IAH Skyway Structural Improvements for the Houston Airport System

Agency: City of Houston
State: Texas
Type of Government: State & Local
NAICS Category:
  • 541330 - Engineering Services
Posted Date: Oct 24, 2025
Due Date: Dec 11, 2025
Solicitation No: CB-2025-0010
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
Reference Number: CB-2025-0010
Title: IAH Skyway Structural Improvements for the Houston Airport System
E-BID
Due Date: 12/11/2025

IAH Skyway Structural Improvements for the Houston Airport System
City of Houston, Texas
Get on Interest List
Details
Interest List
Q&A
E-Bid
Changes
Open
Reference No.
CB-2025-0010
Due Date
December 11, 2025 at 10:0:0 AM CST
Questions Due
11/10/2025
Site Visit - view Terminal(s) (Morning)
11/3/2025
Second Site Visit - Guideway Area (Evening)
11/3/2025
Conference Date
11/3/2025
Deadline to Submit Pre-Registration Site Visit Form
10/29/2025
Time Remaining
47 Days
Basic Info
Release Date
10/24/2025
Type
Competitive Bidding Method
Department(s)
Houston Airport System
Categories
CONSTRUCTION SERVICES, GENERAL, INCLUDING MAINTENANCE AND REPAIR SERVICES)
Trade Services, Construction, (Not Otherwise Classified)
Roofing and Siding
Glass and Glazing
Painting and Wallpapering
+ 4 more
Additional Info
Bid Bond Required
Yes
Contact Info
Contact Name
Jorge Ardines
Email Address
jorge.ardines@houstontx.gov
Phone No.
(281) 233-1620
Download Package
Attachments
E-Bid Attachments
Description

The Houston Airport System (HAS) is seeking a contractor to provide remedial rehabilitation to the Skyway Automated People Mover (APM) superstructure and substructure at George Bush Intercontinental Airport (IAH).


DBE Goal 0%

In Person Conference Date

Date: November 3, 2025 at 10:00 AM CST

A Pre-Bid Conference will be held in person.

Attendees will meet at the Houston Airport System Infrastructure Division Office (IDO) Building, Auditorium No. 1, 111 Standifer Drive, Humble, TX 77338.

A. Stipulated Price
#
Description
Details
Quantity
Est. Value
1
Stipulated Price
N/A
0
$0
B. Base Unit Price Table
#
Calendar Item
Item Description
Estimated Bid Quantity
UoM
Category
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
1A. Mobilization
Installation/removal of all traffic control devices, laydown yard, and cleaning/restoration of work areas.
1
lump sum
Mobilization/Demobilization
1B. Blackout Date
Blackout Periods removal/installation of all traffic control devices, and cleaning/restoration of work areas for temporary use during the blackout.
1
lump sum
Mobilization/Demobilization
2. Install and Maintain TCP
Traffic Control Devices
1
lump sum
Traffic Control
3. Running Beam Coating and Waterproofing
Running Beam Coating: Coating system of a crack bridging and waterproofing product on running beams and deck. Fill cracks with SIKAFLEX 444 and apply waterproofing SIKALASTIC Vehicular 2900 or equal.
1,750
square foot
Surface Repair
4. Running Beam Nosing Repair
Nosing Repair: Contractor shall use a saw cut (or other tools) to square damages in the running guideway beam at the joints or intersections. Repair the area using rapid-set mortar and epoxy mortar.
36
square foot
Surface Repair
5. Shear Key, Bearing Pad replacement, Grout Pad and Steel Diaphragm Installation
Grout Repair: Contractor shall remove the damaged grout under steel connections on the skyway. Following preparing the area, form and pour the area sing rapid-set mortar
10
square foot
Surface Repair
6. Curb Repair & Contraction Joints
Curb repair: The contractor shall remove the damaged curb and install a new curb (6"x 5") to match the existing thickness and elevation. The price includes installing new steel dowels to the existing slab and applying corrosion inhibitor paint (AMP UP RB or equivalent).
101
linear foot
Surface Repair
7. Curb Repair & Contraction Joints
Contraction Joints: The contractor shall use an appropriate saw machine and saw-cut up to 1/8" of the existing curb down to the existing structural slab without damaging the slab and seal the cut with a flexible sealant such as Sikaflex -2c NS EZ Mix+ or equivalent.
115
linear foot
Surface Repair
8. Crack Injection
Epoxy Injection: for structural cracks wider than .004" and less than 1/4": Epoxy inject cracks with SIKADUR 31 HI-MOD GEL Cap Seal, SIKADUR 35, and HI-MOD LV Epoxy Resin. for structural cracks wider than 1/4": Epoxy inject cracks with SIKADUR 31 HI-MOD GELCap Seal and SIKADUR INJECTION GEL Epoxy Resin
11,462
linear foot
Surface Repair
9. Expansion Joints
Expansion joint: The contractor shall remove and replace the existing expansion joints. Price EMSEAL Colorseal Seismic, including nosing repair if needed. In areas lower than 1", the backer rod and sealant shall be used following EOR approval. The contractor shall coordinate with the manufacturer regarding warranty
970
linear foot
Surface Repair
10. Spalling Repair & Plate Repair
Friction Coating: The contractor shall prepare a steel plate in the transition zones for new epoxy coating. The new coating shall match the existing one
250
square foot
Surface Repair
11. Spalling Repair & Plate Repair
Partial-depth Concrete Repair (Spalling)—Contractor Repair horizontal concrete spalls up to 3" in depth per ICRI Guidelines. Price (SIKACRETE 211, SIKACRETE 211 SCC PLUS, SIKAQUICK 1000, SIKA VOH or Equivalent following consulting with EOR.) Work to include saw cutting, replacement of deteriorated steel, surface preparation and coating of exposed steel.
16,474
square foot
Bridge Repairs
12. Spalling Repair & Plate Repair
Full Depth Concrete Repair - Repair horizontal concrete spalls up to full depth (8" depth) of the concrete slab edge per ICRI Guidelines Price (SIKACRETE 211, SIKACRETE 211 SCC PLUS or equivalent). Work to include saw cutting, replacement of deteriorated steel, surface preparation and coating of exposed steel.
250
square foot
Bridge Repairs
13. Shear Key, Bearing Pad replacement, Grout Pad and Steel Diaphragm Installation
Steel Diaphragm: Contractor shall install diaphragms between prestressed beams. The work includes steel beams, connection plates, drilling, and grouting of holding down bolts
40
each
Bridge Repairs
14. Shear Key, Bearing Pad replacement, Grout Pad and Steel Diaphragm Installation
Shear Key: Contractor shall prepare the areas for shear keys and install a shear key as shown in the details. Work to include drilling anchors, installing steel reinforcement and concrete/non-shrink grout.
40
each
Bridge Repairs
15. Shear Key, Bearing Pad replacement, Grout Pad and Steel Diaphragm Installation
Bearing Pad: The contractor shall remove and replace the damaged bearing pad with a new bearing pad matching the existing bearing pad property. Work includes lifting the span as necessary to replace the indicated bearing pad in accordance with TXDOT spec (Item 787). Bearing pad material in accordance with TxDOT spec 434.
40
each
Bridge Repairs
16. Shear Key, Bearing Pad replacement, Grout Pad and Steel Diaphragm Installation
Grout Pad: Remove the delaminated grout pad and prepare the area up to engineers of record satisfaction. Form the area and pour fiber-reinforced concrete or non-shrink grout to match the existing.
12
square foot
Bridge Repairs
17. Spalling Repair & Plate Repair
Rust Spot Concrete Repair - Remove miscellaneous exposed steel from concrete and repair per ICRI guidelines. Price (AMP UP RB and SIKATOP 123 PLUS)
250
each
Bridge Repairs
18. Strengthening of Existing Structure
FRP strengthening: The contractor shall coat the area receiving FRP fabric material with Sika 330, a two-component, medium-viscosity structural epoxy adhesive, immediately before installing it. Then, Pre-saturate FRP fabric with SIKADUR 300, a two-component, low-viscosity structural epoxy saturant resin, and apply the saturated material to the prepared surface. Or use equal upon EOR approval.
3,500
square foot
FRP
19. Strengthening of Existing Structure
Ledge Beam: contractor shall design and provide 0.31in2/ft steel equivalent to the bent caps experiencing bending cracks. Prior to installing FRP spikes, the contractor shall use GPR to locate the steel locations. The FRP installation shall be in between the prestressed beams.
1,800
linear foot
FRP
C. Extra Unit Price Table
#
Description
Details
Quantity
Est. Value
1
Extra Unit Price Table
N/A
0
$0
D. Cash Allowance Table
#
Description
Spec Ref.
Quantity
UoM
Cash Allowance
1
2
3
Building Permit
01210
1
lump sum
$50,000
Environmental Testing and Disposal Allowance - Drain gaskets and bearing pads will be tested by others during Construction. If materials are found to be asbestos containing, the allowance will be utilized to pay for an asbestos disposal by the Contractor. If the materials are not asbestos containing, the allowance will not be utilized.
01210
1
lump sum
$200,000
Additional Flaggers, Barricades, Site Conditions and specific safety conditions improvements
01210
1
lump sum
$50,000
Open
Reference No.
CB-2025-0010
Due Date
December 11, 2025 at 10:0:0 AM CST
Questions Due
11/10/2025
Site Visit - view Terminal(s) (Morning)
11/3/2025
Second Site Visit - Guideway Area (Evening)
11/3/2025
Conference Date
11/3/2025
Deadline to Submit Pre-Registration Site Visit Form
10/29/2025
Time Remaining
47 Days
This solicitation is an E-Bid. Please register and fill out the form.
You will receive an email with a secure link to submit your response.
Register for E-Bid Submission
Contact Information
1
A. Stipulated Price
2
B. Base Unit Price Table
3
C. Extra Unit Price Table
4
D. Cash Allowance Table
5
Document 410A – Bid Form – Part A
6
Document 410B – Bid Form – Part B
7
Document 00430 – Bidder's Bond Security Deposit (as defined in Document 00200 – Instructions to Bidders)
8
Document 00450 – Bidder's Statement of MWSBE Status
9
Document 00454 – Affidavit of Non-Interest
10
Document 00455 – Ownership Information Form
11
Document 00456 – Bidder’s Certificate of Compliance with Buy American Program (required for AIP funded project)
12
Document 00457 – Conflicts of Interest Questionnaire (CIQ)
13
Document 00458 – Bidder’s Certificate Regarding Foreign Trade Restriction (required for AIP funded project)
14
Document 00459 – Contractor’s Statement Regarding Previous Contracts Subject to EEO (required for AIP funded project)
15
Document 00460 – Pay or Play Acknowledgement Form (POP 1-A)
16
Document 00470D - Bidder’s DBE Participation Plan (required for AIP funded project)
17
Document 00480 – Form SCM-1 Reference Verification
18
Document 00481 – Non-Collusion Statement
19
Document 00600 – List of Proposed Subcontractors and Suppliers
Contact Information
Company
Company Name
Company Address
City
State
Select a state
Postal Code
Special Designation
Select business designations
Contact
Contact Name
Contact Phone
Contact Email
Contact Position
Next
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Project: WATER AND WASTEWATER MAIN REPLACEMENTS AT VARIOUS LOCATIONS Ref. #: CIZ-DWU 26

City of Dallas

Bid Due: 7/10/2026

Project: RFSQ - Professional Landscape Architectural and Engineering Services for the Hardy Downtown

Harris County

Bid Due: 7/20/2026

Project: ITB - Replacement of the Existing Generator at the Harris County Sheriff's

Harris County

Bid Due: 6/29/2026

Campus-Wide IP Speaker and Cabling Project Solicitation ID: 26.4026 Due Date: 7/9/2026 Due

State Government of Texas

Bid Due: 7/09/2026