25RFP021025K-CRB Progressive Design/Build for Boat Rock Road Sanitary Sewer Extension
| Agency: | State Government of Georgia |
|---|---|
| State: | Georgia |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Mar 17, 2025 |
| Due Date: | Apr 30, 2025 |
| Solicitation No: | PE-66096-NONST-2025-000000089 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
| Event ID | Event Title | Government Entity | Start Date (ET) | End Date (ET) |
| PE-66096-NONST-2025-000000089 | 25RFP021025K-CRB Progressive Design/Build for Boat Rock Road Sanitary Sewer Extension | Fulton County Purchasing Dept |
Mar 17, 2025 @ 07:52 AM
|
Apr 30, 2025 @ 11:00 AM
|
Start Date: Mar 17, 2025 @ 07:52 AM ET
End Date:
Apr 30, 2025 @ 11:00 AM ET
Description
This project will require all survey, engineering, geotechnical engineering, quality control, etc., for the 90% design to produce a GMP for the construction of the new Boat Rock Road Sanitary Sewer Extension.¿ This project includes but is not limited to the following:¿
The proposed project includes installing approximately 24,000 linear feet of 8¿ sanitary sewers. The new sewers are broken into the general streets, as shown below.
Boat Rock Road and Binford Place:¿ Approximately 8,350 LF. of 8¿ and 10¿ diameter sewers¿
Campbellton Road and New Hope Road: Approximately 7,800 LF. of 8¿ and 10¿ sewers
Elva Drive and in an easement: Approximately 7,850 LF. of 8¿ and 10¿ sewers
Provide sewer lateral connections to approximately 150 - 160 properties.
The design approach is to place the proposed sewer line within the roadway right-of-way and minimize the need for new easement acquisition unless required by hydraulic limitations. Fulton County has run the hydraulic model and provided the pipe diameters for the proposed sewers.
The selected Progressive Design-Build firm (PD/B) will provide all survey, geotechnical, engineering, design, etc. to a 90% design stage to provide a GMP for the following:
Boat Rock Road and Binford Place:¿ Approximately 8,350 LF. of 8¿ diameter sewers and manholes complete in place, including pavement milling and resurfacing, tree planting, and final restoration of disturbed areas. ¿
Campbellton Road and New Hope Road: Approximately 7,800 LF. of 8¿ sewers and manholes complete in place, including pavement milling and resurfacing, tree planting, and final restoration of disturbed areas.¿
Elva Drive and in an easement: Approximately 7,850 LF. of 8¿ sewers and manholes complete in place, including pavement milling and resurfacing, tree planting, and final restoration of disturbed areas.¿ Provide sewer lateral connections to approximately 150 - 160 properties.
| Code | Description |
| 91381 | Maintenance and Repair, Sewer and Storm Drain, Including Removal |
| 91345 | Construction, Sewer and Storm Drain |
| 91063 | Public Utilities: Water, Sewer and Gas Maintenance and Repair Services |
Craig Bogan, APA
craig.bogan@fultoncountyga.gov
404-612-7660
See Also
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-66716-NONST-2027-000000001
State Government of Georgia
Due by 10/22/2026
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-62000-NONST-2027-000000050
State Government of Georgia
Due by 10/15/2026
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-66992-NONST-2027-000000033
State Government of Georgia
Due by 9/25/2026
SOLICITATION DESCRIPTION DUE DATE RFB No. 27-0011 Tennis Court Resurfacing at Lakebottom Park
Consolidated Government of Columbus
Due by 10/07/2026