Enhanced Commissioning of Systems & Envelope for a New Buncombe County EMS Station

Agency: Buncombe County
State: North Carolina
Type of Government: State & Local
NAICS Category:
  • 236220 - Commercial and Institutional Building Construction
  • 541330 - Engineering Services
Posted Date: Feb 26, 2024
Due Date: Mar 14, 2024
Bid Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
Enhanced Commissioning of Systems & Envelope for a New Buncombe County EMS Station

Buncombe County is seeking qualified candidates interested in providing Enhanced Commissioning of Systems and Envelope for a new Buncombe County EMS Station currently being designed. The facility is approximately 12,214 GSF and includes (3) Bays for Emergency Vehicles, Support Areas, Office Areas, and Living Areas for Staff. The facility is to be constructed in Swannanoa, N.C.

Table: News Item Documents
File Name Size Type Date & Time Added
EMS Enhanced Commissioning - RFQ 358 KB 02/26/2024 10:12 AM

Attachment Preview

``
General Services Department
Robert M. Brown
Project Manager
REQUEST FOR QUALIFICATIONS ADVERTISEMENT
TITLE:
ENHANCED COMMISSIONING OF SYSTEMS AND ENVELOPE FOR A NEW
BUNCOMBE COUNTY EMS STATION
DATE ISSUED:
FEBRUARY 26, 2024
DUE DATE:
MARCH 14, 2024
TIME:
2:00 PM
LOCATION:
BUNCOMBE COUNTY GENERAL SERVICES DEPARTMENT
40 MCCORMICK PLACE
ASHEVILLE, NC 28801
TELEPHONE:
(828)250-4233
REQUEST FOR QUALIFICATIONS
Pursuant to the General Statutes of North Carolina, statements of qualification will be received
for the following:
COMMISIONING SERVICES FOR ENHANCED COMMISSIONING OF SYSTEMS AND ENVELOPE FOR A
NEW BUNCOMBE COUNTY EMS STATION.
Buncombe County is seeking Statements of Qualifications from qualified firms interested in
providing systems and envelope enhanced commissioning for a 3 bay EMS station currently
in the design phase. Statements of qualification will be accepted until MARCH 14, 2024,
AT 2:00 PM for the above named items, at the Buncombe County General Services
Department, 40 McCormick Place, Asheville, North Carolina, 28801. Prior experience in
systems and envelop commissioning for EMS facilities is encouraged. Buncombe County
encourages submittals from minority businesses by providing certified minorities an
equal opportunity to participate in all aspects of the RFQ process. One digital copy in
.pdf format of said statements of qualifications must be submitted in person or by email
to generalservices@buncombecounty.org, pam.king@buncombecounty.org , and
robert.brown@buncombecounty.org. Questions about the project may be asked by
contacting the General Services Department project manager at (828) 250-4784 or by
email at robert.brown@buncombecounty.org .
Request for Qualifications Authorized by:
Mike Mace
Director, General Services
e. robert.brown@buncombecounty.org
p. (828) 250-4784 c. (828) 767-3432
buncombecounty.org
``
General Services Department
Robert M. Brown
Project Manager
A. Purpose:
Buncombe County is seeking qualified candidates interested in providing Enhanced
Commissioning of Systems and Envelope for a new Buncombe County EMS Station currently
being designed. The facility is approximately 12,214 GSF and includes (3) Bays for
Emergency Vehicles, Support Areas, Office Areas, and Living Areas for Staff. The facility is to
be constructed in Swannanoa, N.C.
B. Services Required Summary:
The contracted Commissioning Provider (CxP) will provide commissioning services for
[Buncombe County] OWNER to provide [LEED v4 BD+C New Construction] Fundamental and
Verification Commissioning (Energy and Atmosphere Prerequisite) services for the facility.
Also, the (CxP) shall provide [LEED v4 BD+C New Construction] Enhanced Commissioning
[Energy and Atmosphere credit, Option 1, Path 1 (3 points)] services and Enhanced and
Monitoring-Based Commissioning [Energy and Atmosphere credit, Option 1, Path 2 (4
points)] services for the facility. Finally, Envelope Commissioning [Energy and Atmosphere
credit, Option 2 (2 points)] (BECx) services shall be provided for the facility.
Fundamental Commissioning and Verification Services
In summary, Fundamental Commissioning services will include:
1) Design Phase:
a. Commissioning Provider CxP will be contracted after the completion of the
design development phase to lead, review, and oversee the commissioning
process in accordance with ASHRAE Guideline 0-2005 and ASHRAE Guideline 1.1-
2007. The CxP will work directly under the direction of the OWNER.
b. The CxP will review the Owner’s Project Requirements (OPR) and the Basis of
Design (BOD) as developed by the design team. The CxP will submit comments to
the Owner and A/E for consideration.
c. The CxP will participate in [LEED®] progress meetings (conference calls) to review
the project status and provide status updates on the commissioning process. (2
Meetings)
d. The CxP will prepare a design commissioning outline describing the
commissioning process, team structure with a summary of roles and
responsibilities, preliminary time requirements for each project phase and
identification of the types of equipment and systems to be commissioned.
e. robert.brown@buncombecounty.org
p. (828) 250-4784 c. (828) 767-3432
buncombecounty.org
``
General Services Department
Robert M. Brown
Project Manager
e. The CxP will review the contract documents prepared by the A/E and comment
as relevant to the commissioning process and to ensure project coordination for
the MEP systems and exterior enclosure design. To meet the [LEED®]
requirements, the design review shall be performed during the mid-design phase
to ensure the project team has time to make any necessary changes. The review
f. will include a back check of the 90% design documents to verify comments have
been responded to. (2 Review Totals)
g. The CxP will assist the A/E in preparing the specifications for commissioning. The
actual preparation of the contract documents is the sole responsibility of the
A/E.
2) Construction Phase:
a. The CxP will prepare and submit the Cx plan for Owner and A/E review and
approval.
b. The CxP will schedule and conduct a Cx kickoff meeting with the Cx team. (1
Virtual Meeting)
c. The CxP will participate in [LEED®] progress meetings (conference calls) to review
the project status and provide status updates on the commissioning process. (2
Meetings)
d. The CxP will schedule and conduct scheduled commissioning meetings with the
commissioning team to review the commissioning plan and progress. The CxP
will generate and distribute meeting minutes to the team. (4 Virtual Meetings
Total)
e. The CxP will schedule and conduct project site observations of the installation to
assess compliance with the contract documents. Any observed deficiencies will
be brought to the attention of the Owner, A/E, and contractor via an agreed
upon issue tracking system. (2 Site Visits Total)
f. The CxP will coordinate the sequencing and timing of commissioning activities
into the overall project schedule with the Owner, A/E, and contractor.
g. The CxP will review and update the project schedule with the commissioning
team to ensure all required commissioning activities, sequences and durations
are incorporated.
h. The CxP will develop and maintain a construction issue tracking system to make
sure all issues raised during commissioning are documented, addressed,
followed up and tracked until a resolution is reached.
e. robert.brown@buncombecounty.org
p. (828) 250-4784 c. (828) 767-3432
buncombecounty.org
``
General Services Department
Robert M. Brown
Project Manager
i. The CxP will prepare and issue Pre-Functional Checklists (PFC’s) for the
contractor to complete. The PFC’s shall serve as documentation that the
installation was performed in accordance with the contract documents. The
Contractor shall be responsible for executing the PFC’s. The PFC’s shall be
completed prior to the commencement of functional performance testing.
j. The CxP will finalize building systems and equipment Functional Performance
Tests (FPTs). The updated tests will contain specific information required to
demonstrate correct operation under all modes of operation with applicable
pass/fail criteria.
3) Acceptance Phase:
a. The CxP shall conduct Functional Performance Testing (FPTs), designed, and
developed during earlier project phases by the Contractor and the CxP, for
equipment and systems.
b. The CxP will record the results of the FPTs. All deficiencies or non-conformance
issues shall be noted as Action Items, and the cost for the CxP to retest shall be
paid by the Contractor responsible for the deficiency.
c. Owner shall pay the CxP directly and back charge the responsible Contractor.
d. The CxP will prepare and maintain a Current Facilities Requirements and
Operations and Maintenance Plan that consist of information necessary to
operate the building efficiently.
e. The CFR and O+M Plan will include a Sequence of Operations, Occupancy
Schedule, Equipment Schedules, System Setpoints, Lighting Levels, Minimum
Outside Air Requirements, System Narratives and Preventative Maintenance.
f. The CxP will prepare and submit a summary Cx report to the Owner.
g. [The CxP will prepare and submit all required LEED® documentation to LEED®
online for Fundamental Commissioning.]
Enhanced Commissioning and Verification Services
In summary, Fundamental Commissioning services will include:
1. Design Phase:
a. The CxP will be independent from the project design and construction team and
report findings directly to the OWNER.
b. The CxP will verify the inclusion of system manual requirements in the
construction documents.
c. The CxP will verify the inclusion of operator and occupant training requirements
in the construction documents.
e. robert.brown@buncombecounty.org
p. (828) 250-4784 c. (828) 767-3432
buncombecounty.org
``
General Services Department
Robert M. Brown
Project Manager
2. Construction Phase:
a. The CxP will review and comment on equipment and system submittals related
to the systems being commissioned. The CxP will consult with the A/E and
contractor regarding compliance with the design intent. The Owner and A/E
have final approval authority over all submittals
3. Acceptance Phase:
a. The CxP will verify operator (O&M) and occupant training delivery and
effectiveness. The contractor will provide O&M literature and training personnel
in accordance with the contract documents.
b. The CxP will review and evaluate the O&M manuals for completeness.
c. The CxP will receive and review the System Manual as submitted by the
contractor to verify the System Manual and all other design and construction
records have been updated and include all modifications made during the
Construction Phase. The CxP will verify that the System Manual achieves the
OPR. The CxP will insert system descriptions as provided by the design
professional(s) in the System Manual.
d. The CxP will develop an on-going commissioning plan.
e. [The CxP will prepare and submit all required LEED® documentation to LEED®
online for Enhanced Commissioning.]
4. Post-Acceptance Phase:
a. The CxP will review the building systems operation with the O&M staff 8-10
months after the final acceptance of the project. If there are any system issues,
the CxP will work with the O&M staff to develop a plan for resolution of the
system issues as a part of Additional Services.
Enhanced and Monitoring-Based Commissioning and Verification Services
In addition to the Enhanced Commissioning and Verification Services described above, the
Contracted CxP will develop monitoring-based procedures and identify points to be measured
and evaluated to assess performance of energy-and-water consuming systems.
Include the procedures and measurement points in the commissioning plan. Address the
following:
roles and responsibilities;
measurement requirements (meters, points, metering systems, data access);
the points to be tracked, with frequency and duration for trend monitoring;
e. robert.brown@buncombecounty.org
p. (828) 250-4784 c. (828) 767-3432
buncombecounty.org

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Solicitation Number Project Title Description Opening Date Posted Date Status Department 287-21-16730-01 NC

State Government of North Carolina

Bid Due: 5/20/2024

Follow DEVCOM ARMY RESEARCH LABORATORY BROAD AGENCY ANNOUNCEMENT FOR FOUNDATIONAL RESEARCH Active Contract

DEPT OF DEFENSE

Bid Due: 11/20/2027

Solicitation Number Project Title Description Opening Date Posted Date Status Department 179-2324-723 GMP

State Government of North Carolina

Bid Due: 5/09/2024

Solicitation Number Project Title Description Opening Date Posted Date Status Department 96-2405_DS-2819 NCCCS

State Government of North Carolina

Bid Due: 5/09/2024