Description


Project ID:

Title: MGT1 Water Mist Fire Protection system replacement

Addenda: 0

Release Date: 6/25/2026

Due Date: 7/24/2026

Follow
MGT1 Water Mist Fire Protection system replacement
Request For Proposal
LE - Production - MPP
Project ID: 2026-RFP-067
Release Date: Thursday, June 25, 2026
· Due Date: Friday, July 24, 2026 4:00pm
Posted Thursday, June 25, 2026 4:00pm
All dates & times in Eastern Time
Draft Response Events RSVP No Bid28 days, 18 hours, 31 minutes


Post Information

Posted At:Thu, Jun 25, 2026 4:00 PM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

Lakeland Electric intends to replace the existing MGT1 fire suppression system with a self-contained high-pressure water mist fire protection system. The system shall not use electric motor-driven pumps. System operation shall be by stored-pressure nitrogen/water cylinders and electrically supervised solenoid-operated valves.

Actual work completed that would make MGT1 unavailable from 9/13 to 9/19 if possible. We have a planned outage for MGT1 during that period.

Pricing Proposal Line Items (BE SURE TO SUBMIT ATTACHMENT L.)



Background

Lakeland Electric’s existing MGT1 fire suppression system has reached the end of its reliable service life and requires replacement. The current system contains obsolete components, aging piping, outdated detection and releasing equipment, and legacy hardware that presents increasing maintenance and reliability concerns. Existing fire alarm/releasing control equipment is obsolete and replacement parts are becoming increasingly difficult to obtain.

Lakeland Electric previously evaluated replacement of the system with a new CO₂ suppression system. After further review, the decision was made to pursue a self-contained high-pressure water mist system due to the reduced personnel hazards associated with water mist systems, improved maintainability, reduced recharge complexity, and operational flexibility for a power generation environment.

The project includes replacement of the existing piping, nozzles, temperature detection devices, pull stations, audible/visual notification devices, releasing control panel, and associated suppression hardware. The proposed system shall utilize stored-pressure nitrogen/water cylinders with electrically supervised solenoid-operated valves and shall not utilize electric motor-driven pumps.

Due to the outdoor and industrial environment associated with the MGT1 installation, vendors shall also provide a complete freeze protection solution for all system components exposed to low ambient temperatures. Freeze protection methods may include conditioned enclosures, heat trace systems, cabinet heaters, insulation, or other engineered solutions proposed by the contractor.

The intent of this project is to improve fire protection system reliability, maintainability, personnel safety, code compliance, and long-term supportability while minimizing operational impacts to plant personnel and generating equipment.



Timeline

RFP release:
June 25, 2026
Pre-Proposal Meeting (Non-Mandatory):
July 9, 2026, 10:00am
McIntosh Power Plant 3400 E Lake Parker Drive, Lakeland, FL, 33805. Entry is through gate 8. Meeting will be held on the 3rd floor of the white control room building (Unit 5 Conference room) on the right after entry through gate 8.
RFP questions deadline:
July 16, 2026, 5:00pm
RFP proposal due date:
July 24, 2026, 4:00pm
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Description: CABLING SYSTEMS, INSTALLATION AND REPAIR OF Department: Purchasing Buyer: Bobby Brooks Solicitation

Palm Beach County

Due by 7/18/2029

Description: Prequalification - Annual Contract Electrical Services Department: Purchasing Buyer: Jeromy Calderon Solicitation

Palm Beach County

Due by 8/14/2030

Description: Prequalification - Annual Contract Electrical Services Department: Facilities Dev & Ops Buyer:

Palm Beach County

Due by 3/13/2028

Description: Prequalification - Annual Contract Electrical Services Department: Facilities Dev & Ops Buyer:

Palm Beach County

Due by 3/13/2028

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.