Jefferson County, From Old Lemay Ferry Road to Elm Drive, Pedestrian Improvements

Agency: Missouri Department of Transportation(MDOT)
State: Missouri
Type of Government: State & Local
NAICS Category:
  • 237310 - Highway, Street, and Bridge Construction
Posted Date: Aug 26, 2026
Due Date: Sep 25, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description

New Posting Posting Date Project Number Solicitation LPA Contact LPA Phone LPA Email Due Date
NEW 8/26/26 TAP-9902(616) Jefferson County, From Old Lemay Ferry Road to Elm Drive, Pedestrian Improvements Kurt Wengert, PE 636-797-5570 kwengert@jeffcomo.org 9/25/26

Attachment Preview

Jefferson County, Missouri
Maple Street Annex Dennis Gannon
725 Maple Street * PO Box 100 County Executive
Hillsboro, Missouri 63050
DEPARTMENT OF PUBLIC WORKS
Jason Jonas, P.E. - Director
Daniel Naunheim, P.E. - Deputy Director
Telephone: 636-797-5340 * Fax: 636-797-5565
Web Address: www.jeffcomo.org
Cecil Vivrett Kurt Wengert, P.E. Christina Mareschal Matt Stinchcomb Mike Cook
Highway Superintendent T e c h nical Division Manager Fleet Services Manager F a c i lity Maintenance Manager S t o rmwater Manager
636-797-5427 636-797-5570 636-797-5399 636-797-5574 636-797-6318
August 17, 2026
Dear Consultant:
The Jefferson County Department of Public Works is requesting the services of a consulting engineering firm to
perform the professional services described for the project included on the attached list. If your firm would like to
be considered for these consulting services, you may express your interest by responding to the appropriate office
which is indicated on the attachment. Limit your Letter of Interest (LOI) to no more than four (4) pages. This LOI
should include any information which might help us in the selection process, such as the persons or team you would
assign to the project, the backgrounds of those individuals, and other projects your company has recently completed,
or are now active, that are similar in scope.
The selection committee will evaluate submittals based on: (a) experience and technical competence of project
team; (b) capacity and capability of team to take on the project; (c) past record of performance with similar
clients/projects on design scope, schedule and project estimation (reference: 23 CFR 172 Administration of
Engineering & Design Related Service Contracts and RSMO 8.285 - 8.291).
It is required that your firm's Statement of Qualification (SOQ) (RSMo 8.285 through 8.291) and an Affidavit of
Compliance with the federal work authorization program, along with a copy of your company E-Verify
Memorandum of Understanding (15 CSR 60-15.020) be submitted with your firm's LOI or be on file with the
Jefferson County Department of Public Works. The SOQ is not included as part of the LOI. Please only send one
(1) copy of your SOQ.
We request that five (5) copies of your LOI be received by 4:00 pm on Friday, September 25, 2026, at the Jefferson
County Department of Public Works, PO Box 100, Hillsboro, Missouri 63050.
Sincerely,
Kurt Wengert, P.E.
Technical Division Manager
Jefferson County Department of Public Works
Attachments

Jefferson County, Miller Road Pedestrian Improvement Project
Project Number: TAP-9902(616)
Project Funding Source: Transportation Alternatives Program
Project Location/Description: From Old Lemay Ferry Road to Elm Drive
Project Improvement: Pedestrian Improvements
Project Length: 1.0 Miles
Estimated Construction Cost: Estimated at $2,500,000
Consultant Services Required: Roadway, Surveying, and Environmental: Consultant shall be responsible for professional engineering services including the preparation of preliminary plans, right- of-way and easement plats, final construction plans, technical specifications and construction cost estimation. As part of preparing the plans the consultant may need to perform field surveys, archaeological or environmental studies and geotechnical investigations. The consultant shall also be responsible for a limited number of construction engineering services including staking of new right-of-way corners, setting of pins post-construction, review of shop drawings and material certifications, perform any needed drawing revisions and respond to requests for information from both the Contractor and the County.
Other Comments: The TIP grant application is available on the Jefferson County website at the following location: https://www.jeffcomo.gov/DocumentCenter/View/21920/2026- --RFQ---Miller-Road-Pedestrian-Improvement-Project-TAP- Application-PDF All consultant questions or requests for information shall be made in writing to the contact shown below. No project briefing meetings will be granted during the RFQ process.
Contact: Kurt Wengert, PE Public Works Technical Manager PO Box 100 Hillsboro, MO 63050 636-797-5570 kwengert@jeffcomo.org
Submittal Deadline: September 25, 2026, at 4:00 pm
Submittal Package: Letter of interest should not exceed four (4) pages total. A page is defined as 8-1/2 by 11 inches and printed on one side. Five (5) copies of the letter of interest should be received at the address and by the time specified.
Submittal Delivery: Jefferson County Department of Public Works 725 Maple Street, Room 104 (Physical) PO Box 100 (Mailing) Hillsboro, Missouri 63050

Jefferson County, Miller Road Pedestrian Improvement Project
Project Number: TAP-9902(616)
Project Funding Source: Transportation Alternatives Program
Project Location/Description: From Old Lemay Ferry Road to Elm Drive
Project Improvement: Pedestrian Improvements
Project Length: 1.0 Miles
Estimated Construction Cost: Estimated at $2,500,000
Consultant Services Required: Roadway, Surveying, and Environmental:
Consultant shall be responsible for professional engineering
services including the preparation of preliminary plans, right-
of-way and easement plats, final construction plans, technical
specifications and construction cost estimation. As part of
preparing the plans the consultant may need to perform field
surveys, archaeological or environmental studies and
geotechnical investigations. The consultant shall also be
responsible for a limited number of construction engineering
services including staking of new right-of-way corners, setting
of pins post-construction, review of shop drawings and
material certifications, perform any needed drawing revisions
and respond to requests for information from both the
Contractor and the County.
Other Comments: The TIP grant application is available on the Jefferson County
website at the following location:
https://www.jeffcomo.gov/DocumentCenter/View/21920/2026-
--RFQ---Miller-Road-Pedestrian-Improvement-Project-TAP-
Application-PDF
All consultant questions or requests for information shall be
made in writing to the contact shown below. No project
briefing meetings will be granted during the RFQ process.
Contact: Kurt Wengert, PE
Public Works Technical Manager
PO Box 100
Hillsboro, MO 63050
636-797-5570
kwengert@jeffcomo.org
Submittal Deadline: September 25, 2026, at 4:00 pm
Submittal Package: Letter of interest should not exceed four (4) pages total. A
page is defined as 8-1/2 by 11 inches and printed on one
side. Five (5) copies of the letter of interest should be
received at the address and by the time specified.
Submittal Delivery: Jefferson County Department of Public Works
725 Maple Street, Room 104 (Physical)
PO Box 100 (Mailing)
Hillsboro, Missouri 63050

Pursuant to the Brooks Act for Consultant Selection; the following criteria will be the basis for reviews:
RFQ Rating Categories Points Available
Experience and Technical Competence of the Project Team -
* Team Members Professional Work History and Education 10 Points Maximum
* Consultant Firm History Working on Similar Projects 10 Points Maximum
* Examples of Innovative Solutions Used on Past Projects 10 Points Maximum
Subtotal = 30 Points Maximum
Capacity and Capability of Firm to Complete the Project -
* Prime Firm Capacity to Undertake the Project 10 Points Maximum
* Explanation of Proposed Subconsultants with Past Partnership History 10 Points Maximum
(if none, then prime firm will be rated out of 20 points maximum)
* Highlight Consultant Team Capabilities That Stand Out from Other Firms 10 Points Maximum
Subtotal = 30 Points Maximum
Past Record of Performance on Similar Projects -
* Meeting Design Scopes Proposed by Clients without Undo Overruns 10 Points Maximum
* Meeting Design Schedules Under Client Agreements 10 Points Maximum
* Accurate Project Cost Estimation with Examples in Full Detail 10 Points Maximum
* Client References and/or Recommendations 10 Points Maximum
Subtotal = 40 Points Maximum
Total Score = 100 Points Maximum

This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Notice - Progressive Design Build (PDB) Services for the Brush Creek Pump Station

Drexel Technologies

Status Bid Advertisement Post Date Revision Date Letting Date NEW STL District, City

Missouri Department of Transportation(MDOT)

Due by 11/19/2026

Request for Bids: Missouri Greenway: Monarch Chesterfield Levee Trail Signage Replacement Project Submittal

Great Rivers Greenway

Due by 11/06/2026

Status Bid Advertisement Post Date Revision Date Letting Date NEW NW District, City

Missouri Department of Transportation(MDOT)

Due by 11/13/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.