RFQ-CMAR 26-600 Shreveport Regional Airport Air Traffic Control Tower Relocation Project
| Agency: | City of Shreveport |
|---|---|
| State: | Louisiana |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | May 11, 2026 |
| Due Date: | Jun 4, 2026 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
RFQ-CMAR 26-600 Shreveport Regional Airport Air Traffic Control Tower Relocation Project
Attachment Preview
| CMAR Total Fee Proposal | |
|---|---|
| SUMMARY | TOTAL |
| Preconstruction Services (Not To Exceed) Est. 6 Month Duration Construction Management Fee __________% Percentage of Est. Total Cost of Work | $200,000.00 $ |
| TOTAL CMAR FEE PROPOSAL | $ |
Shreveport Regional Airport
Construction Management Fee Proposal
Air Traffic Control Tower Relocation
Date:
Respondent Entity Name:
Est. Total Cost of Work: $24,889,796
CMAR Total Fee Proposal
SUMMARY TOTAL
Preconstruction Services (Not To Exceed)
$200,000.00
Est. 6 Month Duration
Construction Management Fee __________%
$
Percentage of Est. Total Cost of Work
TOTAL CMAR FEE PROPOSAL $
Note: Only Proposers who are invited for an interview shall prepare a Proposer's Fee proposal for the Construction Phase
(Exhibit E). This shall be placed in a separate sealed envelope and be submitted at the beginning of the interview. The
sealed envelope will be opened and used as part of the evaluation of the shortlisted firms after the interview.
The fee proposal is for procurement processes and evaluation only. Any and all proposed fees will follow the terms and
condi(cid:415)ons of the contract and FAA regula(cid:415)ons for conversion to a fixed fee at the (cid:415)me of contract.
EXHIBIT "E" CONSTRUCTION MANAGEMENT FEE PROPOSAL
| Shreveport Regional Airport Air Traffic Control Tower Relocation Cost Estimate Summary Updated: 05/07/2026 | |
| CSI Division Description Total | |
| 01 00 00 General Requirements ($ 1,140,000.00) 02 00 00 Existing Conditions ($ - ) 03 00 00 Concrete ($ 1,882,162.00) 04 00 00 Masonry ($ 184,240.00) 05 00 00 Metals ($ 1,139,510.00) 06 00 00 Woods, Plastics + Composites ($ 227,740.00) 07 00 00 Thermal + Moisture Protection ($ 2,185,343.00) 08 00 00 Openings ($ 1,139,250.00) 09 00 00 Finishes ($ 1,180,281.00) 10 00 00 Specialties ($ 154,190.00) 11 00 00 Equipment ($ 1,514,000.00) 12 00 00 Furnishings ($ - ) 13 00 00 Special Construction ($ - ) 14 00 00 Conveying Equipment ($ 335,000.00) 21 00 00 Fire Suppression ($ 268,120.00) 22 00 00 Plumbing ($ 329,010.00) 23 00 00 HVAC ($ 612,275.00) 25 00 00 Integrated Automation ($ 192,475.00) 26 00 00 Electrical ($ 1,701,010.00) 27 00 00 Communications ($ 132,110.00) 28 00 00 Electronic Safety + Security ($ 451,405.00) 31 00 00 Earthwork ($ 1,788,311.00) 32 00 00 Exterior Improvements ($ 734,243.00) 33 00 00 Utilities ($ 2,849,145.00) Escalation (Assumes 12 Months) ($ 1,409,787.00) Contingency ($ 3,340,189.00) | |
| ($24,889,796.00) |
Shreveport Regional Airport
Air Traffic Control Tower Relocation
Cost Estimate Summary
Updated: 05/07/2026
CSI Division Description Total
01 00 00 General Requirements ($ 1,140,000.00)
02 00 00 Existing Conditions ($ - )
03 00 00 Concrete ($ 1,882,162.00)
04 00 00 Masonry ($ 184,240.00)
05 00 00 Metals ($ 1,139,510.00)
06 00 00 Woods, Plastics + Composites ($ 227,740.00)
07 00 00 Thermal + Moisture Protection ($ 2,185,343.00)
08 00 00 Openings ($ 1,139,250.00)
09 00 00 Finishes ($ 1,180,281.00)
10 00 00 Specialties ($ 154,190.00)
11 00 00 Equipment ($ 1,514,000.00)
12 00 00 Furnishings ($ - )
13 00 00 Special Construction ($ - )
14 00 00 Conveying Equipment ($ 335,000.00)
21 00 00 Fire Suppression ($ 268,120.00)
22 00 00 Plumbing ($ 329,010.00)
23 00 00 HVAC ($ 612,275.00)
25 00 00 Integrated Automation ($ 192,475.00)
26 00 00 Electrical ($ 1,701,010.00)
27 00 00 Communications ($ 132,110.00)
28 00 00 Electronic Safety + Security ($ 451,405.00)
31 00 00 Earthwork ($ 1,788,311.00)
32 00 00 Exterior Improvements ($ 734,243.00)
33 00 00 Utilities ($ 2,849,145.00)
Escalation (Assumes 12 Months) ($ 1,409,787.00)
Contingency ($ 3,340,189.00)
($24,889,796.00)
EXHIBIT "A" COST ESTIMATE SUMMARY
See Also
Bid Number Description Date Issued Bid Open Date/Time 50005-003001 MEB 6TH & 7TH
State Government of Louisiana
Due by 11/05/2026
Bid Number Description Date Issued Bid Open Date/Time JPP-BidEvent#334 Helios Lift Station Generator,
State Government of Louisiana
Due by 1/12/2027
Date: Thursday, November 5, 2026 Time: 11:00 AM Description: REQ6834 Domestic Water Boiler
City of Baton Rouge
Due by 11/05/2026
Bid Number Description Date Issued Bid Open Date/Time CATS-2026-FloridaTerminal-003 2222 Florida Terminal Improvement
State Government of Louisiana
Due by 12/07/2026