Highway Department Road Materials & Services

Agency: Town of Douglas
State: Massachusetts
Type of Government: State & Local
NAICS Category:
  • 237310 - Highway, Street, and Bridge Construction
Posted Date: May 6, 2026
Due Date: Jun 4, 2026
Solicitation No: 26-1
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
Bid Number: 26-1
Bid Title: Highway Department Road Materials & Services
Category: Town Bids
Status: Open
Publication Date/Time:
5/6/2026 7:30 AM
Closing Date/Time:
6/4/2026 10:00 AM
Related Documents:

Attachment Preview

THE COMMONWEALTH OF MASSACHUSETTS
EXECUTIVE OFFICE OF LABOR AND WORKFORCE DEVELOPMENT
DEPARTMENT OF LABOR STANDARDS
Prevailing Wage Rates
As determined by the Director under the provisions of the
MAURA HEALEY LAUREN JONES
Massachusetts General Laws, Chapter 149, Sections 26 to 27H
Governor Secretary
KIM DRISCOLL MICHAEL FLANAGAN
Lt. Governor Director
Awarding Authority: Douglas - Highway Department City/Town: DOUGLAS
Contract Number: 26-1
Description of Work: 6" yellow center line, 6: white edge line; 4: yellow centerline; 4: white edge line
Job Location: Various Roads
Information about Prevailing Wage Schedules for Awarding Authorities and Contractors
* The wage rates will remain in effect for the duration of the project, except in the case of multi-year public construction projects. For construction projects lasting
longer than one year, awarding authorities must request an updated wage schedule no later than two weeks before the anniversary of the date the contract was
executed by the awarding authority and the general contractor. For multi-year CM AT RISK projects, the awarding authority must request an annual update no
later than two weeks before the anniversary date, determined as the earlier of: (a) the execution date of the GMP Amendment, or (b) the execution date of the
first amendment to permit procurement of construction services. The updated wage schedule must be provided to all contractors, including general and sub-
contractors, working on the construction project.
* This annual update requirement is generally not applicable to 27F "rental of equipment" contracts. For such contracts, the prevailing wage rates issued by DLS
shall remain in effect for the duration of the contract term. However, if the prevailing wage rate sheet issued does not contain wage rates for each year covered
by the contract term, the Awarding Authority must request updated rate sheets from DLS and provide them to the contractor to ensure the correct rates are being
paid throughout the duration of the contract. Additionally, if an Awarding Authority exercises an option to renew or extend the contract term, they must request
updated rate sheets form DLS and provide them to the contractor.
* This wage schedule applies only to the specific project referenced at the top of this page and uniquely identified by the "Wage Request Number" on all pages of
this schedule.
* An Awarding Authority must request an updated wage schedule if it has not opened bids or selected a contractor within 90 days of the date of issuance of the
wage schedule. For CM AT RISK projects (bid pursuant to G.L. c.149A), the earlier of: (a) the execution date of the GMP Amendment, or (b) the bid for the
first construction scope of work must be within 90-days of the wage schedule issuance date.
* The wage schedule shall be incorporated in any advertisement or call for bids for the project as required by M.G.L. c. 149, 27. The wage schedule shall be
made a part of the contract awarded for the project. The wage schedule must be posted in a conspicuous place at the work site for the life of the project in
accordance with M.G.L. c. 149 27. The wages listed on the wage schedule must be paid to employees performing construction work on the project whether
they are employed by the prime contractor, a filed sub-bidder, or a sub-contractor.
* Apprentices working on the project are required to be registered with the Massachusetts Division of Apprentice Standards (DAS). Apprentices must keep their
apprentice identification card on their persons during all work hours on the project. An apprentice registered with DAS may be paid the lower apprentice wage
rate at the applicable step as provided on the prevailing wage schedule. Any apprentice not registered with DAS regardless of whether they are registered
with another federal, state, local, or private agency must be paid the journeyworker's rate.
* Every contractor or subcontractor working on the construction project must submit weekly payroll reports and a Statement of Compliance directly to the
awarding authority by mail or email and keep them on file for three years. Each weekly payroll report must contain: the employee's name, address, occupational
classification, hours worked, and wages paid. Do not submit weekly payroll reports to DLS. For a sample payroll reporting form go to
http://www.mass.gov/dols/pw.
* Contractors with questions about the wage rates or classifications included on the wage schedule have an affirmative obligation to inquire with DLS at (617)
626-6953.
* Contractors must obtain the wage schedules from awarding authorities. Failure of a contractor or subcontractor to pay the prevailing wage rates listed on the
wage schedule to all employees who perform construction work on the project is a violation of the law and subjects the contractor or subcontractor to civil and
criminal penalties.
* Employees not receiving the prevailing wage rate set forth on the wage schedule may file a complaint with the Fair Labor Division of the office of the Attorney
General at (617) 727-3465.
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 1 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
(2 AXLE) DRIVER - EQUIPMENT 1/1/2026 $40.95 $16.17 $21.78 $0.00 $0.00 $78.90
TEAMSTERS JOINT COUNCIL NO. 10
6/1/2026 $41.95 $16.17 $21.78 $0.00 $0.00 $79.90
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
12/1/2026 $41.95 $16.17 $23.52 $0.00 $0.00 $81.64
1/1/2027 $41.95 $16.77 $23.52 $0.00 $0.00 $82.24
(3 AXLE) DRIVER - EQUIPMENT 1/1/2026 $41.02 $16.17 $21.78 $0.00 $0.00 $78.97
TEAMSTERS JOINT COUNCIL NO. 10
6/1/2026 $42.02 $16.17 $21.78 $0.00 $0.00 $79.97
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
12/1/2026 $42.02 $16.17 $23.52 $0.00 $0.00 $81.71
1/1/2027 $42.02 $16.77 $23.52 $0.00 $0.00 $82.31
(4 & 5 AXLE) DRIVER - EQUIPMENT 1/1/2026 $41.14 $16.17 $21.78 $0.00 $0.00 $79.09
TEAMSTERS JOINT COUNCIL NO. 10
6/1/2026 $42.14 $16.17 $21.78 $0.00 $0.00 $80.09
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
12/1/2026 $42.14 $16.17 $23.52 $0.00 $0.00 $81.83
1/1/2027 $42.14 $16.77 $23.52 $0.00 $0.00 $82.43
ADS/SUBMERSIBLE PILOT 8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 2)
For apprentice rates see "Apprentice- PILE DRIVER"
AIR TRACK OPERATOR 12/1/2025 $41.22 $10.65 $9.75 $9.11 $0.00 $70.73
LABORERS
6/1/2026 $42.66 $10.65 $9.75 $9.11 $0.00 $72.17
LABORERS - ZONE 2
12/1/2026 $44.10 $10.65 $9.75 $9.11 $0.00 $73.61
6/1/2027 $45.55 $10.65 $9.75 $9.11 $0.00 $75.06
12/1/2027 $47.00 $10.65 $9.75 $9.11 $0.00 $76.51
6/1/2028 $48.50 $10.65 $9.75 $9.11 $0.00 $78.01
12/1/2028 $50.00 $10.65 $9.75 $9.11 $0.00 $79.51
For apprentice rates see "Apprentice- LABORER"
AIR TRACK OPERATOR (HEAVY & HIGHWAY) 12/1/2025 $41.22 $10.65 $9.75 $9.21 $0.00 $70.83
LABORERS
6/1/2026 $42.66 $10.65 $9.75 $9.21 $0.00 $72.27
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $44.10 $10.65 $9.75 $9.21 $0.00 $73.71
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
ASBESTOS WORKER (PIPES & TANKS) 12/1/2025 $44.80 $14.50 $4.30 $6.75 $0.00 $70.35
HEAT & FROST INSULATORS LOCAL 6
HEAT & FROST INSULATORS LOCAL 6 (WORCESTER)
ASPHALT RAKER 12/1/2025 $40.72 $10.65 $9.75 $9.11 $0.00 $70.23
LABORERS
6/1/2026 $42.16 $10.65 $9.75 $9.11 $0.00 $71.67
LABORERS - ZONE 2
12/1/2026 $43.60 $10.65 $9.75 $9.11 $0.00 $73.11
6/1/2027 $45.05 $10.65 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.50 $10.65 $9.75 $9.11 $0.00 $76.01
6/1/2028 $48.00 $10.65 $9.75 $9.11 $0.00 $77.51
12/1/2028 $49.50 $10.65 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
ASPHALT RAKER (HEAVY & HIGHWAY) 12/1/2025 $40.72 $10.65 $9.75 $9.21 $0.00 $70.33
LABORERS
6/1/2026 $42.16 $10.65 $9.75 $9.21 $0.00 $71.77
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $43.60 $10.65 $9.75 $9.21 $0.00 $73.21
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 2 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
ASPHALT/CONCRETE/CRUSHER PLANT-ON SITE 12/1/2025 $58.68 $16.55 $13.35 $3.25 $0.00 $91.83
OPERATING ENGINEERS LOCAL 4
6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
BACKHOE/FRONT-END LOADER 12/1/2025 $58.68 $16.55 $13.35 $3.25 $0.00 $91.83
OPERATING ENGINEERS LOCAL 4
6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
BARCO-TYPE JUMPING TAMPER 12/1/2025 $40.72 $10.65 $9.75 $9.11 $0.00 $70.23
LABORERS
6/1/2026 $42.16 $10.65 $9.75 $9.11 $0.00 $71.67
LABORERS - ZONE 2
12/1/2026 $43.60 $10.65 $9.75 $9.11 $0.00 $73.11
6/1/2027 $45.05 $10.65 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.50 $10.65 $9.75 $9.11 $0.00 $76.01
6/1/2028 $48.00 $10.65 $9.75 $9.11 $0.00 $77.51
12/1/2028 $49.50 $10.65 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
BLOCK PAVER, RAMMER / CURB SETTER 12/1/2025 $41.22 $10.65 $9.75 $9.11 $0.00 $70.73
LABORERS
6/1/2026 $42.66 $10.65 $9.75 $9.11 $0.00 $72.17
LABORERS - ZONE 2
12/1/2026 $44.10 $10.65 $9.75 $9.11 $0.00 $73.61
6/1/2027 $45.55 $10.65 $9.75 $9.11 $0.00 $75.06
12/1/2027 $47.00 $10.65 $9.75 $9.11 $0.00 $76.51
6/1/2028 $48.50 $10.65 $9.75 $9.11 $0.00 $78.01
12/1/2028 $50.00 $10.65 $9.75 $9.11 $0.00 $79.51
For apprentice rates see "Apprentice- LABORER"
BLOCK PAVER, RAMMER / CURB SETTER (HEAVY & 12/1/2025 $41.22 $10.65 $9.75 $9.21 $0.00 $70.83
HIGHWAY)
6/1/2026 $42.66 $10.65 $9.75 $9.21 $0.00 $72.27
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY) 12/1/2026 $44.10 $10.65 $9.75 $9.21 $0.00 $73.71
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
BOILER MAKER 1/1/2024 $48.12 $7.07 $14.60 $6.00 $0.00 $75.79
BOILERMAKERS LOCAL 29
BOILERMAKERS LOCAL 29
Apprentice: BOILER MAKER
Effective Date: 1/1/2024
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57
2 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57
3 70.00 $33.68 $7.07 $10.03 $4.20 $0.00 $54.98
4 75.00 $36.09 $7.07 $10.74 $4.50 $0.00 $58.40
5 80.00 $38.50 $7.07 $11.45 $4.80 $0.00 $61.82
6 85.00 $40.90 $7.07 $12.18 $5.10 $0.00 $65.25
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 3 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
Apprentice: BOILER MAKER
Effective Date: 1/1/2024
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
7 90.00 $43.31 $7.07 $12.88 $5.40 $0.00 $68.66
8 95.00 $45.71 $7.07 $13.62 $5.70 $0.00 $72.10
Apprentice to Journeyworker Ratio: 1:4
BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY 2/1/2026 $65.81 $12.84 $15.57 $7.33 $0.00 $101.55
WATERPROOFING)
8/1/2026 $68.01 $12.84 $15.57 $7.33 $0.00 $103.75
BRICKLAYERS LOCAL 3
BRICKLAYERS LOCAL 3 (WORCESTER) 2/1/2027 $69.41 $12.84 $15.57 $7.33 $0.00 $105.15
Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)
Effective Date: 2/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $32.91 $12.84 $15.57 $7.33 $0.00 $68.65
2 60.00 $39.49 $12.84 $15.57 $7.33 $0.00 $75.23
3 70.00 $46.07 $12.84 $15.57 $7.33 $0.00 $81.81
4 80.00 $52.65 $12.84 $15.57 $7.33 $0.00 $88.39
5 90.00 $59.23 $12.84 $15.57 $7.33 $0.00 $94.97
Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)
Effective Date: 8/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $34.01 $12.84 $15.57 $7.33 $0.00 $69.75
2 60.00 $40.81 $12.84 $15.57 $7.33 $0.00 $76.55
3 70.00 $47.61 $12.84 $15.57 $7.33 $0.00 $83.35
4 80.00 $54.41 $12.84 $15.57 $7.33 $0.00 $90.15
5 90.00 $61.21 $12.84 $15.57 $7.33 $0.00 $96.95
Apprentice to Journeyworker Ratio: 1:5
BULLDOZER/GRADER/SCRAPER 12/1/2025 $58.02 $16.55 $13.35 $3.25 $0.00 $91.17
OPERATING ENGINEERS LOCAL 4
6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
CAISSON & UNDERPINNING BOTTOM MAN 12/1/2025 $49.10 $10.65 $9.75 $9.80 $0.00 $79.30
LABORERS
6/1/2026 $50.65 $10.65 $9.75 $9.80 $0.00 $80.85
LABORERS - FOUNDATION AND MARINE
12/1/2026 $52.15 $10.65 $9.75 $9.80 $0.00 $82.35
For apprentice rates see "Apprentice- LABORER"
CAISSON & UNDERPINNING LABORER 12/1/2025 $47.95 $10.65 $9.75 $9.80 $0.00 $78.15
LABORERS
6/1/2026 $49.50 $10.65 $9.75 $9.80 $0.00 $79.70
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 4 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
LABORERS - FOUNDATION AND MARINE 12/1/2026 $51.00 $10.65 $9.75 $9.80 $0.00 $81.20
For apprentice rates see "Apprentice- LABORER"
CAISSON & UNDERPINNING TOP MAN 12/1/2025 $48.28 $10.65 $9.75 $9.80 $0.00 $78.48
LABORERS
6/1/2026 $49.83 $10.65 $9.75 $9.80 $0.00 $80.03
LABORERS - FOUNDATION AND MARINE
12/1/2026 $51.33 $10.65 $9.75 $9.80 $0.00 $81.53
For apprentice rates see "Apprentice- LABORER"
CARBIDE CORE DRILL OPERATOR 12/1/2025 $40.72 $10.65 $9.75 $9.11 $0.00 $70.23
LABORERS
6/1/2026 $42.16 $10.65 $9.75 $9.11 $0.00 $71.67
LABORERS - ZONE 2
12/1/2026 $43.60 $10.65 $9.75 $9.11 $0.00 $73.11
6/1/2027 $45.05 $10.65 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.50 $10.65 $9.75 $9.11 $0.00 $76.01
6/1/2028 $48.00 $10.65 $9.75 $9.11 $0.00 $77.51
12/1/2028 $49.50 $10.65 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
CARPENTER 3/1/2026 $50.85 $11.08 $11.47 $8.50 $0.00 $81.90
CARPENTERS
9/1/2026 $52.10 $11.08 $11.47 $8.50 $0.00 $83.15
CARPENTERS -ZONE 2 (Eastern Massachusetts)
3/1/2027 $53.35 $11.08 $11.47 $8.50 $0.00 $84.40
Apprentice: CARPENTER
Effective Date: 3/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69
2 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69
3 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45
4 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45
5 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19
6 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19
7 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00
8 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00
Apprentice: CARPENTER
Effective Date: 9/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26
2 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26
3 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14
4 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14
5 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06
6 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06
7 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00
8 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00
Apprentice to Journeyworker Ratio: 1:5
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 5 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
CARPENTER WOOD FRAME 10/1/2025 $27.37 $7.38 $4.47 $1.00 $0.00 $40.22
CARPENTERS
10/1/2026 $28.47 $7.38 $4.47 $1.00 $0.00 $41.32
CARPENTERS-ZONE 3 (Wood Frame)
All Aspects of New Wood Frame Work
Apprentice: CARPENTER WOOD FRAME
Effective Date: 10/1/2025
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80
2 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80
3 65.00 $17.79 $7.38 $0.00 $1.00 $0.00 $26.17
4 70.00 $19.16 $7.38 $0.00 $1.00 $0.00 $27.54
5 75.00 $20.53 $7.38 $3.80 $1.00 $0.00 $32.71
6 80.00 $21.90 $7.38 $3.80 $1.00 $0.00 $34.08
7 85.00 $23.26 $7.38 $3.80 $1.00 $0.00 $35.44
8 90.00 $24.63 $7.38 $3.80 $1.00 $0.00 $36.81
Apprentice: CARPENTER WOOD FRAME
Effective Date: 10/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46
2 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46
3 65.00 $18.51 $7.38 $0.00 $1.00 $0.00 $26.89
4 70.00 $19.93 $7.38 $0.00 $1.00 $0.00 $28.31
5 75.00 $21.35 $7.38 $3.80 $1.00 $0.00 $33.53
6 80.00 $22.78 $7.38 $3.80 $1.00 $0.00 $34.96
7 85.00 $24.20 $7.38 $3.80 $1.00 $0.00 $36.38
8 90.00 $25.62 $7.38 $3.80 $1.00 $0.00 $37.80
Apprentice to Journeyworker Ratio: 1:5
CEMENT MASONRY/PLASTERING 1/1/2026 $53.24 $13.35 $16.43 $7.78 $1.80 $92.60
PLASTERERS AND CEMENT MASONS LOCAL 534
7/1/2026 $54.49 $13.35 $16.43 $7.78 $1.80 $93.85
Plasterers and Cement Masons - Zone 1
1/1/2027 $55.94 $13.35 $16.43 $7.78 $1.80 $95.30
7/1/2027 $57.29 $13.35 $16.43 $7.78 $1.80 $96.65
1/1/2028 $58.64 $13.35 $16.43 $7.78 $1.80 $98.00
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 1/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $26.62 $13.35 $16.43 $0.00 $0.00 $56.40
2 60.00 $31.94 $13.35 $16.43 $7.78 $1.80 $71.30
3 65.00 $34.61 $13.35 $16.43 $7.78 $1.80 $73.97
4 70.00 $37.27 $13.35 $16.43 $7.78 $1.80 $76.63
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 6 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 1/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
5 75.00 $39.93 $13.35 $16.43 $7.78 $1.80 $79.29
6 80.00 $42.59 $13.35 $16.43 $7.78 $1.80 $81.95
7 90.00 $47.92 $13.35 $16.43 $0.00 $0.00 $77.70
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 7/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $27.25 $13.35 $16.43 $0.00 $0.00 $57.03
2 60.00 $32.69 $13.35 $16.43 $7.78 $1.80 $72.05
3 65.00 $35.42 $13.35 $16.43 $7.78 $1.80 $74.78
4 70.00 $38.14 $13.35 $16.43 $7.78 $1.80 $77.50
5 75.00 $40.87 $13.35 $16.43 $7.78 $1.80 $80.23
6 80.00 $43.59 $13.35 $16.43 $7.78 $1.80 $82.95
7 90.00 $49.04 $13.35 $0.00 $7.78 $0.00 $70.17
Apprentice to Journeyworker Ratio: 1:5
CHAIN SAW OPERATOR 12/1/2025 $40.72 $10.65 $9.75 $9.11 $0.00 $70.23
LABORERS
6/1/2026 $42.16 $10.65 $9.75 $9.11 $0.00 $71.67
LABORERS - ZONE 2
12/1/2026 $43.60 $10.65 $9.75 $9.11 $0.00 $73.11
6/1/2027 $45.05 $10.65 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.50 $10.65 $9.75 $9.11 $0.00 $76.01
6/1/2028 $48.00 $10.65 $9.75 $9.11 $0.00 $77.51
12/1/2028 $49.50 $10.65 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
CLAM SHELLS/SLURRY BUCKETS/HEADING MACHINES 12/1/2025 $59.88 $16.55 $13.35 $3.25 $0.00 $93.03
OPERATING ENGINEERS LOCAL 4
6/1/2026 $60.61 $17.05 $13.35 $3.25 $0.00 $94.26
OPERATING ENGINEERS LOCAL 4
12/1/2026 $62.09 $17.05 $13.35 $3.25 $0.00 $95.74
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
COMPRESSOR OPERATOR 12/1/2025 $37.37 $16.55 $13.35 $3.25 $0.00 $70.52
OPERATING ENGINEERS LOCAL 4
6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28
OPERATING ENGINEERS LOCAL 4
12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
DELEADER (BRIDGE) 1/1/2026 $59.56 $10.35 $12.00 $12.60 $0.00 $94.51
PAINTERS LOCAL 35
PAINTERS LOCAL 35 - ZONE 2
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 7 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
Apprentice: DELEADER (BRIDGE)
Effective Date: 1/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $29.78 $10.35 $0.00 $0.00 $0.00 $40.13
2 55.00 $32.76 $10.35 $0.00 $6.93 $0.00 $50.04
3 60.00 $35.74 $10.35 $0.00 $7.56 $0.00 $53.65
4 65.00 $38.71 $10.35 $0.00 $8.19 $0.00 $57.25
5 70.00 $41.69 $10.35 $12.00 $8.82 $0.00 $72.86
6 75.00 $44.67 $10.35 $12.00 $9.45 $0.00 $76.47
7 80.00 $47.65 $10.35 $12.00 $10.08 $0.00 $80.08
8 90.00 $53.60 $10.35 $12.00 $11.34 $0.00 $87.29
Apprentice to Journeyworker Ratio: 1:1
DEMO: ADZEMAN 12/1/2025 $48.00 $10.65 $9.75 $9.65 $0.00 $78.05
LABORERS
6/1/2026 $49.55 $10.65 $9.75 $9.65 $0.00 $79.60
LABORERS - ZONE 2
12/7/2026 $51.05 $10.65 $9.75 $9.65 $0.00 $81.10
6/7/2027 $52.65 $10.65 $9.75 $9.65 $0.00 $82.70
12/6/2027 $54.25 $10.65 $9.75 $9.65 $0.00 $84.30
6/5/2028 $55.93 $10.65 $9.75 $9.65 $0.00 $85.98
12/4/2028 $57.60 $10.65 $9.75 $9.65 $0.00 $87.65
For apprentice rates see "Apprentice- LABORER"
DEMO: BACKHOE/LOADER/HAMMER OPERATOR 12/1/2025 $49.00 $10.65 $9.75 $9.65 $0.00 $79.05
LABORERS
6/1/2026 $50.55 $10.65 $9.75 $9.65 $0.00 $80.60
LABORERS - ZONE 2
12/7/2026 $52.05 $10.65 $9.75 $9.65 $0.00 $82.10
6/7/2027 $53.65 $10.65 $9.75 $9.65 $0.00 $83.70
12/6/2027 $55.25 $10.65 $9.75 $9.65 $0.00 $85.30
6/5/2028 $56.93 $10.65 $9.75 $9.65 $0.00 $86.98
12/4/2028 $58.60 $10.65 $9.75 $9.65 $0.00 $88.65
For apprentice rates see "Apprentice- LABORER"
DEMO: BURNERS 12/1/2025 $48.75 $10.65 $9.75 $9.65 $0.00 $78.80
LABORERS
6/1/2026 $50.30 $10.65 $9.75 $9.65 $0.00 $80.35
LABORERS - ZONE 2
12/7/2026 $51.80 $10.65 $9.75 $9.65 $0.00 $81.85
6/7/2027 $53.40 $10.65 $9.75 $9.65 $0.00 $83.45
12/6/2027 $55.00 $10.65 $9.75 $9.65 $0.00 $85.05
6/5/2028 $56.68 $10.65 $9.75 $9.65 $0.00 $86.73
12/4/2028 $58.35 $10.65 $9.75 $9.65 $0.00 $88.40
For apprentice rates see "Apprentice- LABORER"
DEMO: CONCRETE CUTTER/SAWYER 12/1/2025 $49.00 $10.65 $9.75 $9.65 $0.00 $79.05
LABORERS
6/1/2026 $50.55 $10.65 $9.75 $9.65 $0.00 $80.60
LABORERS - ZONE 2
12/7/2026 $52.05 $10.65 $9.75 $9.65 $0.00 $82.10
6/7/2027 $53.65 $10.65 $9.75 $9.65 $0.00 $83.70
12/6/2027 $55.25 $10.65 $9.75 $9.65 $0.00 $85.30
6/5/2028 $56.93 $10.65 $9.75 $9.65 $0.00 $86.98
12/4/2028 $58.60 $10.65 $9.75 $9.65 $0.00 $88.65
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 8 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
For apprentice rates see "Apprentice- LABORER"
DEMO: JACKHAMMER OPERATOR 12/1/2025 $48.75 $10.65 $9.75 $9.65 $0.00 $78.80
LABORERS
6/1/2026 $50.30 $10.65 $9.75 $9.65 $0.00 $80.35
LABORERS - ZONE 2
12/7/2026 $51.80 $10.65 $9.75 $9.65 $0.00 $81.85
6/7/2027 $53.40 $10.65 $9.75 $9.65 $0.00 $83.45
12/6/2027 $55.00 $10.65 $9.75 $9.65 $0.00 $85.05
6/5/2028 $56.68 $10.65 $9.75 $9.65 $0.00 $86.73
12/4/2028 $58.35 $10.65 $9.75 $9.65 $0.00 $88.40
For apprentice rates see "Apprentice- LABORER"
DEMO: WRECKING LABORER 12/1/2025 $48.00 $10.65 $9.75 $9.65 $0.00 $78.05
LABORERS
6/1/2026 $49.55 $10.65 $9.75 $9.65 $0.00 $79.60
LABORERS - ZONE 2
12/7/2026 $51.05 $10.65 $9.75 $9.65 $0.00 $81.10
6/7/2027 $52.65 $10.65 $9.75 $9.65 $0.00 $82.70
12/6/2027 $54.25 $10.65 $9.75 $9.65 $0.00 $84.30
6/5/2028 $55.93 $10.65 $9.75 $9.65 $0.00 $85.98
12/4/2028 $57.60 $10.65 $9.75 $9.65 $0.00 $87.65
For apprentice rates see "Apprentice- LABORER"
DIRECTIONAL DRILL MACHINE OPERATOR 12/1/2025 $58.02 $16.55 $13.35 $3.25 $0.00 $91.17
OPERATING ENGINEERS LOCAL 4
6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
DIVER 8/1/2024 $78.11 $10.08 $11.62 $12.67 $0.00 $112.48
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 2)
as of 8-1-24, Apprentices with diving licenses begin at second year. % of Diver wage 70/80/90 2A $69.83, 3A $91.79,4A $102.14 Total Rate
DIVER TENDER 8/1/2024 $51.97 $10.08 $11.62 $12.67 $0.00 $86.34
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 2)
as of 8-1-24, Apprentices with diving licenses begin at second year. % of Piledriver wage 70/80/90 2A $54.20, 3A $73.93,4A $82.05 Total Rate
DIVER TENDER (EFFLUENT) 8/1/2024 $83.69 $10.08 $11.62 $12.67 $0.00 $118.06
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 2)
For apprentice rates see "Apprentice- PILE DRIVER"
DIVER/SLURRY (EFFLUENT) 8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 2)
For apprentice rates see "Apprentice- PILE DRIVER"
DRAWBRIDGE OPERATOR (Construction) 7/1/2020 $26.77 $6.67 $3.93 $0.00 $0.16 $37.53
DRAWBRIDGE - SEIU LOCAL 888
DRAWBRIDGE - SEIU LOCAL 888
ELECTRICIAN 9/7/2025 $48.16 $14.98 $14.30 $5.30 $0.00 $82.74
ELECTRICIANS LOCAL 96
9/6/2026 $49.38 $15.96 $14.57 $5.43 $0.00 $85.34
ELECTRICIANS LOCAL 96
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 9 of 31

Construction
Supplemental Total
Classification Effective Date Base Wage Health Pension Annuity Unemployment Rate
Apprentice: ELECTRICIAN
Effective Date: 9/7/2025
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 40.00 $19.26 $14.98 $0.58 $0.00 $0.00 $34.82
2 45.00 $21.67 $14.98 $0.65 $0.00 $0.00 $37.30
3 48.00 $23.12 $14.98 $13.55 $2.54 $0.00 $54.19
4 55.00 $26.49 $14.98 $13.65 $2.92 $0.00 $58.04
5 65.00 $31.30 $14.98 $13.80 $3.45 $0.00 $63.53
6 80.00 $38.53 $14.98 $14.02 $4.24 $0.00 $71.77
Apprentice: ELECTRICIAN
Effective Date: 9/6/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 40.00 $19.75 $15.96 $0.59 $0.00 $0.00 $36.30
2 45.00 $22.22 $15.96 $0.67 $0.00 $0.00 $38.85
3 48.00 $23.70 $15.96 $13.80 $2.61 $0.00 $56.07
4 55.00 $27.16 $15.96 $13.90 $2.99 $0.00 $60.01
5 65.00 $32.10 $15.96 $14.05 $3.53 $0.00 $65.64
6 80.00 $39.50 $15.96 $14.28 $4.35 $0.00 $74.09
Apprentice to Journeyworker Ratio: 2:3
ELEVATOR CONSTRUCTOR 1/1/2026 $69.23 $16.38 $11.06 $10.70 $0.00 $107.37
ELEVATOR CONSTRUCTORS LOCAL 41
1/1/2027 $72.23 $16.48 $11.16 $11.00 $0.00 $110.87
ELEVATOR CONSTRUCTORS LOCAL 41
Apprentice: ELEVATOR CONSTRUCTOR
Effective Date: 1/1/2026
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $34.62 $16.38 $0.00 $0.00 $0.00 $51.00
2 55.00 $38.08 $16.38 $11.06 $10.70 $0.00 $76.22
3 65.00 $45.00 $16.38 $11.06 $10.70 $0.00 $83.14
4 70.00 $48.46 $16.38 $11.06 $10.70 $0.00 $86.60
5 80.00 $55.38 $16.38 $11.06 $10.70 $0.00 $93.52
Apprentice: ELEVATOR CONSTRUCTOR
Effective Date: 1/1/2027
Apprentice Supplemental Total
Step Percent Base Wage Health Pension Annuity Unemployment Rate
1 50.00 $36.12 $16.48 $0.00 $0.00 $0.00 $52.60
2 55.00 $39.73 $16.48 $11.16 $11.00 $0.00 $78.37
3 65.00 $46.95 $16.48 $11.16 $11.00 $0.00 $85.59
Issue Date: 05/04/2026 Wage Request Number: 20260504140828 Page 10 of 31

This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Header Information Bid Number: BD-19-1272-ADMNS-ADMNS-131533 Description: Highway Materials Bid Opening Date: 08/10/2026 02:00:00

Commonwealth of Massachusetts

Bid Due: 8/10/2026

Bid Solicitation: BD-21-1021-DFS-DFS01-58331 Header Information Bid Number: BD-21-1021-DFS-DFS01-58331 Description: DFSMH RFR for Sand

Commonwealth of Massachusetts

Bid Due: 12/31/2026

Bid Solicitation: BD-23-1030-CPO1-CPO1-78412 Responses Due in 3272 Days, 4 Hours, 30 Minutes Header

Commonwealth of Massachusetts

Bid Due: 8/01/2031

Header Information Bid Number: BD-27-1030-CPO1-CPO1-131646 Description: Due Diligence Continuous Concrete Mix Station Bid

Commonwealth of Massachusetts

Bid Due: 8/05/2026