Request for Proposals: Dosewallips River - Rocky Brook Reach
|
| Category: | Health Dept |
| Status: | Open |
|
615 Sheridan Street
Port Townsend, WA 98368
www.JeffersonCountyPublicHealth.org
JEFFERSON COUNTY PUBLIC HEALTH
REQUEST FOR PROPOSALS
Dosewallips River Habitat Restoration:
Rocky Brook Reach Final Design and Permitting
Jefferson County, WA
Proposal Due: Transmit electronically to tpokorny@co.jefferson.wa.us on or before May 13, 2026
Questions Due: Email tpokorny@co.jefferson.wa.us on or before May 4, 2026
Public Notice: Posted to Jefferson County Business Opportunities
(https://www.co.jefferson.wa.us/428/Business-Opportunities) on April 19, 2026; Noticed in The Leader
and Seattle Daily Journal of Commerce on April 22, 2026
Project Number: WQ-26-020
Category: Engineering (A & E)
Page Limit: 10 pages double-sided, not to include cover letter or resumes. Please provide in Calibri
(body) 11 font with minimum 1" margins
Example projects: 5-10 in western Washington only
Experience Threshold: Timeframe for relevant experience is 10 years
Anticipated Project Timeframe: June 1, 2026 - June 1, 2027
1. Introduction
Jefferson County, hereafter referred to as the Agency, is seeking a multi-disciplined engineering firm to
provide civil and structural engineering, surveying, geotechnical engineering, geology, hydrology and
hydraulic analysis, and environmental assessments and permitting (Exhibit A) to develop preliminary
and final habitat restoration designs and associated permits for a portion of the Dosewallips River and
floodplain (River Mile 3 .6 to 4.0) upstream of the community of Brinnon, WA. The project is funded
through a grant agreement between Jefferson County and the Washington State Recreation and
Conservation Office (RCO) Salmon Recovery Funding Board (SRFB). The primary deliverable is a
construction-ready design package including all necessary local, state, and federal permit applications to
restore critical spawning and rearing habitat for Hood Canal summer chum and Puget Sound Chinook
salmon. The Rocky Brook Resiliency Plan (Exhibit B) was produced in 2024 as phase I of this effort and
contains flood modeling, geomorphic and habitat assessments, and a conceptual design.
Since 2003, Jefferson County has been working with willing landowners and partners to reduce flood risk
and improve habitat for listed salmonids in the lower Dosewallips River. Currently, the County is working
progressively towards engineered restoration designs in the Brinnon, Powerlines and Rocky Brook
reaches.
Preliminary and final designs for the Rocky Brook Reach will guide access, construction and related
activities with the goal of improving the quality and quantity of habitat for Hood Canal Summer Chum
and Puget Sound Chinook salmon. Two private landowners are cooperating with the project to allow
ground-based construction. Additional landowners or partners include Jefferson County, Washington
Community Health Environmental Public Health
Developmental Disabilities 360-385-9444
360-385-9400 (f) 360-379-4487
360-385-9401 (f) Alwa ys w orking for a safer and healthier community
State Parks and the Department of Natural Resources. Designs are to be accomplished in coordination
with the Jamestown and Port Gamble S'Klallam Tribes, the Lower Elwha Klallam, Suquamish, and the
Skokomish Tribes as well as the Hood Canal Lead Entity and the interested public through local meetings
of the local Dosewallips River Collaborative and/or South County Task Force groups. Neighborhood and
individual landowner meetings will also be held in support of this project.
2. Desired Team Experience
The Agency requires a consultant team with a balanced skill set and demonstrated expertise in salmonid
biology, river ecology and natural processes, civil engineering, fluvial geomorphology, hydraulic
modeling, and geology. The design team must include licensed professional engineers (Washington) and
one or more licensed professional geologists with at least five years of experience in river restoration
specifically within comparable western Washington watersheds. Desired experience includes two-
dimensional (2D) hydraulic modeling using HEC-RAS 6.4.1 or later, the design and stability analysis of
Engineered Log Jams (ELJs), side channel excavation, and the preparation of comprehensive federal and
state permit packages. Consultants must demonstrate a history of successful collaboration with Tribes,
agencies, and private landowners.
3. Project Descriptions and Scopes of Work
The Rocky Brook Reach, located between River Mile (RM) 3.5 and 6.7, is a wood-deficient, primarily
straight channel characterized by channel incision and loss of floodplain connectivity. Utilizing the
Dosewallips River Rocky Brook Reach Resiliency Plan, the consultant will develop preliminary and final
designs for RM 3.6 to 4.0 to address alteration of the mainstem and floodplain, the loss of side channel
habitat, and the restriction of natural channel migration zone processes. The designs will restore habitat
for Hood Canal summer chum and Chinook salmon by improving opportunities for spawning, rearing
and migration, and improving sediment transport, pool formation, and in-channel habitat complexity at
flows typical for these targeted salmon life histories. Through a range of actions to include engineered
log jams and side channel excavation and enhancements, the project will 1) promote sediment sorting,
bar aggradation, and pool development, 2) stabilize channel migration to protect riparian plantings, and
3) enhance existing side channel habitat and promote conveyance and a diversity of side channel habitat
types. Designs will incorporate climate-influenced flow and channel migration projections utilizing a
hydraulic model built on 2023 LiDAR and surface water change detection. The final design effort will
prepare all permit applications to include the CLOMR/LOMR process. Tasks will also include additional
steps to restore floodplain forests and treat invasive weeds. Formal and informal meetings will be held
in-person in Brinnon or the Rocky Brook Reach as well as online or by phone. Ongoing communications
between the Agency and Consultant will occur primarily via email and through online or phone-based
meetings held at least biweekly. Occasional impromptu phone communications with the Agency or
landowner(s) may also become necessary to address particularly time-sensitive matters.
4. Deliverables and Performance Standards
Work must be performed consistently with current requirements of RCO Manual 18: Salmon Recovery
Grants and RCO Manual 8: Reimbursements. Deliverables for both reaches shall include:
* Hydraulic Modeling: Updated 2D hydraulic modeling incorporating climate-influenced flow and
channel migration projections.
* Design Packages: Preliminary and final design drawings (AutoCAD), technical specifications, and
Basis of Design Reports that meet SRFB Review Panel requirements.
2
| Criteria | Weight | Evaluation Focus |
|---|---|---|
| Specialized Experience & Technical Competence | 25%- 35% | Does the firm have at least 5 example projects that match the complexity, size, and scope of this solicitation? |
| Professional Qualifications | 20%- 25% | Are key personnel licensed/certified in the required disciplines? Does their individual experience match their proposed role? |
| Past Performance | 15%- 20% | Has the firm performed previous work, including multiple phases, on mainstem river channels with comparable flows to the Dosewallips? Were the firm's in-channel designs constructed successfully? |
| Capacity to Accomplish Work | 10%- 15% | Does the team have enough staff to handle this project given their current and projected workload? Are they prepared to meet milestones and the overall project deadline? |
| Knowledge of Locality | 5%- 10% | To what degree is the firm familiar with Jefferson County zoning, environmental conditions, geological features, FEMA and county floodplain regulations? |
| Secondary Criteria (Tiebreakers) | Varies | Small business participation, geographic proximity, and volume or magnitude of prior agency awards. |
* Permit Applications: Complete Joint Aquatic Resources Permit Application (JARPA) packages,
SEPA checklists, and all local land use permits. CLOMR/LOMR as required.
* Cultural Resources Documentation: Support for compliance with Governor's Executive Order
21-02 and Section 106 of the National Historic Preservation Act, including archaeological
monitoring of geotechnical investigations if required.
* Public Outreach: See Task 6 in Exhibit A
5. General Considerations and Compliance
* Nondiscrimination: Jefferson County ensures that Disadvantaged Business Enterprises (DBEs)
will be afforded full opportunity to submit proposals and will not be discriminated against.
* Cultural Resources: No ground-disturbing work may commence until the RCO has provided a
notice of cultural resources completion. If archaeological resources are discovered, work must
stop immediately.
* Invoicing: Reimbursement for expenses, including those from subcontractors, must meet
Washington State travel and other applicable reimbursement guidelines. Receipts must be
provided that are scanned (not photographed) and fully legible including the date and other
purchase details. Lodging must include the name(s) associated with each room. Any receipt
including the purchase of alcohol will not be reimbursed. Check with the Agency in advance for
additional specific backup and other requirements and instructions.
6. Evaluation Process and Criteria
Proposals will be rated by a selection committee of Agency staff based on the following criteria:
Criteria Weight Evaluation Focus
Specialized Experience 25%- Does the firm have at least 5 example projects that match the
& Technical 35% complexity, size, and scope of this solicitation?
Competence
Professional 20%- Are key personnel licensed/certified in the required disciplines?
Qualifications 25% Does their individual experience match their proposed role?
Past Performance 15%- Has the firm performed previous work, including multiple phases,
20% on mainstem river channels with comparable flows to the
Dosewallips? Were the firm's in-channel designs constructed
successfully?
Capacity to 10%- Does the team have enough staff to handle this project given
Accomplish Work 15% their current and projected workload? Are they prepared to meet
milestones and the overall project deadline?
Knowledge of Locality 5%- To what degree is the firm familiar with Jefferson County zoning,
10% environmental conditions, geological features, FEMA and county
floodplain regulations?
Secondary Criteria Varies Small business participation, geographic proximity, and volume or
(Tiebreakers) magnitude of prior agency awards.
3
| Receive Proposals electronically | May 13, 2026 |
|---|---|
| Selection Committee reviews proposals and selects consultant(s) for interview(s) | Third week in May 2026 |
| Conduct interview(s) | Third or fourth week in May 2026 |
| Recommendation to Department Director of highest-ranking consultant | Fourth week in May, 2026 |
| Scope of Work developed and reviewed | First week in June 2026 |
| Agreement execution | Late June 2026 |
| Meetings (landowners and/or public) begin | July 2026 |
| Field work begins | August 2026 |
| Cultural resources survey complete | Late October 2026 |
| Preliminary design complete | January 2027 |
| Final design complete | June 2027 |
| All associated documents and materials complete | June 2027 |
7. Anticipated Budget
The estimated cost for the tasks described in this RFP (see also Exhibit A) is $200,000.
Anticipated schedule
Receive Proposals electronically May 13, 2026
Selection Committee reviews proposals and selects Third week in May 2026
consultant(s) for interview(s)
Conduct interview(s) Third or fourth week in May 2026
Recommendation to Department Director of highest-ranking Fourth week in May, 2026
consultant
Scope of Work developed and reviewed First week in June 2026
Agreement execution Late June 2026
Meetings (landowners and/or public) begin July 2026
Field work begins August 2026
Cultural resources survey complete Late October 2026
Preliminary design complete January 2027
Final design complete June 2027
All associated documents and materials complete June 2027
Americans with Disabilities Act (ADA) Information
The Agency in accordance with Section 504 of the Rehabilitation Act (Section 504) and the
Americans with Disabilities Act (ADA), commits to nondiscrimination on the basis of disability, in all of its
programs and activities.
Equal Opportunity
Jefferson County Public Health in accordance with the provisions of Title VI of the Civil Rights Act of 1964
(78 Stat. 252.42 U.S.C. 2000d to 2000d-4) and the Regulations, hereby notifies all A & E firms that it will
affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged
business enterprises will be afforded full and fair opportunity to submit proposals in response to this
invitation and will not be discriminated against on the grounds of race, color, or national origin in
consideration for an award.
Funding
This project is funded through the Recreation and Conservation Office Salmon Recovery Funding Board
State Funds (Puget Sound Acquisition & Restoration) RCO #24-1096P. It is match to a federal funding
source as a federal subaward to the US Environmental Protection Agency Federal Award Identification
Number: CE-01J31901 in Federal Fiscal Year 2017.
4
Exhibit A
RCO Project Description and Tasks
Tasks may be subject to revision but, taken together, must result in completion of the
project as described below, performed consistently with RCO Manual 18 and Manual 8.
Jefferson County will utilize the data and information collected in the assessment and conceptual design
phase (Resiliency Plan for RM 3.4 to 5.8, attached) to develop preliminary and final designs for a pilot
project for RM 3.6 to 4.0 to address alteration of the mainstem and floodplain, the loss of side channel
habitat, and the restriction of natural channel migration zone processes. The goal of the overarching
project remains, to restore habitat for Hood Canal summer chum and Chinook salmon to improve
opportunities for spawning, rearing, and migration by improving sediment transport, pool formation, in-
channel habitat complexity at flows typical for these targeted salmon life histories. Through a range of
actions to include engineered log jams and side channel excavation and enhancement, the project will 1)
promote sediment sorting, bar aggradation, and pool development, 2) stabilize channel migration to
protect riparian plantings, and 3) enhance existing side channel habitats to promote conveyance and a
diversity of side channel habitat types. Designs will incorporate climate-influenced flow and channel
migration projections utilizing a hydraulic model built on 2023 LiDAR and topographic change detection
analysis. The County and contractor will continue to host meetings of the Dosewallips River
Collaborative, and with individual landowners, in order to gather and disseminate information across
the Brinnon community and to inform design development.
Task 1: Preliminary Design
Complete preliminary design, hydraulic modeling, engineering analysis, site visit, Basis of Design Report,
and construction cost estimate.
Task 2: Final Design
Complete draft final design, hydraulic modeling, engineering analysis, site visit, Basis of Design Report,
construction cost estimate, and special provisions.
Task 3: Cultural Resources
Cultural resources survey. Field delineation of wetlands and aquatic resources, reporting, impacts and
benefits analysis.
Task 4: Data Collection and Reporting
Background data analysis, field survey, reporting.
Task 5: Permit Applications
5
Preparation of permit applications including: JARPA form, WQ Monitoring Plan, HPA Pathway submittal,
ESA Consultation. Agency pre-application coordination and responses to agency data requests. Includes
pre-application coordination with FEMA. Does not include CLOMR preparation or submittal.
Task 6: Education and Outreach
* Rocky Brook Neighborhood: 1 in-person at Brinnon Community Center (BCC)
* Dosewallips River Collaborative Technical Work Group at the BCC: 1 in-person/online to inform
preliminary design; 1 in-person/online to inform final design
* Two private landowners: 3 in-person meetings with each over the length of the project. May
coincide with other tasks
* Jefferson County Public Works: up to 3 meetings, online
* Department of Natural Resources and Washington State Parks: 2 meetings total, online
* Presentation to the South County Task Force: 1 in-person at Brinnon Community Center
* Additional meetings, as needed: up to 4 in-person (various locations on Olympic or Kitsap
Peninsulas or Olympia)
6
Exhibit B
Rocky Brook Resiliency Plan
7
Dosewallips River
Rocky Brook Reach Resiliency Plan
August 2024
Tami Pokorny
Natural Resources Coordinator
Jefferson County Public Health Department
615 Sheridan Street 1900 N. Northlake Way, Suite 211
Port Townsend, WA 98368
Seattle, WA 98103
THIS PAGE INTENTIONALLY LEFT BLANK
Cover Photo: Looking upstream from River Mile 5 on the Lower Dosewallips River Rocky Brook reach on September 13th,
2023. A pattern observed through much of the river is shown, with limited instream wood leading to coarse substrate, low
flows, and floodplain disconnection, limiting available habitat for key salmonid species.
JEFFERSON COUNTY ROCKY BROOK RESILIENCY PLAN
TABLE OF CONTENTS
1 Executive summary ......................................................................................................................................... 1-1
2 Introduction .................................................................................................................................................... 2-1
2.1 Project Goals and Purpose Statement(s) .............................................................................................. 2-1
2.2 Project Location .................................................................................................................................... 2-1
2.3 Landowner Acknowledgment ............................................................................................................... 2-2
3 Reach History .................................................................................................................................................. 3-1
3.1 Recreation ............................................................................................................................................. 3-3
4 What does good aquatic habitat look like? .................................................................................................... 4-1
5 Reach Conditions ............................................................................................................................................ 5-1
5.1 Geology ................................................................................................................................................. 5-2
5.2 Channel and Floodplain Morphology .................................................................................................... 5-3
5.3 Sediment ............................................................................................................................................... 5-7
5.4 Hydrology and Hydraulics ..................................................................................................................... 5-8
5.4.1 Hydrology ................................................................................................................................. 5-8
5.4.2 Hydraulic Modeling ................................................................................................................ 5-11
5.5 Sediment Transport Dynamics ............................................................................................................ 5-17
5.6 Channel Migration History .................................................................................................................. 5-18
5.7 Large Wood ......................................................................................................................................... 5-20
5.8 Riparian and Wetland Communities ................................................................................................... 5-24
5.9 Salmonid Use and Existing Aquatic Habitat Conditions ...................................................................... 5-26
5.9.1 Hood Canal Summer Chum (Oncorhynchus keta) .................................................................. 5-27
5.9.2 Puget Sound Chinook Salmon (Oncorhynchus tshawytscha) ................................................ 5-28
5.9.3 Existing Habitat ...................................................................................................................... 5-28
5.10 The Warming Climate ......................................................................................................................... 5-32
5.10.1 Fisheries ................................................................................................................................. 5-32
5.10.2 River Morphology/Property Risk ........................................................................................... 5-32
6 Summary of Impairments ............................................................................................................................... 6-1
7 Resiliency Opportunities ................................................................................................................................. 7-1
7.1 Short Term Habitat Enhancement Opportunities ................................................................................. 7-1
7.1.1 Riparian Restoration ................................................................................................................ 7-1
7.1.2 Engineered Log Jams and Large Wood Placement .................................................................. 7-2
7.1.3 Side Channels ........................................................................................................................... 7-4
Natural Systems Design i
August 2024
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Bid Number: 26013 Bid Title: Davies Beach Decking Replacement Category: Construction Projects Status:
City of Lake Stevens
Bid Due: 7/30/2026
Follow TDA Auxiliary Water Supply (AWS) Backup Debris Management Active Contract Opportunity Notice
DEPT OF DEFENSE
Bid Due: 7/30/2026
Follow Mud Mountain Dam Bridge Pier Repair Active Contract Opportunity Notice ID W912DW26RA018
DEPT OF DEFENSE
Bid Due: 7/31/2026
Follow Repair Building 2008 Active Contract Opportunity Notice ID W912DW27RA010 Related Notice Department/Ind.
DEPT OF DEFENSE
Bid Due: 8/05/2026