The Ohio Department of Natural Resources is requesting bids for: Division of Parks & Watercraft Maumee Bay State
Park Campground Resurfacing of Four Restroom Floors, Base and Divider Walls.
Name or Title of the Service: Resurface of Campground floors project that will completely resurface the floors, base, and
divider walls located in four campground bathrooms.
Location: Maumee Bay State Park 1400 State Park Rd Oregon, Ohio 43616
Specifications:
NW, SW and SE Men’s and Women’s Bathrooms:
• Resurface three campground bathrooms (NW, SW, SE), each with a men’s and women’s side, with Sherwin
Williams Resuflor Deco Flake BC Flooring System
• Contractor must use the Manufacturer's Application Instructions
• Total of approximately 1800 sq ft of concrete flooring, 1200 sq ft of block shower walls, and 700 linear ft of 8”
base trim on block walls between all three bathrooms total.
• All heat containment structures, commercial heating units, and water needed for cleanup are the responsibility
of the contractor for the three winterized bathrooms with no heat or running water.
• Remove existing flake and coating on flooring, walls, and base down to bare concrete and block
• Repair any cracks or imperfections in surface
• Mechanically prepare surface for base coat
• Apply primer coat
• Apply base coat and flake to floors, shower walls, and 8” base trim
• Scrap and sweep after cured
• Apply UVE Topcoat to surface
Northeast Family Bathroom:
• In the fourth bathroom (NE), work will be done in the two Family rooms of NE camp bathroom. This will remove
existing Quartz flooring, trowel level the slope to properly drain to two floor drains (current drainage is poor),
and then apply Sherwin Williams Resuflor Deco Quartz DB23 Flooring System.
• Contractor must use the Manufacturer's Application Instructions
• Total of approximately 300 sq ft of concrete floor and 100 linear ft of 4” base trim on block walls between both
family restrooms total
• All heat containment structures and commercial heating units are the responsibility of the contractor for family
bathrooms.
• Only one family bathroom can be done at a time, as the two family rooms are the only restrooms open to
campers or walkers in the campground for the off-season.
• Remove existing quartz flooring and base down to bare concrete and block.
• Trowel level the slope of floor to properly drain to the two floor drains (one in shower area, one in center of
remaining floor area). Build floor using trowel to let water flow to drains. Install trowel over entire floor surface
for proper drainage.
• Approximately 3/4" of trowel over entire surface.
Completion Date: April 10, 2026.
Site Visit & Point of Contact: Prior to submitting a bid response, offerors are encouraged to do a site visit.
Site visits available by appointment only. To schedule an appointment, contact: Eric Schabel, Mobile: (419)279-4580 or
Eric.Schabel@dnr.ohio.gov.
Once a contract is awarded, failure of the bidder to have requested a site visit to become familiar with the facility and
requirements of the bid will be insufficient reason to support any request to be released from the contract.
This project is federally assisted. Contracts to be awarded under this invitation for bids will be subject to
federal laws and related acts that are referenced in this bid package.
Prevailing Wage.
All current wage rates apply for Lucas County, Ohio.
https://wagehour.com.ohio.gov/w3/webwh.nsf/wrlogin/?openform
The Ohio Department of Commerce, Division of Labor and Worker Safety, Wage and Hour Bureau has identified that work
in this solicitation and to be performed under contract may be subject to the requirements of Ohio Revised Code Sections
4115.03 to 4115.16, Prevailing Wage. Upon award of a Contract, the successful Contractor, and all of the sub-contractors,
guarantees that the prevailing wage for the area, to include any adjustments thereto, as published by the Ohio
Department of Commerce, Division of Labor and Worker Safety, Wage and Hour Bureau will apply to any workman
assigned by the Contractor or all of the sub-contractors to this project. The DNR representative will serve
as prevailing wage coordinator and will be responsible for proper application of labor rates as required by the Ohio
Department of Commerce. Responsibilities of the Prevailing Wage Coordinator include but are not limited to; setting up
and maintaining payroll reports, monitoring when payments of wages are made, receiving the Contractor’s complete
payroll records of each employee, establish procedures to monitor compliance, notify Contractor of any adjustment to
the prevailing wage scales and report delinquencies on the part of the Contractor. The successful supplier and all of the
sub-contractors shall strictly comply with the wage provisions of the contract.
All equipment used on-site shall be free of sediment and debris from off-site to minimize the introduction of invasive
species. Any timber matting used shall be new. Previously used matting will not be permitted.
Evaluation. The contract will be awarded to the lowest responsive and responsible bidder as determined by the State.
Contract Award. The contract will be awarded to the lowest responsive and responsible bidder by low lot total. Low lot
total will be determined by multiplying the unit cost by the estimated usage listed in the bid and then adding each of the
totals together to arrive at a total for all items. Failure to bid all items may result in the bidder being deemed not responsive
Preferences. The State will apply all preferences pursuant to Ohio Administrative Code 123:5-1-06.
Following the initial evaluation and scoring, all Proposals will be considered for preferences. Preferences will be calculated
at a rate of five percent (5%) for the first preference and two percent (2%) each for the second and third preferences. The
preferences shall be combined and applied as a total percentage of the original Proposal to determine the score for
evaluation purposes.
Preferences will only be applied if there is at least one Offeror that does not qualify for that particular preference. For
purposes of qualifying for a preference, an Offeror failing to complete the certification for each preference will be deemed
as not qualifying for that preference.
(a) For the Buy American preference, if any Offeror offers a product that is not a domestic source end product, the
State will add the applicable percentage of the total available points to the total score of each Offeror offering a
domestic source end product.
(b) For the Buy Ohio preference, if any Offeror is a Buy Ohio Offeror claiming the preference, the State will add the
applicable percentage of the total available points to each Buy Ohio Offeror’s total score.
(c) If claiming the preferences in (a) and (b) based on the product(s) offered, an Offeror is only eligible to receive the
preference if the cost of the product(s) offered exceeds 50% of the total offered cost for products and services. A Buy
Ohio Offeror is also eligible to receive the Buy Ohio preference based on its significant economic presence in Ohio or
a border state.
(d) For the Veteran-Friendly Business preference, the State will add the applicable percentage of the total available points
to any certified veteran-friendly business Offeror’s total score.
Bill to information:
Invoices Origin-DNR-486 Maumee Bay State Park
All invoices must be submitted DIRECTLY to Financial Shared Services (FSS).
There are three options available to submit invoices to FSS:
• EMAIL the invoice to: invoices@ohio.gov
• MAIL the invoice to: Financial Shared Services, PO Box 182880, Columbus, Ohio 43218-2880
In order to process your invoice, please make sure all the required information listed below is on your invoice before submitting it to
FSS or they will be returned for not being a proper invoice.
1. Must include the Purchase Order (PO) number assigned. You may shorten it to the last five digits.
2. Supplier full name as it appears on your PO.
3. The Ship to and/or service facility name and full address
4. Unique invoice number
5. Date of service or date work was completed.
6. Complete itemization of services performed, materials or goods supplied and/or labor furnished.
7. Line charge(s). If parts are included, please break out the line charges with product and charges separately.
8. No State of Ohio sales tax
9. Remit to address must match our records for payment
10. This PO is only valid for the goods and/or services received through June 30, 2025.
11. Any goods/services received after June 30, 2025 will require a new PO.
All fields mentioned above are required to count as a correct invoice; failure to provide this information will result in a returned
invoice and delayed payment.