City of Dublin, GA
Request for Qualifications
To Provide
Engineering Services
For
SEID Grant
Dublin, GA
RFQ #26-0227-01
Issue Date February 27, 2026
Due Date: April 1, 2026 by 2PM
RFQ #26-0227-01 – SEID Grant Engineering Services
2
REQUEST FOR QUALIFICATIONS
Engineering Services for
SEID Grant - Dublin, GA
REQUEST FOR QUALIFICATIONS
Engineering Services for SEID Grant – City of Dublin, Georgia
RFQ No. 26‑0227‑01
The City of Dublin (“Owner”) is seeking Statements of Qualifications (SOQs) from qualified engineering firms to provide
professional services for the State Economic and Infrastructure Development (SEID) Grant project. The project involves
improvements to the City’s Wastewater Treatment Plant, including replacement of the headworks screening equipment.
Services will include design, permitting, bidding assistance, construction administration, inspection, and preparation of
all SEID‑required documentation.
This project is funded through the Southeast Crescent Regional Commission (SCRC) and must comply with all
applicable federal and state requirements, including the Build America, Buy America (BABA) Act, 2 CFR 200 Uniform
Guidance, and all Georgia procurement statutes. Firms responding to this RFQ should have demonstrated experience
delivering engineering services for federally funded infrastructure projects.
Following the review of submitted Statements of Qualifications, the City may identify a shortlist of firms determined to
be the most qualified for further consideration. Shortlisted firms may be invited to participate in interviews. The firm
selected as the finalist will be required to submit a fee proposal in accordance with subsequent instructions issued by
the City. The City of Dublin reserves the right to reject any or all Statements of Qualifications, to waive technicalities,
irregularities, or informalities, and to cancel or conclude this procurement at any time without obligation.
The selected engineering firm will work collaboratively with the City to complete all required engineering tasks
associated with the SEID Grant and ensure full compliance with federal and state standards.
Purpose of the RFQ
The purpose of this Request for Qualifications (RFQ) is to solicit Statements of Qualifications (SOQs) from qualified and
experienced engineering firms to provide professional engineering services for the City of Dublin’s State Economic and
Infrastructure Development (SEID) Grant project. The project, funded through the Southeast Crescent Regional
Commission (SCRC), involves improvements to the City’s Wastewater Treatment Plant, including but not limited to the
replacement of the existing headworks screening equipment and associated system upgrades.
This RFQ is issued in accordance with all applicable federal and state requirements governing the procurement of
professional services, including the Uniform Administrative Requirements codified at 2 CFR Part 200, the Build America,
Buy America (BABA) Act, and relevant Georgia procurement statutes. Engineering firms responding to this solicitation
must demonstrate the capacity and qualifications necessary to perform all required design, permitting, bidding and
procurement assistance, construction administration, inspection, close‑out services, and SEID‑related documentation
and compliance.
The Owner intends to conduct a qualifications‑based selection process to identify the engineering firm that is most
capable of delivering the required services in a timely, compliant, and cost‑effective manner. The Selection Committee
will evaluate submitted qualifications in accordance with the criteria set forth herein, and finalist firms may be invited to
interviews and to submit fee proposals at a later stage of this procurement.
The issuance of this RFQ does not commit the Owner to award a contract, to pay any costs incurred in the preparation
of a response, or to procure or contract for any services. The Owner reserves the right to reject any or all Statements
of Qualifications, to waive technicalities and informalities, and to conduct the procurement in a manner deemed to be in
the best interests of the City of Dublin.
RFQ #26-0227-01 – SEID Grant Engineering Services
3
1. GENERAL PROJECT INFORMATION
Background
The City of Dublin applied for and received SEID grant funding to assist with Wastewater Treatment
improvements including the replacement of headworks screens. The city is seeking an engineering firm with
broad experience to provide design and construction supervision for this project, if awarded, and other related
professional services. SEID grants are funded by the federal government and administered at the state level by
the Southeast Crescent Regional Commission. Therefore, all activities must be performed in strict adherence to
applicable federal and state regulations.
This selected engineering firm will be expected to work with the City of Dublin to complete engineering work associated
with federal and state funding opportunities, including a State Economic and Infrastructure Development (SEID) Grant
from the Southeast Crescent Regional Commission. Funding for project has already been obtained.
Three to five firms that respond to this RFQ by submitting statements of qualifications may be determined to be
especially qualified and capable of delivering services and may be deemed eligible for further consideration to provide
these services as the engineering firm and invited to interview for these services. All respondents to this RFQ are
cautioned to completely review the entire RFQ and follow instructions carefully. The City of Dublin reserves the right to
reject any or all statements of qualifications, and to waive technicalities, irregularities, and informalities, and retains the
right to cancel or conclude this procurement at any time without selecting a firm to provide the described services,
without any liability to any respondents, or any other person or entity, and is under no obligation to make an award
relating to this RFQ to any person or entity. The final terms of any Engineering Services Agreement for the project
contemplated by this procurement will be determined by the Owner, subject, in all cases, to strict compliance with the
applicable provisions of the laws of the City of Dublin.
Project Description
Wastewater Treatment Improvements
Scope of Work – Engineering Services for SEID Grant Project
The City of Dublin intends to improve the Wastewater Treatment Facility, with a primary focus on replacing the existing
headworks screening equipment and completing related system upgrades. The selected engineering firm will be
responsible for providing comprehensive professional services that support the planning, design, procurement,
construction, and close‑out of the project.
1. Preliminary Engineering & Coordination
Develop complete engineering plans, specifications, and cost opinions in close coordination with the City of
Dublin.
Conduct site evaluations, confirm existing conditions, and assess design alternatives to support project
objectives such as improved operational performance, durability, and long‑term efficiency.
Ensure all design documents conform to applicable federal, state, and local codes, standards, and SEID
program requirements.
2. Permitting & Regulatory Compliance
Prepare and submit all necessary permit applications required for the project, including environmental,
wastewater, construction, and state/federal approvals.
Ensure all documents and materials fully meet Build America, Buy America (BABA) requirements, and
incorporate all required language into project specifications.
Assist the City in meeting all federal compliance obligations, including SEID documentation and 2 CFR 200
requirements.
RFQ #26-0227-01 – SEID Grant Engineering Services
4
3. Bidding & Procurement Support
Prepare complete bid packages and procurement documents in accordance with Georgia procurement statutes
and federal guidelines.
Assist the City with advertising, bidder inquiries, pre‑bid meetings, bid openings, and evaluation of contractor
bids.
Support the City in verifying bidder certifications and required BABA manufacturer documentation.
4. Construction Administration & Oversight
Provide construction administration services throughout the duration of the project, including:
o Review and approval of contractor submittals, schedules, and shop drawings.
o Engineering firm shall perform one site visit per week at minimum, with additional visits as needed to
support construction progress.
o Review and recommendation of contractor pay applications and change orders.
o Coordination with the contractor to resolve field issues promptly and effectively.
5. SEID Grant Support & Documentation
Maintain all records and provide required SEID reporting, including progress reports, compliance
documentation, and close‑out materials.
Collect and verify all BABA certifications from manufacturers and contractors.
Ensure all documentation meets SCRC and federal audit requirements.
6. Project Close‑Out
Conduct final inspections and verify completion of all work.
Prepare as‑built drawings, warranties, operation and maintenance manuals, and all required close‑out
certifications.
Assist the City with final SEID reporting and compliance verification.
2. QUALIFICATIONS REVIEW PROCESS
Selection of the engineering firm will be a multi-step process. The City of Dublin reserves the right to reject any or all
statements of qualifications, and to waive technicalities and informalities at the discretion of the City of Dublin.
Qualification Ranking is initiated with this RFQ, which is issued for the purpose of acquiring Statements of
Qualifications from prospective engineering firms. A selection of finalist firms will be made by a Selection Committee
consisting of representatives of the Owner. The Selection Committee will review Statements of Qualifications submitted
in response to this RFQ. To be deemed eligible for evaluation, firms must meet the following minimum qualifications:
Minimum Qualifications Required
Preparation of final design, plans, and specifications.
The securing of all necessary permits and clearances as applicable to comply with state and federal mandates. For
this project the engineering will be required to provide engineering plans/drawings showing all dimensions drawn to
current engineering standards and the required plans in order for the contractor to apply for permits.
Preparation of bid and contract documents, including advertising and bidding procedures, holding the bidders
conference, bid openings, and evaluations.
Post-award services, including securing the construction firm’s certifications and review of specifications,
warranties, operation manuals, and as-built drawings.
Construction services including supervision/administration of construction, review of payment requests, change
orders, and other coordination with the construction firm. Periodic construction review (at least one visit per week
during regular working hours) and other work as required in assuring proper execution of the work. Periodic
construction reviews must ensure that the contractor’s methods comply with approved plans and specifications.
Construction close-out, final inspection, project certification, and coordination with the City of Dublin and the
Southeast Crescent Regional Commission to provide periodic updates to satisfy SEID program requirements.
The engineer shall fully understand the Build America, Buy America (BABA) provisions of this project. All construction
contracts furnished or prepared by the engineer shall include required language. Further, the engineer shall be
RFQ #26-0227-01 – SEID Grant Engineering Services
5
responsible for obtaining all required BABA documentation (i.e. manufacturers’ certifications) during construction.
The Selection Committee will then evaluate the submittals, which have met the above minimum qualifications. Criteria
for the evaluation are listed below:
Criteria for evaluation of Statements of Qualifications
15% Factor Stability of the firm.
40% Factor Firm’s relevant project experience and qualifications.
25% Factor Firm’s suitability for the project.
20% Factor Firm’s management plan to provide engineering services for the project.
Final selection of the engineering firm will proceed following interviews with the shortlisted finalists. Upon
completion of the interview process, the City will identify the firm deemed most qualified. That firm, and only
that firm, will be invited to submit a detailed fee proposal in accordance with instructions issued by the City.
The successful engineering firm will be determined based on the Selection Committee’s evaluation of the
interviews and all other factors outlined in this RFQ.
3. SCHEDULE OF EVENTS
The following Schedule of Events represents the Owner’s best estimate of the schedule that will be followed. All times
indicated are Eastern. The Owner reserves the right to adjust the schedule as the Owner deems necessary.
Schedule
A. Owner issues public advertisement of RFQ
B. Mandatory Pre-Proposal Meeting
C. Deadline for submission of written questions and requests for clarification
D. Answers to all written questions posted
E. Qualification Proposal Due
F. Finalists will be notified
G. Finalist engineering firms interviews
H. Selected engineering firm notified
I. Contract negotiations as needed
J. Contract Awarded
2/27/26
3/12/26 10:00AM
3/23/26 2:00PM
3/25/26
4/01/26 2:00PM
4/02/26
4/07/26 TBD
4/17/26
4/17-24/26 TBD
4/27/26
4. SUBMITTAL OF QUESTIONS AND REQUESTS FOR CLARIFICATION
It is the responsibility of each respondent to examine the entire RFQ, seek clarification in writing, and review its submittal
for accuracy before submitting the document. Once the submission deadline has passed, all submissions will be final.
The Owner will not request clarification from individual respondents relative to their submission but reserves the right to
ask for additional information from all parties who have submitted qualifications. Questions about any aspect of the RFQ
or the project, shall be submitted in writing (e-mail) to:
David Sawyer, Purchasing Director, e-mail: sawyerd@dublinga.org
The deadline for submission of questions relating to the RFQ is the time and date shown in the Schedule of
Events. All relevant and significant questions that have been submitted in writing prior to the deadline will be compiled,
and answers will be posted.
5. INSTRUCTIONS FOR PREPARING STATEMENTS OF QUALIFICATIONS
Submittals must be prepared in a manner that when printed would typically fit on standard (8 ½” x 11”) paper. Responses
RFQ #26-0227-01 – SEID Grant Engineering Services
This page summarizes the opportunity, including an overview and a preview of the attached documents.