Pump Station 35 Improvements
Project ID: PW#2024-019
Title: Pump Station 35 Improvements
Addenda: 2
Release Date: 11/13/2024
Due Date: 12/18/2024
Post Information
Posted At:Wed, Nov 13, 2024 7:00 AMSealed Bid Process:Yes (Bids Sealed / Pricing Sealed)Private Bid:No
Overview
Project Description:
This Project will remove and replace existing mechanical, electrical, and structural features at Pump Station (PS) 35. The Work will require bypassing of wastewater flow throughout construction. General items of work include, but are not limited to:
-
Establishment of temporary sewer bypass.
-
Installation of approximately 800 linear feet of cured-in-place pipe (CIPP) liner into an 8-inch-diameter cast iron sewer force main.
-
Installation of new maintenance hole and connection to King County 42-inch-diameter existing sewer line; abandon existing connection.
-
Replacement of existing electrical service cabinet, conduit, and conductors.
-
Demolition of existing site features, structural elements, electrical elements, mechanical equipment and removal of lead-containing coatings.
-
Installation of new structural elements including a new roof slab, interior partition wall, hatches, beams, gratings, and guardrails.
-
Installation of new electrical service and power equipment, including variable frequency drive (VFD) motor starters and on-site generator.
-
Installation of new mechanical equipment, including pumps, valves, process piping, HVAC (i.e. ventilation), and odor control.
-
Installation of new instrumentation including a wastewater flow meter.
-
Restoration of existing landscaping and site features.
-
Post-construction testing and commissioning.
Engineer's Estimate:
$2,993,000 (not including sales tax)
Project Location:
The project location is addressed to 2734 NE 45th St; however the facility is located primarily on private property in the University Village shopping center in Northeast Seattle.
Timeline
Release Project Date:
November 13, 2024
Pre-Bid Site Inspection #1 (Mandatory for Bidders to attend at least 1 Pre-Bid Inspection):
November 20, 2024, 1:00pm
The project location is addressed to 2734 NE 45th St; however the facility is located primarily on private property in the University Village shopping center in Northeast Seattle. Please meet at the Pump Station for the pre-bid site inspection.
Pre-Bid Site Inspection #2 (Mandatory for Bidders to attend at least 1 Pre-Bid Meeting):
November 21, 2024, 1:00pm
The project location is addressed to 2734 NE 45th St; however the facility is located primarily on private property in the University Village shopping center in Northeast Seattle. Please meet at the Pump Station for the pre-bid site inspection.
Question Submission Deadline:
December 5, 2024, 5:00pm
Bid Open Date:
December 18, 2024, 2:00pm
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.
Sign-up for a Free Trial, Government Bid Alerts
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Try One Week FREE Now
See Also
Project ID: Title: Northwest Landing Pump Station Addenda: 0 Release Date: 5/20/2026 Due
Pierce County
Bid Due: 6/10/2026
Bid Title: RFP Asphalt Improvements and Seal Coating Category: Tribal Employment Rights Ordinance
Quinault Indian Nation
Bid Due: 6/12/2026
Project ID: Title: Three Rivers Transit Center Security Windows Addenda: 0 Release Date:
Ben Franklin Transit (BFT)
Bid Due: 6/16/2026
SKAGIT COUNTY Invitation to Bid: Apron Flap Replacement Project #FETM25-1 MUST BE AN
Skagit County
Bid Due: 6/15/2026