CP090925 Russell Hall Thermal Comfort Improvements
| Agency: | University of Connecticut |
|---|---|
| State: | Connecticut |
| Type of Government: | State & Local |
| Posted Date: | Dec 8, 2025 |
| Due Date: | Dec 10, 2025 |
| Solicitation No: | CP090925 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
CP090925 Russell Hall Thermal Comfort Improvements
| Number | CP090925 |
| Open | 11/06/2025 |
| Close | 12/10/2025 2:00 PM EDT UPDATED |
| Type | ITB - Invitation to Bid |
|
Pre-Bid
|
Non-Mandatory
11/13/2025 10:00 AM EDT
3 Discovery Drive, Purchasing Bid Room
|
|
RFI
|
11/20/2025 2:00 PM |
| Contact | Chris Peters (860) 486-6324 |
| Details | Only previously prequalified contractors may submit a bid for this project. |
| Documents | CP090925-Project-Information .pdf |
Attachment Preview
PROJECT INFORMATION SHEET
CONSTRUCTION - GENERAL CONTRACTOR/TRADE CONTRACTOR
INVITATION TO BID
ELIGIBLE PREQUALIFIED BIDDERS: The following Contractors are prequalified and may submit a bid for
this Project:
•
All State Construction Inc
•
Ferguson Mechanical Company, Inc
•
Lee Kennedy Co., Inc.
•
The Whiting-Turner Contracting Company
PROJECT SCHEDULE/DURATION:
• Anticipated Contract Issuance/Notice to Proceed: January 2026
• Construction is planned to start: May 22, 2026
• Installation work in the dorm rooms must be completed by: August 7, 2026
• Hydronic balancing of the dorm room FCUs to be complete by August 19, 2026
• Heating system and associated controls must be complete by: October 1, 2026
• Make up air systems to be complete by December 31, 2026
• Cooling systems must be operational by: April 15, 2026
PROJECT DESCRIPTION/SCOPE OF WORK: Installation of mechanical equipment, piping, ductwork, and
controls. Mechanical equipment to include new make up air units, fan coil units, convectors, pumps, and
heat exchangers. Architectural and structural modifications to support mechanical work. Electrical work
associated with new mechanical equipment. Fire protection and fire alarm system modifications are
associated with new mechanical work.
Project Info. Sheet Construction GC-Trade ITB, November 6, 2025
Page 1 of 1
This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email
Receive daily bid alerts that match your keywords, business categories, and target regions.
See Also
Greeneville Fire House HVAC Upgrade The intent of this project is to improve
State Government of Connecticut
Due by 11/05/2026
Project ID: 26/27-17 Title: FURNISH AND INSTALL INSERTS FOR SIPHONS 1 & 3
Town of Manchester
Due by 11/17/2026
Window Replacement Services Addendum #1 Addendum #2
Town of Plainfield
Due by 11/10/2026
NUMBER TITLE STATUS BID TYPE NAME CONTACT INFORMATION AVAILABLE DATE CLARIFICATION DEADLINE DUE
Regional Water Authority
Due by 11/12/2026
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.