MIlan Manor Dr. Landslip Repair - Milan Village
| Agency: | Huron County Engineer |
|---|---|
| State: | Ohio |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Apr 30, 2026 |
| Due Date: | May 14, 2026 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
| Project Title | Bid Date | Completion Date | Engineer Estimate | Legal Advertisement | Plan Holders List | Questions and Answers | Addendum | Bid Tabulation |
| MIlan Manor Dr. Landslip Repair - Milan Village | May 14, 2026 | Oct 09, 2026 |
Attachment Preview
| CATEGORY | COST (Dollars) |
|---|---|
| Roadway | $ 27,610 |
| Erosion Control | $ 10,600 |
| Pavement | $ 33,290 |
| Traffic Control | $ 100 |
| Retaining Wall | $ 1 83,770 |
| Incidentals | $ 40,000 |
| SUBTOTAL - BASE BID CONSTRUCTION COSTS (2026) | $ 295,370 |
| Construction Contingency (10%) | $ 29,537 |
| TOTAL - BASE BID CONSTRUCTION COSTS (2026) | $ 324,907 |
| Alternate 1 | $ 4,840 |
| SUBTOTAL - ALTERNATE 1 CONSTRUCTION COSTS (2026) | $ 4,840 |
| Construction Contingency (10%) | $ 484 |
| TOTAL - ALTERNATE 1 CONSTRUCTION COSTS (2026) | $ 5,324 |
| GRAND TOTAL - CONSTRUCTION COSTS (2026) | $ 330,231 |
ADR & ASSOCIATES, LTD. 04/15/2026
Village of Milan
MILAN MANOR DRIVE LANDSLIP REPAIR PROJECT
ENGINEER'S ESTIMATE OF PROBABLE CONSTRUCTION COSTS
PROJECT DESCRIPTION: Stabilizeembankment along Milan Manor Drive using Geopier SRT Plate Pile system. Restore
roadway structure, curb, drainage, and surface pavement while maintaining traffic during construction.
CATEGORY COST (Dollars)
Roadway $ 27,610
Erosion Control $ 10,600
Pavement $ 33,290
Traffic Control $ 100
Retaining Wall $ 1 83,770
Incidentals $ 40,000
SUBTOTAL - BASE BID CONSTRUCTION COSTS (2026) $ 295,370
Construction Contingency (10%) $ 29,537
TOTAL - BASE BID CONSTRUCTION COSTS (2026) $ 324,907
Alternate 1 $ 4,840
SUBTOTAL - ALTERNATE 1 CONSTRUCTION COSTS (2026) $ 4,840
Construction Contingency (10%) $ 484
TOTAL - ALTERNATE 1 CONSTRUCTION COSTS (2026) $ 5,324
GRAND TOTAL - CONSTRUCTION COSTS (2026) $ 330,231
Prepared by ADR & Associates, Ltd. Prices are based on available historical data and supplier orcontractor estimates.
Prices are subject to change due to market conditions.
April 16, 2026
1 of 2 Village of Milan
| ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | COST |
|---|---|---|---|---|---|
| ROADWAY | |||||
| 201 | CLEARING AND GRUBBING | LS | 1 | $ 10,000.00 | $ 10,000.00 |
| 202 | PAVEMENT REMOVED | SY | 212 | $ 25.00 | $ 5,300.00 |
| 202 | CONCRETE BARRIER REMOVED | FT | 109 | $ 15.00 | $ 1,640.00 |
| 203 | EXCAVATION | CY | 41 | $ 30.00 | $ 1,230.00 |
| 203 | EMBANKMENT | CY | 245 | $ 25.00 | $ 6,130.00 |
| 204 | PROOF ROLLING | HOUR | 1 | $ 300.00 | $ 300.00 |
| 204 | EXCAVATION OF SUBGRADE | CY | 13 | $ 45.00 | $ 590.00 |
| 204 | GRANULAR MATERIAL, TYPE B | CY | 13 | $ 80.00 | $ 1,040.00 |
| 204 | GEOTEXTILE FABRIC | SY | 25 | $ 5 .00 | $ 130.00 |
| 204 | SUBGRADE COMPACTION | SY | 249 | $ 5 .00 | $ 1,250.00 |
| ROADWAY TOTAL | $ 27,610.00 | ||||
| EROSION CONTROL | |||||
| 659 | TOPSOIL | CY | 67 | $ 40.00 | $ 2,680.00 |
| 659 | SEEDING AND MULCHING | SY | 603 | $ 8 .00 | $ 4,820.00 |
| 659 | REPAIR SEEDING AND MULCHING | SY | 30 | $ 10.00 | $ 300.00 |
| 659 | COMMERCIAL FERTILIZER | TON | 0.08 | $ 1,200.00 | $ 100.00 |
| 659 | LIME | ACRE | 0.12 | $ 800.00 | $ 100.00 |
| 659 | WATER | MGAL | 2 | $ 50.00 | $ 100.00 |
| 832 | EROSION CONTROL, AS PER PLAN | EACH | 2500 | $ 1 .00 | $ 2,500.00 |
| EROSION CONTROL TOTAL | $ 10,600.00 | ||||
| PAVEMENT | |||||
| 252 | FULL DEPTH PAVEMENT SAWING | FT | 228 | $ 20.00 | $ 4,560.00 |
| 301 | ASPHALT CONCRETE BASE, PG64-22, (449) | CY | 34 | $ 200.00 | $ 6,800.00 |
| 304 | AGGREGATE BASE | CY | 34 | $ 100.00 | $ 3,400.00 |
| 407 | TACK COAT | GAL | 30 | $ 8 .00 | $ 240.00 |
| 441 | ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG64-22 | CY | 8 | $ 300.00 | $ 2,400.00 |
| 441 | ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (449) | CY | 10 | $ 250.00 | $ 2,500.00 |
| 605 | 6" BASE PIPE UNDERDRAINS | FT | 206 | $ 15.00 | $ 3,090.00 |
| 609 | COMBINATION CURB AND GUTTER, TYPE 2 | FT | 206 | $ 50.00 | $ 10,300.00 |
| PAVEMENT TOTAL | $ 33,290.00 | ||||
| TRAFFIC CONTROL | |||||
| 614 | WORK ZONE STOP LINE, CLASS 1, 642 PAINT | FT | 20 | $ 5 .00 | $ 100.00 |
| TRAFFIC CONTROL TOTAL | $ 100.00 | ||||
| RETAINING WALL | |||||
| 507 | STEEL PILES, MISC.: GEOPIER SRT, FURNISHED | FT | 2,812 | $ 44.00 | $ 123,730.00 |
| 507 | STEEL PILES, MISC.: GEOPIER SRT, DRIVEN | FT | 3,002 | $ 20.00 | $ 60,040.00 |
| RETAINING WALL TOTAL | $ 183,770.00 | ||||
| INCIDENTALS | |||||
| 103 | PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYMENT BOND | LS | 1 | $ 5,000.00 | $ 5,000.00 |
| 614 | MAINTAINING TRAFFIC | LS | 1 | $ 20,000.00 | $ 20,000.00 |
| 623 | CONSTRUCTION LAYOUT STAKES AND SURVEYING | LS | 1 | $ 5,000.00 | $ 5,000.00 |
| 624 | MOBILIZATION | LS | 1 | $ 10,000.00 | $ 10,000.00 |
| INCIDENTALS TOTAL | $ 40,000.00 |
| ALTERNATE 1 | |||||
|---|---|---|---|---|---|
| 254 | PAVEMENT PLANING, ASPHALT CONCRETE | SY | 271 | $ 5 .00 | $ 1,360.00 |
| 407 | TACK COAT | GAL | 23 | $ 8 .00 | $ 180.00 |
| 441 | ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG64-22 | CY | 11 | $ 300.00 | $ 3,300.00 |
| ALTERNATE 1 TOTAL | $ 4,840.00 |
ADR & ASSOCIATES, LTD. 04/15/2026
Village of Milan
MILAN MANOR DRIVE LANDSLIP REPAIR PROJECT
ENGINEER'S ESTIMATE OF PROBABLE CONSTRUCTION COSTS
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE COST
ROADWAY
201 CLEARING AND GRUBBING LS 1 $ 10,000.00 $ 10,000.00
202 PAVEMENT REMOVED SY 212 $ 25.00 $ 5,300.00
202 CONCRETE BARRIER REMOVED FT 109 $ 15.00 $ 1,640.00
203 EXCAVATION CY 41 $ 30.00 $ 1,230.00
203 EMBANKMENT CY 245 $ 25.00 $ 6,130.00
204 PROOF ROLLING HOUR 1 $ 300.00 $ 300.00
204 EXCAVATION OF SUBGRADE CY 13 $ 45.00 $ 590.00
204 GRANULAR MATERIAL, TYPE B CY 13 $ 80.00 $ 1,040.00
204 GEOTEXTILE FABRIC SY 25 $ 5 .00 $ 130.00
204 SUBGRADE COMPACTION SY 249 $ 5 .00 $ 1,250.00
ROADWAY TOTAL $ 27,610.00
EROSION CONTROL
659 TOPSOIL CY 67 $ 40.00 $ 2,680.00
659 SEEDING AND MULCHING SY 603 $ 8 .00 $ 4,820.00
659 REPAIR SEEDING AND MULCHING SY 30 $ 10.00 $ 300.00
659 COMMERCIAL FERTILIZER TON 0.08 $ 1,200.00 $ 100.00
659 LIME ACRE 0.12 $ 800.00 $ 100.00
659 WATER MGAL 2 $ 50.00 $ 100.00
832 EROSION CONTROL, AS PER PLAN EACH 2500 $ 1 .00 $ 2,500.00
EROSION CONTROL TOTAL $ 10,600.00
PAVEMENT
252 FULL DEPTH PAVEMENT SAWING FT 228 $ 20.00 $ 4,560.00
301 ASPHALT CONCRETE BASE, PG64-22, (449) CY 34 $ 200.00 $ 6,800.00
304 AGGREGATE BASE CY 34 $ 100.00 $ 3,400.00
407 TACK COAT GAL 30 $ 8 .00 $ 240.00
441 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG64-22 CY 8 $ 300.00 $ 2,400.00
441 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (449) CY 10 $ 250.00 $ 2,500.00
605 6" BASE PIPE UNDERDRAINS FT 206 $ 15.00 $ 3,090.00
609 COMBINATION CURB AND GUTTER, TYPE 2 FT 206 $ 50.00 $ 10,300.00
PAVEMENT TOTAL $ 33,290.00
TRAFFIC CONTROL
614 WORK ZONE STOP LINE, CLASS 1, 642 PAINT FT 20 $ 5 .00 $ 100.00
TRAFFIC CONTROL TOTAL $ 100.00
RETAINING WALL
507 STEEL PILES, MISC.: GEOPIER SRT, FURNISHED FT 2,812 $ 44.00 $ 123,730.00
507 STEEL PILES, MISC.: GEOPIER SRT, DRIVEN FT 3,002 $ 20.00 $ 60,040.00
RETAINING WALL TOTAL $ 183,770.00
INCIDENTALS
103 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYMENT BOND LS 1 $ 5,000.00 $ 5,000.00
614 MAINTAINING TRAFFIC LS 1 $ 20,000.00 $ 20,000.00
623 CONSTRUCTION LAYOUT STAKES AND SURVEYING LS 1 $ 5,000.00 $ 5,000.00
624 MOBILIZATION LS 1 $ 10,000.00 $ 10,000.00
INCIDENTALS TOTAL $ 40,000.00
ALTERNATE 1
254 PAVEMENT PLANING, ASPHALT CONCRETE SY 271 $ 5 .00 $ 1,360.00
407 TACK COAT GAL 23 $ 8 .00 $ 180.00
441 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG64-22 CY 11 $ 300.00 $ 3,300.00
ALTERNATE 1 TOTAL $ 4,840.00
2 of 2 Village of Milan
See Also
Description Opening Date/Time Closing Date/Time Request for Proposals 2026 Shoreline Park Concession September
City of Sanduskey
Due by 10/01/2026