56--NV-STILLWATER NWRC-HUNTER RD GRAVEL PROJ
| Agency: | INTERIOR, DEPARTMENT OF THE |
|---|---|
| State: | Federal |
| Type of Government: | Federal |
| FSC Category: |
|
| NAICS Category: |
|
| Set Aside: | Total Small Business Set-Aside (FAR 19.5) |
| Posted Date: | Feb 17, 2026 |
| Due Date: | Feb 19, 2026 |
| Solicitation No: | 140F0S26Q0004 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
- Contract Opportunity Type: Solicitation (Updated)
- Updated Published Date: Feb 17, 2026 01:18 pm EST
- Original Published Date: Feb 13, 2026 02:59 pm EST
- Updated Date Offers Due: Feb 19, 2026 01:00 pm EST
- Original Date Offers Due: Feb 19, 2026 01:00 pm EST
- Inactive Policy: 15 days after date offers due
- Updated Inactive Date: Mar 06, 2026
- Original Inactive Date: Mar 06, 2026
-
Initiative:
- None
- Original Set Aside: Total Small Business Set-Aside (FAR 19.5)
- Product Service Code: 5610 - MINERAL CONSTRUCTION MATERIALS, BULK
-
NAICS Code:
- 212319 - Other Crushed and Broken Stone Mining and Quarrying
-
Place of Performance:
Type 2 Class B base course with Tailgate spread for Fallon NV. See SOW in solicitation packet for specifications.
Provide a statement that you understand the standard for Type 2 Class B base course as defined in the SOW and include your CAGE code in your submission.
Email Robert_Sung@fws.gov for questions and your quotes. RFI Q&A response
Q1: After reviewing this requirement with our subcontractor, we received the following clarification from them:
"If the trucks ran consecutively, they could all dump in sequence, allowing the refuge staff time to work the material before the trucks returned for their second and third trips. The total daily tonnage can be adjusted to suit your needs by increasing or decreasing the number of trucks. We anticipate approximately 800-1,000 tons per shift. The material would be delivered using belly dump trains, leaving a window for the refuge staff to spread.
We would revise the proposal to include minimum truck spacing. However, doing so would limit roughly half the trucks to only two loads per day, increasing the cost per ton. Based on this scenario and eight trucks per day, spacing would be approximately 15-30 minutes between loads, followed by about 1.25 hours of downtime between the last truck in the first rotation and the first truck returning for the second rotation. This would result in approximately 800 tons per shift."
Based on this, strict adherence to the minimum 15-minute spacing requirement would materially affect operational efficiency and increase the cost per ton.
We would respectfully like to inquire whether there is any flexibility in the delivery spacing requirement. Specifically:
A. Would consecutive dumping be acceptable if coordinated safely and efficiently with the grading contractor?
B. Is the 15-minute minimum interval mandatory throughout the entire shift, or could it be adjusted during certain delivery windows?
C. Would alternative staging or sequencing methods be considered, provided safety and site control are maintained?
A1: The refuge does have some flexibility on the spacing of the trucks and could be coordinated at that time with the project coordinator. During the work day - we will have a refuge staff member who is stationed to take the tickets from drivers and direct them when it is safe to unload. However, we have completed similar projects at least three times in the past 5 years with various contractors. A 15-minute interval between trucks was generally what they averaged between trucks just based on how long it took the for each load to be filled between the first and the next truck at the gravel pit. Across the projects, delivery has averaged between 800-1k tons per day.
For the specific questions:
A. Yes, consecutive dumping can be coordinated with the refuge staff who will be completing the gravel grading.
B. The 15 minute interval would not be mandatory and could vary throughout the shift, but would need to be coordinated with staff on site.
C. Alternative staging or sequencing methods could be considered, provided safety and site control are maintained. The contractor would be responsible for coordinating with the project manager on site and ultimately would be responsible for ensuring the gravel is delivered to its final location on the delivery route.
- FWS, Over SAT G/S 5275 Leesburg Pike
- Falls Church , VA 22041
- USA
- Sung, Robert
- robert_sung@fws.gov
- Phone Number 5038722825
- Feb 17, 2026 01:18 pm ESTSolicitation (Updated)
- Feb 13, 2026 02:59 pm EST Solicitation (Original)
- Jan 14, 2026 11:55 pm EST Sources Sought (Original)
Related Document
| Dec 16, 2025 | [Sources Sought (Original)] 56--Sources Sought, Gravel, Fallon NV |
| Feb 13, 2026 | [Solicitation (Original)] NV-STILLWATER NWRC-HUNTER RD GRAVEL PROJ |
| Feb 23, 2026 | [Solicitation (Updated)] 56--NV-STILLWATER NWRC-HUNTER RD GRAVEL PROJ |
| Mar 3, 2026 | [Award Notice (Original)] 56--NV-STILLWATER NWRC-HUNTER RD GRAVEL PROJ |
See Also
Follow 56--PRE-BLEND & SACK DRY MIX (GUNITE) - Colorado River Active Contract Opportunity
INTERIOR, DEPARTMENT OF THE
Due by 9/22/2026
Follow 56--TAPE,NUCLEAR ET GR Active Contract Opportunity Notice ID N0010426QEF31 Related Notice Department/Ind.
DEPT OF DEFENSE
Due by 9/28/2026
Follow 56--LAG SEAL Active Contract Opportunity Notice ID N0010426QEE99 Related Notice Department/Ind. Agency
DEPT OF DEFENSE
Due by 10/05/2026
Follow Cobblestone Curbing and Molded Plastic Lumber Supply, Buffumville Lake, Charlton, MA Active
DEPT OF DEFENSE