Lake Hartwell WTP Expansion and Ozone Improvements

Agency: Goodwyn Mills Cawood(GMC)
State: Federal
Type of Government: State & Local
NAICS Category:
  • 236220 - Commercial and Institutional Building Construction
  • 237990 - Other Heavy and Civil Engineering Construction
  • 238990 - All Other Specialty Trade Contractors
Posted Date: Apr 20, 2026
Due Date: May 21, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
Lake Hartwell WTP Expansion and Ozone Improvements
Fair Play,
South Carolina
May 21, 2026 10:00 am

Attachment Preview

REQUEST FOR PROPOSALS
FOR CONSTRUCTION MANAGER ATRISK
Lake Hartwell WTP Expansion and Ozone
Improvements
Pioneer Rural Water District (PRWD)
1. INTRODUCTION
Pioneer Rural Water District (PRWD) is seeking Construction Managers to submit proposals
for the opportunity to serve as a Construction Manager AtRisk (CMAR) in the design review,
construction, and commission of the 2.5 MGD plant expansion at Pioneer Rural Water District
Water Treatment Plant (WTP). The objective of this Request for Proposals (RFP) is to provide
additional information to enable Proposers to submit written proposals for the project.
Construction Managers must submit four (5) hard copies of their proposal. Proposals must be
received by PRWD at their administrative offices no later than 10:00 AM on Thursday, May
21st, 2026.
PRWD
Attn: Terry Pruitt, General Manager
5500 W Oak Hwy
Westminster, SC 29693
Proposers are encouraged to contact Amy Hopkins (amy.hopkins@gmcnetwork.com) with the
Owner’s engineer, Goodwyn, Mills and Cawood, Inc. (GMC), in order to attend the mandatory
pre-proposal meeting on Wednesday, April 29th, 2026 @ 2:00 PM at the WTP, which is located
at 1142 Hwy 59 Fair Play, South Carolina 29643 A tour of the plant will be provided at this time.
Additional tours of the project site and additional contact with PRWD are not allowed.
PRWD intends to select the CMAR for the Project based on review and evaluation of the
Proposals and shortlist interviews.
Proposers are encouraged to provide input on the overall project schedule and provide
suggested improvements to reduce the construction schedule. The preliminary procurement
schedule is as follows:
Milestone Activity
RFP Issue
Mandatory Pre-Proposal Meeting
Final Date to Submit Questions
Proposals Due
Proposer Interviews (if desired)
Notice of Award (approximate date)
Date
April 20, 2026
April 29, 2026
May 14, 2026
May 21, 2026
May 28, 2026
June 4, 2026
Page 1 of 15
Proposals will be evaluated to select a CMAR with the requisite experience, qualifications,
and resources to complete the Project successfully within an agreed Guaranteed Maximum
Price (GMP) and construction schedule in accordance with the project requirements as
specified by PRWD.
2. BACKGROUND
The existing PRWD water treatment facilities, which are located in Fair Play, SC, consist of a
reliable 2.5 MGD water treatment facility (originally constructed in the 2019). The 2.5 MGD
capacity serves the water treatment needs of PRWD’s 7,000 customers.
The proposed funding for the project is private funding.
3. PROJECT SCOPE
Due to ongoing taste and odor (T&O) concerns, PRWD is seeking improvements at the Lake
Hartwell Water Treatment plant to address capacity and treatment.
The project will include the following elements:
Addition of one (1) raw water pump
Addition of one (1) finished water pump
Installation of a 5-MGD ozone system
4. DRAFT SUMMARY SCOPE OF SERVICES
A draft summary of Scope of Services is included below. The final Scope of Services will be
negotiated with the selected CMAR. The Proposal shall include any comments or suggested
changes to the draft summary Scope of Services.
a. Pre-Construction Services:
i. Value Engineering services shall include a thorough review of the completed
design drawings and specifications and the identification of any alternative
design components, construction methods, or materials that could reduce the
cost of the project without sacrificing project quality.
ii. GMP Development will, at the latest, commence upon the completion of permit
acquisition and will include the costs developed through an openbook
process including thorough review by GMC. The CMAR may choose to perform
some preliminary aspects of the GMP preparation prior to the acquisition of the
permits; however, formal GMP development will not start until all permits have
been acquired. PRWD requires that for those components of the Project that
the CMAR may want to selfperform, the CMAR will need to submit bill rates,
overhead, markup on subcontractors, profit rates, and other similar financial
Page 2 of 15
information for that scope. The GMP will also include CMAR overhead costs
and margin for all work under the Construction Phase Services Agreement, as
described in the following outline of CMAR Construction Services, as well as any
contingency allowances.
iii. GMP Negotiation, if successful, will result in the execution of an amendment to
the “Agreement between Owner and CMAR.”
b. Construction Phase Services
i. Construction Administration Services represent the management and
administration of the CMAR’s Construction Phase contract obligations
including, but not limited to, the following activities:
1. Provide all requisite bonds and insurance for the construction of the
project;
2. Possess the requisite license and assure that all subcontractors are also
appropriately licensed and bonded for the tasks needed to complete
construction phase of the project;
3. Procure and manage all equipment and construction contractors to
complete the Construction Phase scope of work for the project;
4. Hold monthly progress/construction meetings and submit meeting
minutes for review and approval by PRWD and GMC;
5. Develop and update a construction management plan that includes
Construction Phase quality control procedures, safety programs,
construction document management protocol, etc.;
6. Manage subcontractors (contracts, insurance, and bonds);
7. Prepare payment requests and maintain cash flow projection;
8. Submit and track shop drawings and equipment Operations &
Maintenance (O&M) Manuals;
9. Track Request for Information and/or clarifications (RFIs);
10. Prepare record drawings;
11. Startup and commission facilities with operator training through
completion of acceptance testing;
12. Facilitate project closeout; and
13. Administer warranties through the warranty period.
ii. Site Security will be the responsibility of the CMAR throughout the duration of
the construction phase. The CMAR will need to develop an acceptable security
plan to control access to the construction site during all phases of construction
without interrupting normal daytoday operations of the facility. The CMAR will
be responsible for construction of any alternate entrance locations or
operations of any existing security gates, as well as any repairs required to bring
facilities (i.e., roadways, curb and gutter, landscaping) back to their current
condition.
Page 3 of 15
iii. Project Schedule requirements will include developing a detailed project
construction schedule defining construction activities of each element of the
project and their interrelationships along with milestone dates relative to
project completion and permit requirements using approved scheduling
software. Monthly monitoring, updating, and reporting of the project
schedule will be required to demonstrate an efficient and timely delivery of
the project.
iv. Project Budget Reporting requirements will include the preparation of a project
budget monitoring protocol to provide monthly updates on the status of the
following financial attributes of the project: update cash flow projections for
the Construction Phase including actual construction costs; maintain a
comparative assessment of actual costs relative to the GMP; and provide
documentation of any resultant changes in the projected life cycle costs
resulting from constructionrelated decisions and/or changes.
v. Design Compliance Review will include meetings with PRWD and GMC to
validate that the design requirements are being provided during the
Construction Phase. The meetings shall occur as necessary but not less than
every two weeks. One objective of these meetings will be to review the CMAR’s
documentation of any resultant changes in the projected costs resulting from
constructionrelated decisions and/or changes.
vi. Plant Operational Compliance includes all aspects of the Project that may
adversely affect the ability of the PRWD WTP to comply with all applicable
regulations. Any noncompliance event caused by the CMAR will be cause for
the CMAR to reimburse PRWD for all costs associated with the
noncompliance event including, but not limited to, fines, fees, PRWD staff,
corrective action, Owner’s Engineer, etc. Refer to Standard Form of
Agreement and Standard Form of General Conditions for more information.
vii. The System Programmer will be Inframark, Lord and Company, Southern Flow,
ICS Automated, or approved equal and will be responsible for design review
and integration services. The CMAR will contract with the System Programmer.
The System Programmer will serve as a subcontractor to the CMAR and will be
involved during design and construction. The scope and fee for the System
Programmer work will be negotiated by the CMAR during the contract
negotiation phase.
viii. Operation and Maintenance (O&M) Manuals will include, but are not
limited to, the following:
1. Supply a complete set of equipment O&M manuals that provide the
requisite components;
2. Supply an O&M manual for the instrumentation and control system,
including a complete log of the programming and signal tagging list;
Page 4 of 15
3. Supply a custom prepared O&M manual for the operation of the
overall facility that addresses, as a minimum, the startup and
shutdown under normal and emergency conditions;
4. Supply equipment summary reference sheets and maintenance
schedules for all major equipment with interface references to
equipment O&M;
5. Supply a troubleshooting section for normal and emergency
conditions; and
6. Supply O&M manuals for any additional elements necessary to
acquire the operating permits for the facility.
O&M documents shall be in PDF format and created from the software in which
they were produced or scanned at a resolution of 300 dpi or greater. Scanned
documents shall be scanned with the “original image with hidden text” option.
Documents scanned at 300 dpi or greater provides for optical character
recognition (OCR) and word search functionality. All text of the document
must be text selectable with the exception of pages which are in their entirety
drawings or diagrams.
Word searches of the PDF documents must operate successfully.
ix. Startup and Commissioning of the constructed facility will include
completion of the requisite startup and commissioning activities. As a
minimum, the activities will include the following:
1. Completion of equipment operational checkout and startup;
2. Operational testing of the individual systems; and
3. The operation of the overall facility as a whole under various
configurations necessary to demonstrate compliance with the
acceptance test requirements and the process performance criteria
defined in the final contract documents.
x. Operator Training shall be provided to the PRWD staff and videotaped by the
CMAR. The operator training will include prestartup training that will continue
through the startup, acceptance testing, and commissioning of the project. All
training scheduling will be coordinated with PRWD. All O&M Manuals will be
presented in electronic versions (format to be agreed upon by PRWD) and
hard copies.
xi. Coordinate with PRWD’s and GMC’s staff regarding all applicable components
of the project. Other subcontractors and PRWD may be performing work in
close proximity to or bordering on the work of the CMAR. The CMAR shall
cooperate in the coordination of their separate activities in a manner that will
provide the least interference with PRWD’s operations and in the interfacing and
connection of the separate elements of the overall project work.
xii. Construction Document Management shall be implemented as defined in the
construction management plan to collect and store the following data in a
Page 5 of 15
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Follow NM DEXTER NFHTC POND LINER 12B & 13B Active Contract Opportunity Notice

INTERIOR, DEPARTMENT OF THE

Bid Due: 6/24/2026

Home NOTICE TO BIDDERS Notice is hereby given NOTICE TO BIDDERS Notice is

MPN

Bid Due: 12/19/2079

Robertsdale USDA Force Main Upgrades Robertsdale, Alabama June 18, 2026 10:00 am Plans

Goodwyn Mills Cawood(GMC)

Bid Due: 6/18/2026

Follow Z2DA--Project 521-22-119 NRM Replace windows (VA-26-00016046) Active Contract Opportunity Notice ID 36C24726R0032

VETERANS AFFAIRS, DEPARTMENT OF

Bid Due: 6/18/2026