Repair/Refurbish/Reinstall Fairbanks Morse 8300-GPM/18-Inch End-Suction Angle-Flow Centrifugal Wastewater Treatment Facility Raw Sewage Influent Pump
| Agency: |
West County Wastewater |
| State: |
California |
| Type of Government: |
State & Local |
| NAICS Category: |
- 221320 - Sewage Treatment Facilities
- 237110 - Water and Sewer Line and Related Structures Construction
- 811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance
|
| Posted Date: |
Nov 20, 2025 |
| Due Date: |
Dec 12, 2025 |
| Original Source: |
Please Login to View Page |
| Contact information: |
Please Login to View Page |
| Bid Documents: |
Please Login to View Page |
Project ID:
Title: Repair/Refurbish/Reinstall Fairbanks Morse 8300-GPM/18-Inch End-Suction Angle-Flow Centrifugal Wastewater Treatment Facility Raw Sewage Influent Pump
Addenda: 0
Release Date: 11/20/2025
Due Date: 12/12/2025
Post Information
Posted At:Thu, Nov 20, 2025 5:00 PMSealed Bid Process:Yes (Bids Sealed / Pricing Sealed)Private Bid:No
Overview
Contractor to repair, refurbish, and reinstall one (1) Fairbanks Morse Figure 5711, 18-inch vertical centrifugal pump (8,300 GPM, 29-ft TDH, 75 HP, 600 RPM) at the West County Wastewater raw sewage influent pump station (please see details below):
1. Repair & Refurbishment
-
Perform repairs per the vendor's disassembly/inspection report.
-
Use original pump drawings and specifications.
-
Follow industry-standard repair procedures.
2. Reinstallation
-
Reinstall the pump, motor, and all associated piping, electrical connections, and supports approximately 30 feet below grade.
3. Transportation
-
Transport the pump and related parts to and from the worksite.
4. Compliance & Permitting
-
Adhere to all applicable State and Local codes.
-
Obtain all necessary permits and licenses.
5. Schedule Management
-
Notify the Project Manager at least 72 hours in advance of any delays.
6. Inspection & Quality Control
-
Allow periodic inspections by West County Wastewater staff during work.
-
Participate in a final inspection and correct and deficiencies before final acceptance.
Timeline
IFB Issued:
November 20, 2025
Pre-Bid Conference (Non-Mandatory):
November 25, 2025, 1:00pm
Site Visit:
December 2, 2025, 11:00am
West County Wastewater - Water Quality & Resource Recovery Plant
2377 Garden Tract Road
Richmond, CA 94801
Questions, Requests for Approved Equals, and Requests for Clarifications ("RFCs") Due:
December 4, 2025, 5:00pm
WCW's Response to Questions, Requests for Approved Equals, and RFCs Due:
December 8, 2025, 5:00pm
Bid Submission Deadline:
December 12, 2025, 5:00pm
Notice of Award (tentative):
December 19, 2025
Notice to Proceed (tentative):
December 22, 2025
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.
Sign-up for a Free Trial, Government Bid Alerts
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Try One Week FREE Now
See Also
RFB for Santiago Pump Station Modifications, Contract No. SB-2026-1 The Orange County Water
Orange County Water District
Bid Due: 9/21/2026
RFB for Santiago Pump Station Modifications, Contract No. SB-2026-1 The Orange County Water
Orange County Water District
Bid Due: 9/21/2026
RFB for Santiago Pump Station Modifications, Contract No. SB-2026-1 The Orange County Water
Orange County Water District
Bid Due: 9/21/2026
Solicitation Number: RFB-IS-27200104 Title: 2368 APOLLO PARK IRRIGATION DEP WELL PUMP Department: Internal
County of Los Angeles
Bid Due: 8/26/2026