| Agency: | City of Kalamazoo |
|---|---|
| State: | Michigan |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Jul 7, 2026 |
| Due Date: | Jul 21, 2026 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Closing date
July 21, 2026, 03:30 PM
90900-029.0-Addendum 1 (PDF, 213KB)
90900-029.0-bid document (PDF, 33MB)
90900-029.0-distribution list (PDF, 93KB)
90900-029.0-specifications (PDF, 25MB)
Phase 1: Central Pump Station 1 Filter Media Replacement (As Needed) and Misc. Filter Improvements
SCOPE OF WORK
THE PROJECT LOCATION FOR PUMP STATION NO.1 (PS1), ALSO REFERRED TO AS CENTRAL WATER STATION IS 215 WEST STOCKBRIDGE, KALAMAZOO, MI 49001.
THE WORK CONSISTS OF MEDIA REPLACEMENT IN 2 GRAVITY FILTERS EACH WITH 4 FILTER CELLS, FILTER INLET PIPE, VALVE AND ACTUATOR REPLACEMENT. THE WORK ALSO INCLUDES CLEANING AND REPAIRS TO THE UNDERDRAIN SYSTEM AND NOZZLES. ALL OF THE FILTER MEDIA, INLET PIPES, VALVES, AND ACTUATORS WILL BE INCLUDED IN THE PRICE FOR THE WORK. HOWEVER, THE CITY MAY DECIDE TO ONLY DO THE WORK FOR SOME FILTERS CELLS, INLET PIPES, VALVES, AND ACTUATORS. FOR THE WORK NOT COMPLETED WILL BE CREDITED BACK TO THE CITY. SEE DRAWINGS FOR ADDITIONAL INFORMATION AND REQUIREMENTS
This contract includes, but is not limited to: All work as shown on the drawings and described in the specifications for the Phase 1: Central Pump Station 1 Filter Media Replacement (As Needed) and Misc. Filter Improvements Project.
The bidder shall furnish all labor, supervision, supplies, tools, equipment and other means necessary or proper for performing and completing the work. The bidder shall be responsible for the cleaning up of the job site and shall repair or restore all structures and property that may be damaged or disturbed during performance of the work to the satisfaction of the Public Services Department for the City of Kalamazoo.
This site is an active well-field. All equipment shall be kept in leak-free condition. Contractor shall keep a spill kit on site. The City’s draft Spill Contingency Plan for this site is included in these project specifications.
Work may begin within 10-days of Notice to Proceed. Cell 1D media replacement shall be scheduled immediately Notice to Proceed and be completed as soon possible. Only one filter cell shall be out of service at a time. Removal of filter cells from service shall be coordinated with the City. Alternate 1 is a like for like replacement that does not require EGLE PA 399 permitting. Alternative 2 requires EGLE PA 399 permitting and shall not be implemented until the permit is issued. Final completion shall be December 22, 2028.
CITY OF KALAMAZOO
DEPARTMENT OF PUBLIC SERVICES
PHASE 1: CENTRAL PUMP STATION 1 FILTER MEDIA
REPLACEMENT (AS NEEDED) AND MISC. FILTER
IMROVEMENTS
Contract No. 200-19743-24010
Project Manual
and
Drawings
Prepared by:
Ann Arbor, Michigan
May 8, 2026
Section Number Title
DIVISION 1 - GENERAL REQUIREMENTS
01005 Project Requirements
01110 Summary of Work
01210 Allowances
01220 Unit Prices
01290 Applications for Payment
01310 Project Coordination
01330 Submittals
01420 Definitions and Standards
01450 Quality Control Services
01500 Temporary Facilities
01530 Protection of Existing Facilities
01600 General Equipment Stipulations
01730 Cutting and Patching
01770 Contract Closeout
DIVISION 2 - SITE WORK
02225 Selective Demolition
DIVISION 3 - CONCRETE (Not Used)
DIVISION 4 - MASONRY (Not Used)
DIVISION 5 - METALS (Not Used)
DIVISION 6 - WOOD AND PLASTICS (Not Used)
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
(Not Used)
DIVISION 8 - DOORS AND WINDOWS (Not Used)
DIVISION 9 - FINISHES (Not Used)
DIVISION 13 - SPECIAL CONSTRUCTION
13225 Filter Materials
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 TC-1 5/8/2026
DIVISION 15 - MECHANICAL
15100 Pressure Process Piping
15110 Process Valves
OTHER SPECIFICATIONS
City of Kalamazoo Standard Specifications for Water Main and
Service Installation 2021
APPENDIX A - Filter Media Testing
A PPENDIX B - WesTech Cleaning Media Retaining Nozzles
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 TC-2 5/8/2026
SECTION 01005 - PROJECT REQUIREMENTS
PART 1 - GENERAL
1.01 DESCRIPTION
A. Scope of Work:
1. The Work to be done consists of the furnishing of all labor, materials, and equipment, and the
performance of all Work included in this Contract. The summary of the Work is presented in
Section 01110: Summary of Work.
2. Work Included:
a. The Contractor shall furnish all labor, superintendence, materials, power, light, heat, fuel,
water, tools, appliances, equipment, supplies, and means of construction necessary for
proper performance and completion of the Work. The Contractor shall obtain and pay for
all necessary construction permits. The Contractor shall perform and complete the Work in
the manner best calculated to promote rapid construction consistent with safety of life and
property and to the satisfaction of the Engineer, and in strict accordance with the Contract
Documents. The Contractor shall clean up the Work and maintain it during and after
construction, until accepted, and shall do all Work and pay all costs incidental thereto.
Contractor shall repair or restore all structures and property that may be damaged or
disturbed during performance of the Work.
b. The cost of incidental work described in these Project Requirements, for which there are no
specific Contract Items, shall be considered as part of the general cost of doing the Work
and shall be included in the prices for the various Contract Items. No additional payment
will be made therefore.
c. The Contractor shall provide and maintain tools and equipment as may be necessary, in the
opinion of the Engineer, to perform in a satisfactory and acceptable manner all the Work
required by this Contract. Only equipment of established reputation and proven efficiency
shall be used. The Contractor shall be solely responsible for the adequacy of his
workmanship, materials, and equipment, prior approval of the Engineer notwithstanding.
3. Public Utility Installations and Structures:
a. Public utility installations and structures shall be understood to include all poles, tracks,
pipes, wires, conduits, vaults, manholes, and all other appurtenances and facilities
pertaining thereto whether owned or controlled by the Owner, other governmental bodies,
or privately owned by individuals, firms, or corporations, used to serve the public with
transportation, traffic control, gas, electricity, telephone, sewerage, drainage, water, or other
public or private property which may be affected by the Work shall be deemed included
hereunder.
b. The Contract Documents contain data relative to existing public utility installations and
structures above and below the ground surface. These data are not guaranteed as to their
completeness or accuracy and it is the responsibility of the Contractor to make his own
investigations to inform himself fully of the character, condition, and extent of all such
installations and structures as may be encountered and as may affect the construction
operations.
c. The Contractor shall protect all public utility installations and structures from damage
during the Work. Access across any buried public utility installation or structure shall be
made to avoid any damage to these facilities. All required protective devices and
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-1 5/8/2026
construction shall be provided by the Contractor at his expense. All existing public utilities
damaged by the Contractor shall be repaired by the Contractor, at his expense. No separate
payment shall be made for such protection or repairs to public utility installations or
structures.
d. Public utility installations or structures owned or controlled by the Owner or other
governmental body which are shown on the Drawings to be removed, relocated, replaced,
or rebuilt by the Contractor shall be considered as a part of the general cost of doing the
Work and shall be included in the prices bid for the various Contract Items. No separate
payment shall be made therefore.
e. Where public utility installations of structures owned or controlled by the Owner or other
governmental body are encountered during the course of the Work, and are not indicated on
the Drawings or in the Specifications, and when, in the opinion of the Engineer, removal,
relocation, replacement, or rebuilding is necessary to complete the Work under this
Contract, such Work shall be accomplished by the utility having jurisdiction, or such Work
may be ordered, in writing by the Engineer, for the Contractor to accomplish. If such work
is accomplished by the utility having jurisdiction it will be carried out expeditiously, and the
Contractor shall give full cooperation to permit the utility to complete the removal,
relocation, replacement, or rebuilding as required. If such work is accomplished by the
Contractor, it will be paid for as extra work as provided in the Agreement.
f. The Contractor shall, at all times in performance of the Work, employ acceptable methods
and exercise reasonable care and skill so as to avoid unnecessary delay, injury, damage, or
destruction of public utility installations and structures; and shall, at all times in the
performance of the Work, avoid unnecessary interference with, or interruption of, public
utility services, and shall cooperate fully with the owners thereof to that end.
g. The maintenance, repair, removal, relocation, or rebuilding of public utility installations and
structures, when accomplished by the Contractor as herein provided, shall be done by
methods approved by the owners of such utilities.
1.02 DRAWINGS AND PROJECT MANUAL
A. Drawings: When obtaining data and information from the Drawings, figures shall be used in
preference to scaled dimensions, and large-scale drawings in preference to small-scale drawings.
B. Supplementary Drawings:
1. When, in the opinion of the Engineer, it becomes necessary to explain more fully the Work to
be done or to illustrate the Work further or to show any changes which may be required,
drawings known as Supplementary Drawings, with specifications pertaining thereto, will be
prepared by the Engineer, and the Contractor will be furnished one (1) complete set of
reproducible drawings (24 inches by 36 inches) and one (1) reproducible copy of the
specifications.
2. The Supplementary Drawings shall be binding upon the Contractor with the same force as the
Contract Drawings. Where such Supplementary Drawings require either less or more than the
estimated quantities of Work, credit to the Owner or compensation therefore to the Contractor
shall be subject to the terms of the Agreement.
C. Contractor to Check Drawings and Data:
1. The Contractor shall verify all dimensions, quantities, and details shown on the Drawings,
Supplementary Drawings, Schedules, Specifications, or other data received from the Engineer,
and shall notify him of all errors, omissions, conflicts, and discrepancies found therein. Failure
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-2 5/8/2026
to discover or correct errors, conflicts, or discrepancies shall not relieve the Contractor of full
responsibility for unsatisfactory work, faulty construction, or improper operation resulting
therefrom, nor from rectifying such conditions at his own expense. He will not be allowed to
take advantage of any errors or omissions, as full instructions will be furnished by the Engineer,
should such errors or omissions be discovered.
2. All schedules are given for the convenience of the Engineer and the Contractor and are not
guaranteed to be complete. The Contractor shall assume all responsibility for the making of
estimates of the size, kind, and quality of materials and equipment included in work to be done
under the Contract.
D. Specifications: The Technical Specifications consist of three (3) parts: General, Products, and
Execution. The General part of a Specification contains General Requirements which govern the
Work. The Products and Execution parts modify and supplement the General Requirements by
detailed requirements for the Work and shall always govern whenever there appears to be a conflict.
E. Intent:
1. All Work called for in the Specifications applicable to this Contract, but not shown on the
Drawings in their present form, or vice versa, shall be of like effect as if shown or mentioned in
both. Work not specified in either the Drawings or in the Specifications, but involved in
carrying out their intent or in the complete and proper execution of the Work, is required and
shall be performed by the Contractor as though it were specifically delineated or described.
2. The apparent silence of the Specifications as to any detail, or the apparent omission from them
of a detailed description concerning any work to be done and materials to be furnished, shall be
regarded as meaning that only the best general practice is to prevail and that only material and
workmanship of the best quality is to be used, the interpretation of these Specifications shall be
made upon that basis.
1.03 MATERIALS AND EQUIPMENT
A. Manufacturer:
1. All transactions with the manufacturers or subcontractors shall be through the Contractor,
unless the Contractor shall request and at the Engineer's option, that the manufacturer or
subcontractor deal directly with the Engineer. Any such transactions shall not in any way
release the Contractor from his full responsibility under this Contract.
2. Any two (2) or more pieces of material or equipment of the same kind, type, or classification,
and being used for identical types of service, shall be made by the same manufacturer.
B. Delivery:
1. The Contractor shall deliver materials in ample quantities to ensure the most speedy and
uninterrupted progress of the Work so as to complete the Work within the allotted time.
2. The Contractor shall also coordinate deliveries in order to avoid delay in, or impediment of, the
progress of the work of any related Contractor.
C. Tools and Accessories:
1. The Contractor shall, unless otherwise stated in the Contract Documents, furnish with each type,
kind, or size of equipment, one (1) complete set of suitably marked high grade special tools and
appliances which may be needed to adjust, operate, maintain, or repair the equipment. Such
tools and appliances shall be furnished in approved painted steel cases, properly labeled and
equipped with good grade cylinder locks and duplicate keys.
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-3 5/8/2026
2. Spare parts shall be furnished as specified herein and as recommended by the manufacturer
necessary for the operation of the equipment, not including materials required for routine
maintenance.
3. Each piece of equipment shall be provided with a substantial nameplate, securely fastened in
place and clearly inscribed with the manufacturer's name, year of manufacture, serial number,
weight, and principal rate data.
D. Service of Manufacturer's Engineer:
1. The Contract Prices for equipment shall include the cost of furnishing a competent and
experienced engineer or superintendent who shall represent the manufacturer and shall assist the
Contractor, when required, to install, adjust, test, and place in operation, the equipment in
conformity with the Contract Documents.
2. After the equipment is placed in permanent operation by the Owner, such engineer or
superintendent shall make all adjustments and tests required by the Engineer to prove that such
equipment is in proper and satisfactory operating condition, and shall instruct such personnel as
may be designated by the Owner in the proper operation and maintenance of such equipment.
1.04 INSPECTION AND TESTING
A. General:
1. For tests specified to be made by the Contractor, the testing personnel shall make the necessary
inspections and tests, and the reports thereof shall be in such form as will facilitate checking to
determine compliance with the Contract Documents. Five (5) copies of the reports shall be
submitted, and authoritative certification thereof must be furnished to the Engineer as a
prerequisite for the acceptance of any material or equipment.
2. If, in the making of any test of any material or equipment, it is ascertained by the Engineer that
the material or equipment does not comply with the Contract Documents, the Contractor will be
notified thereof, and he will be directed to refrain from delivering said material or equipment, or
to remove it promptly from the site or from the Work and replace it with acceptable material,
without cost to the Owner.
3. Tests of electrical and mechanical equipment and appliances shall be conducted in accordance
with the recognized test codes of the ANSI, ASME, or the IEEE, except as may otherwise be
stated herein.
4. The Contractor shall be fully responsible for the proper operation of equipment during testing
and instruction periods and shall neither have nor make any claim for damage which may occur
to equipment prior to the time when the Owner formally takes over the operation thereof.
B. Costs:
1. All costs for inspections required under the Building Permit shall be provided by the Contractor,
unless otherwise expressly specified.
2. The cost of shop and field tests of equipment and of certain other tests specifically called for in
the Contract Documents shall be borne by the Contractor, and such costs shall be deemed to be
included in the Contract Price.
3. Materials and equipment submitted by the Contractor as the equivalent to those specifically
named in the Contract may be tested by the Owner for compliance. The Contractor shall
reimburse the Owner for the expenditures incurred in making such tests of materials and
equipment which are rejected for non-compliance.
C. Certificate of Manufacture:
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-4 5/8/2026
1. Contractor shall furnish to Engineer authoritative evidence in the form of a certificate of
manufacture that the materials to be used in the Work have been manufactured and tested in
conformity with the Contract Documents.
2. These certificates shall be notarized and shall include copies of the results of physical tests and
chemical analyses, where necessary, that have been made directly on the product or on similar
products of the manufacturer.
3. All materials shall be in compliance with "build America buy America" requirements.
Certifications shall be provided for all materials.
D. Shop Tests:
1. Each piece of equipment for which pressure, duty, capacity, rating, efficiency, performance,
function, or special requirements are specified shall be tested in the shop of the maker in a
manner which shall conclusively prove that its characteristics comply fully with the
requirements of the Contract Documents. Shop tests where specified shall be witnessed by the
Engineer.
2. Five (5) copies of the manufacturer's actual test data and interpreted results thereof,
accompanied by a certificate of authenticity sworn to by a responsible official of the
manufacturing company and/or independent laboratory, shall be submitted to the Engineer for
approval.
3. The cost of shop tests, travel expenses of the Engineer, and of furnishing manufacturer's
preliminary and shop test data of operating equipment shall be borne by the Contractor.
E. Start-up Tests:
1. As soon as conditions permit, the Contractor shall furnish all labor, materials, and instruments
and shall make start-up tests of equipment.
2. If the start-up tests disclose any equipment furnished under this Contract which does not comply
with the requirements of the Contract Documents, the Contractor shall, prior to demonstration
tests, make all changes, adjustments, and replacements required. The furnishing Contractor
shall assist in the start-up tests as applicable.
F. Demonstration Tests:
1. Prior to Contractor's request for a Substantial Completion inspection, all equipment and piping
installed under this Contract shall be subjected to demonstration tests as specified or required to
prove compliance with the Contract Documents.
2. The Contractor shall furnish labor, fuel, energy, water, and all other materials, equipment, and
instruments necessary for all demonstration tests, at no additional cost to the Owner. Contractor
shall assist in the demonstration tests as applicable.
1.05 LINES AND GRADES
A. Grade:
1. All work under this Contract shall be constructed in accordance with the lines and grades shown
on the Drawings, or as given by the Engineer. The full responsibility for keeping alignment and
grade shall rest upon the Contractor.
2. The Engineer will establish benchmarks and baseline controlling points. Reference marks for
lines and grades as the Work progresses will be located by the Contractor to cause as little
inconvenience to the prosecution of the Work as possible. The Contractor shall so place
excavation and other materials as to cause no inconvenience in the use of the reference marks
provided. He shall remove any obstructions placed by him contrary to this provision.
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-5 5/8/2026
B. Surveys:
1. The Contractor shall furnish and maintain, at his own expense, stakes and other such materials.
2. The Contractor shall check such reference marks by such means as he may deem necessary and,
before using them, shall call the Engineer's attention to any inaccuracies.
3. The Contractor shall, at his own expense, establish all working or construction lines and grades
as required from the reference marks set by the Engineer, and shall be solely responsible for the
accuracy thereof. He shall, however, be subject to the check and review by the Engineer.
C. Safeguarding Marks:
1. The Contractor shall safeguard all points, stakes, grade marks, monuments, and bench marks
made or established on the Work, bear the cost of re-establishing them if disturbed, and bear the
entire expense of rectifying work improperly installed due to not maintaining or protecting or to
removing without authorization such established points, stakes, and marks.
2. The Contractor shall safeguard all existing and known property corners, monuments, and marks
adjacent to but not related to the Work and shall bear the cost of re-establishing them if
disturbed or destroyed.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
City of Kalamazoo
Phase 1: Central Pump Stations 1 Filter Media
Replacement (As Needed) and Misc.
Filter Improvements
Tetra Tech Project No. 200-19743-24010 01005-6 5/8/2026
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Project ID: Title: Bloomfield Park Toddler Playground Addenda: 0 Release Date: 7/23/2026 Due
City of Jackson
Bid Due: 8/12/2026
Description: Cheboygan Area High School Security Door Project Department: Wayne RESA Buyer: Stacey
State of Michigan
Bid Due: 8/21/2026
Due Date: 08/06/2026 Pre-Bid Conference: N/A ADVERTISEMENT FOR TOWNSHIP HALL ROOFING REPLACEMENT FOR
Flushing charter township
Bid Due: 8/06/2026
Follow Coast Guard Air Station Detroit Roof Repairs Active Contract Opportunity Notice ID
HOMELAND SECURITY, DEPARTMENT OF
Bid Due: 8/12/2026