Main Street Well 3 & Newport Well 3 Improvements Project (2026/2027) - CIP No. 60177

Agency: City of Tustin
State: California
Type of Government: State & Local
NAICS Category:
  • 236220 - Commercial and Institutional Building Construction
  • 237110 - Water and Sewer Line and Related Structures Construction
  • 237310 - Highway, Street, and Bridge Construction
  • 237990 - Other Heavy and Civil Engineering Construction
  • 238910 - Site Preparation Contractors
Posted Date: Sep 14, 2026
Due Date: Sep 18, 2026
Solicitation No: CIP No. 60177
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description


Project ID: CIP No. 60177

Title: Main Street Well 3 & Newport Well 3 Improvements Project (2026/2027) - CIP No. 60177

Addenda: 2

Release Date: 8/7/2026

Due Date: 9/18/2026

Follow
Main Street Well 3 & Newport Well 3 Improvements Project (2026/2027) - CIP No. 60177
Last updated by Addendum #2 on Sep 15, 2026 4:18 AM
Invitation for Bids
Public Works
Project ID: CIP No. 60177
Release Date: Friday, August 7, 2026
· Due Date: Friday, September 18, 2026 2:00pm
Posted Friday, August 7, 2026 4:31pm
All dates & times in Pacific Time - Los Angeles
Draft Response Events RSVP No Bid
Time Remaining: 3 days, 19 hours, 34 minutes


Post Information

Posted At:Fri, Aug 7, 2026 4:31 PM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

NOTICE IS HEREBY GIVEN that the CITY OF TUSTIN, hereinafter referred to as City or AGENCY invites sealed bids for the above stated project and will receive sealed bids for the construction, materials, supplies, equipment and/or services set forth herein, subject to all conditions outlined in the Bid Package.

Scope of Work: The Work encompassed by the Project is more specifically defined in the Contract Documents, but in general consists of, but is not limited to the following Work:

Main Street Well #3:

  • Perform pre-removal testing and document existing pump and motor operating conditions.
  • Remove, transport, inspect, test, and evaluate the existing pump and motor; submit condition-assessment reports.
  • Perform downhole video inspection and submit well-condition assessment report.
  • Convert the existing oil-lubricated lineshaft system to a continuous water-lubricated configuration, where indicated and authorized.
  • Perform brushing, bailing, chemical treatment, dual-swab airlifting, redevelopment, and related well rehabilitation only when authorized by the City based on inspection results.
  • Rehabilitate, rewind, reinstall, or replace the existing pump and/or motor as authorized by the City.
  • Reinstall the approved rehabilitated or replacement pump and motor and provide a complete operational pumping system.
  • Perform startup, performance, vibration, electrical, operational testing, flushing, disinfection, and post-rehabilitation inspection where required.
  • Restore disturbed areas and complete closeout requirements.

Newport Well #3:

  • Perform pre-removal testing and document existing pump and motor operating conditions.
  • Remove, transport, inspect, test, and evaluate the existing pump and motor; submit condition-assessment reports.
  • Perform downhole video inspection and noninvasive electromagnetic casing-thickness/integrity analysis; submit well-condition assessment report.
  • Because Newport Well No. 3 is considered fragile, perform well cleaning, redevelopment, casing repair, or other downhole rehabilitation only when specifically authorized by the City.
  • Rehabilitate, rewind, reinstall, or replace the existing pump and/or motor as authorized by the City.
  • Install new magnetic flow meter and MOV on the waste-discharge piping.
  • Remove and replace the existing magnetic flow meter and MOV on the system-discharge piping.
  • Remove existing electrical equipment as needed and furnish/install new electrical, controls, instrumentation, PLC, and SCADA work where required.
  • Reinstall the approved rehabilitated or replacement pump and motor and provide a complete operational pumping system.
  • Perform startup, performance, vibration, electrical, operational testing, flushing, disinfection, meter/MOV testing, and post-work inspection where required.
  • Restore disturbed areas and complete closeout requirements.


Background

Project Schedule (contract days): 150 Days

Engineer’s Estimate: $ 775,000

Liquidated Damages: $ 1,000 Per Day

Bid Valid (calendar days): 60 Days

Contractor's License(s): Class A



Timeline

Advertisement/Release Project Date:
August 7, 2026
Pre-Bid Meeting (Mandatory):
August 20, 2026, 10:00am
Begin at Main Street Well No. 3 (235 E. Main St., Tustin)
Question Submission Deadline:
August 27, 2026, 5:00pm
Bid Opening:
September 18, 2026, 2:00pm
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Post Date 11/02/2026 Quest Number 10426124 Category Code Commercial Entrances Storefront Steel/Aluminum,Concrete/Formed/Flatwork/Foundation,Construction,Lamp/Lighting Interior/Exterior,Lighting

City of Atascadero

Due by 11/19/2026

Project ID: Title: Katella Ave & State College Blvd Rehabilitation Project Addenda: 1

City of Anaheim

Due by 11/12/2026

Joint Outfall A Unit 3C Trunk Sewer Protection Between Manholes A38 and A39

Los Angeles County Sanitation Districts

Due by 12/01/2026

Project Summary Project ID: TDS0001709 Federal No: HSIPL 5953(759) Project Name: San Gabriel

La County

Due by 11/24/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.