Procurement #: 51825>
CITY OF PROVIDENCE, RHODE ISLAND
Department: Sustainability
RFP Title: RFP for EV Infrastructure at the Telecommunications Department
Opening Date: 02/09/2026
Addendum #: 1
Issue Date: 01/20/2026
The purpose of this addendum is to extend the proposal bid and deadline to February 9th,
2026 and responding to questions.
Providence City Hall
25 Dorrance Street
Providence, RI 02903
MAYOR BRETT P. SMILEY
CITY OF PROVIDENCE
RFP Addendum 1: Deadline Extension & Response to Bidder Questions
RFP for EV Infrastructure at the Telecommunications Department
MinuteTraq #: 51825
Date to be opened: 2/9/2026 at 2:15 p.m.
Please note that this addendum must be signed and included with your proposal package.
A. The proposal deadline is being extended by two weeks. Proposals and bids are now due
Monday, February 9, 2026 at 2:15 p.m.
B. The following are the City’s responses to questions asked at this RFP’s pre-bid conference on
January 7, 2026 and/or emailed to the City before the question submission deadline on January
11, 2026.
1. Davis Bacon
This project is federally funded through a U.S. Department of Energy Energy Efficiency and
Conservation Block Grant. As such, the awarded vendor will need to comply with Davis Bacon
wage requirements. Further, Davis Bacon reporting must be submitted via an online portal. The
awarded vendor will meet with U.S. DOE prior to beginning the project to be set up in the
portal and to ensure a proper understanding of reporting requirements.
2. ITC Eligibility
This project is eligible for an ITC credit from the federal government. To maximize the credit,
the awarded vendor shall use a registered apprentice(s), to complete the project. The awarded
vendor will meet with the City’s consultant who assists the City with ITC compliance prior to
the start of the project to ensure the vendor’s approach to project will be recognized by the
federal government and enable the City to apply for the credit following construction.
Department of Sustainability
75 Chapman Street, Providence, Rhode Island 02905
Phone: 401.680.5476 | www.providenceri.gov
3. Proposal Scoring
Per page 16 of the RFP, project approach and contractor experience are factors in the award
decision, along with bid price. Please review and follow the Proposal and Scoring section of the
RFP (page 16, section 4) to ensure your firm is submitting a complete proposal that can earn
the maximum number of points during the review process.
4. Analysis of Future Electrical Capacity
While the scope only calls for the installation of two single-port EV chargers, the awarded
vendor shall provide an assessment of the capacity to add stations in the future. For example,
how many ports can be added under existing service conditions, when will the need for service
or transformer upgrades kick in, can upgrades be avoided through the introduction of a charge
management system while still meeting the operational needs of the fleet. This assessment will
be part of the project scope and is not something that needs to be included with your proposal.
5. Should service or transformer upgrades be factored into the bid price?
The scope of work only calls for adding two, single-port EV chargers to the site at this time.
Service and transformer upgrades should only be included in the bid price if either will be
required to support these two ports. The City understands that service and/or transformer
upgrades will likely be required for a full site buildout and is requesting that the awarded
vendor assess exactly what upgrades will be needed for a full site buildout as part of the
project scope (see item 3 above).
6. Can additional site visits be scheduled?
No.
7. When is the start date, if awarded?
The City’s goal is to make an award on March 9,2026 and have a vendor under contract by late-
March to early-April. The project timeline will be coordinated with the City’s DPW, which will
be doing the sitework. The project shall be scheduled between early-April and May 31, 2026.
8. Is there a bonding requirement for this project?
Per page 5 of the RFP, no financial assurance is necessary for this item.
9. What are the insurance requirements for this project?
Page 2 of 3
The City’s standard insurance terms are:
• General Liability Insurance—Property damage and bodily injury: $1,000,000 per
occurrence; $2,000,000 aggregate limit.
• Owned, Hired, and Non-Owned Automobile Liability Insurance: for bodily injury, wrongful
death, and property damage, $1,000,000 per occurrence; $2,000,000 aggregate.
• Workers’ Compensation and Occupational Disease Insurance: including Employer’s Liability-
Statutory Limit, such employer’s liability limits for bodily injury by accident or disease to not
be less than $500,000 each accident, $500,000 each employee and $500,000 policy limit.
• Umbrella Liability Insurance: $5,000,000 per occurrence; $5,000,000 aggregate.
• Professional Liability covering negligent acts, errors, and omissions in the performance of
professional services with policy limits of not less than $5,000,000 per claim and in the
aggregate. Said coverage shall have a deductible not exceeding $100,000 per occurrence
and shall remain in effect continuously from the effective date of this Contract to ten years
after substantial completion of this Contract.
• Pollution Liability Insurance: $2,000,000 policy limit for bodily injury, property damage, and
resulting loss of use and environmental damages resulting from sudden accidental (and/or
gradual if appropriate) pollution and related cleanup costs.
Authorized Bidder Representative Name: ________________________________________
Authorized Bidder Representative Title: _________________________________________
Authorized Bidder Representative Signature: _____________________________________
Page 3 of 3