1411985846 (RFP) TRALC Class Transformers for JEA Inventory FY25 - FY27
The purpose of this Request for Proposal (RFP) is to evaluate and select a vendor that can provide TRALC class
transformers for JEA Inventory FY25 – FY27 that meet the technical specifications and provide the best value to JEA
as described in this Solicitation (the "Work") and to determine the best method for JEA to procure the Work with
regards to pricing, lead time, quality, design, and workmanship.
The required reports are as follows: iSupplier Open PO – This report must be completed weekly and include the
expected delivery date and any additional comments regarding the orders. Registering for iSupplier is required to
complete this report. The report will be utilized to determine compliance with deliver and lead times. Monthly review
meetings may be held. Failure to comply with lead times could result in JEA terminating the Contract for Default.
TRALC002 – Quantity 3
TRANSFORMER, 1500/2250 KVA, 13200 DELTA VOLT PRIMARY 480Y/277 VOLT SECONDARY CAST COI,
- DEL TO BE SCH 72 HOURS IN ADVANCE OF ARRIVAL, SUITABLE FOR FORKLIFT UNLOADING
DELIVER TO 2325 EMERSON ST 32207
Approved Manufacturer(s):
Federal Pacific
MGM Transformer
ABB
Square D
TRALC003 – Quantity 1
TRANSFORMER, DRY TYPE SUBMERSABLE, 1000KVA, 13200 DELTA VOLT PRIMARY 480Y/277 VOLT
SECONDARY, HIGHSIDE EATON SWITCH, (DEL TO BE SCH 72 HOURS IN ADVANCE OF ARRIVAL,
SUITABLE FOR FORKLIFT UNLOADING, DELIVER TO 2325 EMERSON ST 32207)
Approved Manufacturer(s):
ABB
TRALC004 – Quantity 1
TRANSFORMER, DRY TYPE SUBMERSABLE, 1500KVA, 13200 DELTA VOLT PRIMARY 480Y/277 VOLT
SECONDARY, HIGHSIDE EATON SWITCH, (DEL TO BE SCH 72 HOURS IN ADVANCE OF ARRIVAL,
SUITABLE FOR FORKLIFT UNLOADING, DELIVER TO 2325 EMERSON ST 32207)
Approved Manufacturer(s):
ABB
TRALC005 – Quantity 1
TRANSFORMER, DRY TYPE SUBMERSABLE, 2000KVA, 13200 DELTA VOLT PRIMARY 480Y/277 VOLT
SECONDARY, HIGHSIDE EATON SWITCH, ( DEL TO BE SCH 72 HOURS IN ADVANCE OF ARRIVAL,
SUITABLE FOR FORKLIFT UNLOADING, DELIVER TO 2325 EMERSON ST 32207)
Approved Manufacturer(s):
ABB
A more detailed description of the Work is provided in the Technical Specifications included as an Appendix to this
Solicitation.
USE THIS LINK TO ACCESS THE SOLICITATION ON ZYCUS:
https://zsn.zycus.com/guest/genericRegister/JEA074/iSource/960410/
Response Due Date: May 20, 2025
Response Due Date: May 28, 2025
Response Due Date: June 10, 2025