| Agency: | State Government of North Carolina |
|---|---|
| State: | North Carolina |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Apr 19, 2026 |
| Due Date: | May 8, 2026 |
| Solicitation No: | 373GHS00008 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
| Solicitation Number: | 373GHS00008 |
| Project Title: | RFI : Deaerator (DA) Tank Replacement |
| Description: | Granville Health System is issuing this Request for Information (RFI) to qualified mechanical contractors, boiler system specialists, and engineering firms regarding the replacement of the existing Deaerator (DA) tank system serving the hospital’s central energy plant. Objectives of this RFI include: • Coordinate on-site vendor assessments with GHS representatives • Obtain engineering recommendations for replacement of the existing DA tank system • Understand installation requirements, phasing impacts, and operational considerations • Gather budgetary pricing to support immediate replacement. This RFI is for planning and information only. No award will be made solely from this request. |
| Opening Date: | 5/8/2026 2:00 PM |
| Posted Date: | 4/19/2026 |
| Status: | Open |
| Department: | GRANVILLE HEALTH SYSTEM |
|
Solicitation Number
*
373GHS00008
|
Department
GRANVILLE HEALTH SYSTEM
|
Status Reason
Open
|
|
|
Opening Date
2026-05-08T14:00:00.0000000
|
Posted Date
*
2026-04-18T15:48:06.0000000Z
|
Primary Commodity Code
Boiler and furnace construction and maintenance services
|
|
|
Mandatory Conference/Site Visit
—
—
|
Special Instructions
please schedule site visits ASAP with the contacts listed in RFI
|
Solicitation Type
*
Select RFP IFB RFI
|
|
|
Owner
Zeb Barnette
|
|||
|
Description
Granville Health System is issuing this Request for Information (RFI) to qualified mechanical contractors, boiler system specialists, and engineering firms regarding the replacement of the existing Deaerator (DA) tank system serving the hospital’s central energy plant. Objectives of this RFI include: • Coordinate on-site vendor assessments with GHS representatives • Obtain engineering recommendations for replacement of the existing DA tank system • Understand installation requirements, phasing impacts, and operational considerations • Gather budgetary pricing to support immediate replacement. This RFI is for planning and information only. No award will be made solely from this request.
|
|||
Granville Health System
Request for Information (RFI)
Deaerator (DA) Tank Replacement - Central Energy Plant
1. Purpose
Granville Health System is issuing this Request for Information (RFI) to qualified mechanical contractors, boiler system specialists, and engineering firms regarding the replacement of the existing Deaerator (DA) tank system serving the hospital's central energy plant.
Objectives of this RFI include:
Coordinate on-site vendor assessments with GHS representatives
Obtain engineering recommendations for replacement of the existing DA tank system
Understand installation requirements, phasing impacts, and operational considerations
Gather budgetary pricing to support immediate replacement.
This RFI is for planning and information only. No award will be made solely from this request.
2. Project Scope
Granville Health System intends to replace the existing DA tank, including evaluation and coordination with the current boiler plant.
Scope may include:
Replacement of existing Deaerator (DA) tank
Evaluation and replacement of feedwater pumps (if required)
Associated piping, valves, and controls
Integration with existing boiler systems (two main boilers)
Electrical and control system upgrades (as needed)
Structural support, pad, or rigging considerations
Insulation and system commissioning
The DA Tank currently supports a closed-loop boiler feedwater system serving the hospital campus and returning to the central energy plant.
3. Requested Information
3.1 System Recommendations
Tank construction materials and expected lifespan
Redundancy considerations for healthcare environments
Recommended deaerator configuration
Guaranteed oxygen removal performance (ppb)
Operating pressure and temperature ranges
Storage Volume and effective hold time
Turndown capability
Materials and Construction of proposed DA Tank
Controls and Instrumentation
3.2 Compliance & System Standards
ASME Boiler and Pressure Vessel Code compliance
National Board Inspection Code (NBIC) considerations
Applicable state and local boiler/mechanical codes
OSHA requirements for installation and operation
3.3 System Interface & Utility Requirements
Steam and condensate return integration requirements
Water quality considerations and chemical treatment coordination
Venting and exhaust requirements
Blowdown and drainage requirements
Electrical service requirements
Control system integration with existing plant systems
3.4 Installation Requirements
Expected construction duration
Phasing requirements to maintain boiler operation
Rigging and access constraints within existing energy plant
Measures for safety, noise control, and operational continuity
3.5 Service & Long-Term Maintenance
Warranty periods and coverage levels
Recommended preventative maintenance (PM) programs
Spare parts availability and lead times
Expected lifecycle of system components
3.6 Budgetary Information
Provide rough order-of-magnitude pricing for:
Engineering and design fees
DA tank equipment
Pumps, controls, and accessories
Installation labor
Piping and mechanical modifications
Electrical and controls integration
Temporary system provisions (if required)
Commissioning and startup
All pricing should be structured to support immediate replacement.
4. Vendor Site Visits
Review of existing DA tank and boiler plant
Inspection of feedwater, condensate return, and piping systems
Evaluation of mechanical room layout and access
Identification of rigging and installation constraints
Assessment of phasing limitations and operational risks
Target Date for completed initial site visits: 5/1/2026
Contacts for coordination: Zeb Barnette, Jonathan Pernell
5. Response Format
Company information and primary contacts
Relevant experience with boiler plant / DA tank systems (healthcare preferred)
Credentials, licensing, and mechanical/engineering capabilities
Recommended system approach and configuration
Technical literature or product data sheets
Lead times for equipment and mobilization
Installation approach and phasing plan
Maintenance and service offerings
Preferred site visit dates
Budgetary pricing (design, labor, equipment, etc.)
6. Submission Deadline
Responses requested by: 5/8/2026
7. Contact Information
Granville Health System - Facilities / Operations
Primary Contact: Jonathan Pernell, Facilities Director
Email: jpernell@granvillemedical.com
Phone: 919-691-0708
Secondary Contact: Zeb Barnette, Project Manager
Email: zbarnette@granvillemedical.com
Phone: 336-504-0068
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Bridge Repairs: Hawley Lane, Filter Plant Drive & Campbell Avenue Closing date August
City of Fayetteville
Bid Due: 8/11/2026
MA00030 SBE Incidental Concrete Installation & Repairs, Upon Request (ID/IQ) In District 2
Division of Highways
Bid Due: 8/19/2026
D12-12224960 POC GMR12.GAS.1PB - BEAM END REPAIR ON BRIDGE NO. 22 IN GASTON
Division of Highways
Bid Due: 8/11/2026
D12-12224960 POC GMR12.GAS.1PB- BEAM END REPAIR ON BRIDGE NO. 22 IN GASTON COUNTY
Division of Highways
Bid Due: 8/11/2026