Paving, Leveling and Patching North St. and Paul Croft Way (Short St.) and Sidewalk Installation
| Agency: | State Government of Georgia |
|---|---|
| State: | Georgia |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Jul 2, 2025 |
| Due Date: | Aug 5, 2025 |
| Solicitation No: | PE-62351-NONST-2025-000000020 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
| Event ID | Event Title | Government Entity | Start Date (ET) | End Date (ET) |
| PE-62351-NONST-2025-000000020 | Paving, Leveling and Patching North St. and Paul Croft Way (Short St.) and Sidewalk Installation | Ringgold, City Of |
Jul 02, 2025 @ 12:38 PM
|
Aug 05, 2025 @ 02:00 PM
|
Start Date: Jul 02, 2025 @ 12:38 PM ET
End Date:
Aug 05, 2025 @ 02:00 PM ET
Description
North Street
¿ Paving is to start at Cleveland and end at High Street.
¿ North Street is .28 LM and 18 feet wide.
¿ Traffic control will be needed.
*Spot Leveling
*Recycled Asphalt Conc. Leveling include
Bitum Matl and H Lime 1 inch thick---- 96Tons
*Recycled Asphalt Conc. 9.5MM
Superwave, type 1 Blend include
Bitum and H Lime 1 inch thick----------------------------------- 96Tons
*Bitum tack coat---- 201 Gallons
*Milling required at all intersection transitions
*No Striping
Paul Croft Way (Short Street)
¿ Paving is to start at Sparks Street and end at Guyler Street.
¿ Paul Croft Way is .30 LM and 28 feet wide.
¿ Traffic control will be needed.
*Spot Leveling
*Recycled Asphalt Conc. Leveling include
Bitum Matl and H Lime 1 inch thick---- 24 Tons
*Recycled Asphalt Conc. 9.5MM
Superwave, type 1 Blend include
Bitum and H Lime 1 inch thick----24 Tons
*Bitum tack coat---- 40 Gallons
¿ Milling required at intersection transitions
*No Striping
Sparks Street Sidewalk
¿ Sidewalk is to start at Whitten Street and continue to Cleveland Street at Lafayette Street.
¿ Sidewalk to be 5 feet wide and 4 inch in depth
¿ Radius form is required at each intersection and connection to existing sidewalk
¿ Sidewalk is to be flush with existing ground
¿ 4 inches of #89 base stone is required
¿ Broom finish is required
¿ Backfill and in finish seeding is required
¿ Traffic control will be needed.
*Estimated concrete required (580 linear feet) --- 38 cu yd
*No crosswalk Striping
Boynton Drive Sidewalk
¿ Sidewalk is to start at existing termination of sidewalk and continue to Hummingbird Lane.
¿ Sidewalk to be 5 feet wide and 4 inch in depth
¿ Radius form is required at each intersection
¿ Sidewalk is to be flush with existing ground
¿ 4 inches of #89 base stone is required
¿ Broom finish is required
¿ Backfill and in finish seeding is required
*Estimated concrete required (190 linear feet) ----- 14 cu yd
*No crosswalk Striping
See complete ITB at www.cityof ringgoldga.gov
| Code | Description |
| 91395 | Paving and Resurfacing, Highway and Road |
| 91396 | Paving and Resurfacing, Streets, Major and Residential |
Nicki Lundeen
nickilundeen@cityofringgoldga.gov
706-935-3061
See Also
RFQ for MLK Blvd-Altama Ave Bicycle and Pedestrian Trail Project Bid/RFP Status Open
City of Brunswick
Due by 9/18/2026
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-66033-NONST-2027-000000008
State Government of Georgia
Due by 10/06/2026
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-55463-NONST-2027-000000027
State Government of Georgia
Due by 10/01/2026
RFP2027-02 Lewis Frasier Middle School Boiler Replacement Title: RFP2027-02 Lewis Frasier Middle School
Liberty County School System
Due by 10/09/2026