, is realigned to meet FAA design criteria.
Furthermore, the FAA funded a safety and capacity study for BHM that outlined a strategy
to not only address the non-standard runway-to-taxiway separation distance, but also an
installation approach for additional airfield capacity improvement projects congruent
with the 2018 ALP.
The primary enabling project for the relocation of Taxiway ‘A’ is a channel realignment of
Village Creek, which runs parallel to Taxiway ‘A’. An Environmental Assessment (EA) of
the potential impacts to Village Creek is underway with a target conclusion date of March
2026.
2
Village Creek Relocation
Pending the result of the Environmental Assessment (EA), the preferred alternative
involves the relocation of approximately 3,200 linear feet of Village Creek to
accommodate the future realignment of Taxiway ‘A’.
This design effort shall include, but is not limited to the following enabling elements:
• Building abatement and demolition
• Environmental testing
• Utility considerations (Water, Sewer, Gas, Communication, and FAA NAVAID)
• Vehicle Service Road (VSR) demolition and realignment
• Village Creek channel realignment
• Administration of required environmental mitigation credits
II. Scope of Services
A. Goals
i. To enter into a contract with the most qualified engineering firm for professional
services pertaining to taxiway, stream, utility, and service road realignment.
ii. To design plans that meet BAA goals and federal requirements for the project.
iii. To design and provide bid ready, construction plans by or before the target bid
period of March 2027.
iv. To perform bid phase services.
v. To perform construction phase services through project closeout.
B. Anticipated Project Elements
The anticipated project element necessary phases to successfully execute the proposed
project are listed below. These are subject to change based on actual project needs
determination.
Preliminary Phase: This phase involves those activities required for defining the scope of
a project and establishing preliminary requirements. Some examples of activities within
this phase of a project include, but are not limited to:
i. Coordinating with the sponsor on project scope requirements, finances,
schedules, operational safety and phasing considerations, site access and other
pertinent matters.
ii. As applicable, coordinating projects with local FAA personnel and other pertinent
stakeholders to identify potential impacts to their operations.
iii. Planning, procuring, and/or preparing necessary surveys, geotechnical,
engineering investigations, field investigations, and architectural and engineering
studies required for design considerations.
iv. Developing design schematics, sketches, environmental and aesthetic
considerations, project recommendations, and preliminary layouts and cost
estimates.
3
Design Phase: This phase includes all activities required to undertake and accomplish a
full and complete project design. Examples include, but are not limited to, those below:
i. Conducting and attending meetings and design conferences to obtain
information and to coordinate or resolve design matters.
ii. Collecting engineering data and undertaking field investigations; performing
geotechnical engineering studies; and performing architectural, engineering, and
special environmental studies.
iii. Preparing necessary engineering reports and recommendations.
iv. Preparing detailed plans, specifications, cost estimates, and design/construction
schedules.
v. Preparing/submitting a Construction Safety and Phasing Plan (CSPP) and required
7460-1 airspace studies to the FAA needed for site investigation and construction.
vi. Providing necessary copies of engineering drawings in print and CAD format.
Bidding Phase: These activities are sometimes considered part of the construction phase.
They involve assisting the sponsor in advertising and securing bids, analyzing and
certifying bids, furnishing recommendations on the award of contracts, and preparing
contract documents.
Construction Phase: This phase includes all basic and special services associated with the
oversight of construction activities from project commencement to project closeout.
III. Submittal Requirements
A. Selection Process
This qualification-based selection process shall be in accordance with FAA Advisory
Circular 150/5100-14E, Architectural, Engineering, and Planning Consultant Services for
Airport Grant Projects.
Award of this project would not preclude the awarded firm from future planning,
environmental, design and/or construction services award with BAA. This applies to both
prime firms and subconsultants.
A Statement of Qualifications (SOQ) and Project Proposal will be solicited from all
interested firms. The SOQ will allow the opportunity to provide data relating to the
experience and qualifications of the interested firm as it relates to the proposed project.
The Project Proposal will include information to illustrate the firm’s category
understanding, approach, and project management / communication plan.
Firms may be interviewed. However, BAA reserves the right to select the highest ranked
consultant based solely upon submittals if sufficient information is included in the SOQ
and project proposals.
B. Statement of Qualifications / Project Proposal
Please submit five (5) hard copies and one (1) electronic copy of your SOQ and Project
Proposal submittal to the address below.
Contact:
Ed Seoane, VP of Purchasing
E-mail:
eseoane@flybhm.com
4
Address:
Birmingham Airport Authority Receiving Warehouse
5500 Airline Drive
Birmingham, AL 35212
Hard copies may be shipped via U.S. Postal Service or any other reputable courier service
(e.g., Federal Express, UPS, etc.). The electronic copy must be included with the hard
copies via a USB flash drive. Deliveries can also be made in-person to the BAA Office
located on the ground level of the Terminal Building (located at the above address).
All questions associated with this RFQ must be submitted in writing via e-mail to Ed
Seoane at eseoane@flybhm.com by the deadline identified for questions/clarifications
(see timeline). Questions related to the RFQ directed to any other BAA personnel may be
grounds for disqualification.
C. Statement of Qualifications / Project Proposal Format
Respondent’s SOQ and Project Proposal shall be submitted together as one submittal no
longer than thirty (30) total pages of content (not including back / front cover, tabs /
dividers, cover letter, or table of contents). Each page must not be larger than 8.5” x 11”.
D. Statement of Qualifications Section Requirements
The SOQ portion of the submittal must include the following sections:
i.
Firm Overview and Capability to Perform All Aspects of the Project: Detail the
overall structure of the firm and any unique operating characteristics that may
enhance the project’s overall success. This should include but is not limited to:
information such as relevant services provided by the firm, office locations, and
total number of employees providing relevant services.
ii.
Recent Company Experience in Relevant Projects: Discuss relevant services
completed at other comparable airports within the past five (5) years. This should
include, but is not limited to: project location, start and completion date,
description, outcome, quality, and applicability to BAA’s proposed project.
Identify the firm’s role as either a prime or subconsultant and specific
contribution to the project. A point of contact for the project’s sponsor must also
be included. References may be contacted, as necessary.
iii. Personnel Qualifications: Discuss the professional qualifications and relevant
experience for key members of the project team (including sub consultants).
Include how specific team members will contribute to the project’s overall
success. Provide organizational chart depicting project manager, deputy project
manager, and other project team members in their respective roles. The
workload of the project manager must also be identified.
iv. Project Partners: Discuss any subconsultants intended to be included on the
project team, if any. Detail their expected contribution to the project and, if
applicable, the number of projects the prime consultant and subconsultant have
previously completed or are nearing completion.
E. Project Proposal Section Requirements
The Project Proposal portion of the submittal must include the following sections:
5
This page summarizes the opportunity, including an overview and a preview of the attached documents.