The Project involves the renovation of a portion of the Second and Third Levels and Exterior Improvements at the Historic UP Depot building located at 121 West 15th Street, Cheyenne, Wyoming. The Project involves furnishing all labor, materials, services, and equipment required for the project, including, but not limited to selective demolition, site work, repairs and treatment of historic stone masonry, work on historic wood windows, finishes, electrical, mechanical and other related items of work.
Timeline
Release Project Date:
August 5, 2025
Legal Advertisement 1 of 2:
August 8, 2025
Legal Advertisement 2 of 2:
August 15, 2025
Pre-Bid Meeting (Mandatory):
August 19, 2025, 10:00am
Cheyenne Depot, 121 West 15th Street, Cheyenne, Wyoming
Question Submission Deadline:
August 28, 2025, 5:00pm
Masonry and Painting Subcontractor Prequalification Statements Due:
August 28, 2025, 5:00pm
Notice of Subcontractor Prequalification Requirement
Masonry and Painting Subcontractor Prequalification Statements, are due no later than August 28, 2025.
See Bid Specs:
SECTION 00 4513
MASONRY SUBCONTRACTOR'S PREQUALIFICATION SUBMITTAL
SECTION 00 4514
PAINTING SUBCONTRACTOR'S PREQUALIFICATION SUBMITTAL
Submissions must be sent via email to TJ Barttelbort at
tbarttelbort@cheyennecity.org
.
Prequalification is a requirement for these two subcontractor trades.
Addendum Response Deadline:
September 2, 2025, 5:00pm
Proposal Submission Deadline:
September 9, 2025, 2:00pm
City Council 1st Reading: :
September 22, 2025
Finance Committee: :
October 7, 2025
City Council Final Approval :
October 13, 2025
Contract Signature Processing:
October 14, 2025
Notice to Proceed (Estimated):
October 22, 2025
Substantial Completion (Interior Renovation):
February 27, 2026
Substantial Completion (Plaza Work):
April 15, 2026
Substantial Completion (Exterior Masonry and Painting):
May 15, 2026
Final Completion:
30 days after Substantial Completion
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.
Sign-up for a Free Trial, Government Bid Alerts
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Try One Week FREE Now
See Also
Follow GRTE CHILLER REPAIR Active Contract Opportunity Notice ID 140P1426Q0079 Related Notice Department/Ind.
INTERIOR, DEPARTMENT OF THE
Bid Due: 6/24/2026
Project ID: Title: 2026 Crack Seal Addenda: 0 Release Date: 6/16/2026 Due Date:
City of Cheyenne
Bid Due: 7/13/2026
Follow PVC Roofs Active Contract Opportunity Notice ID FA461326B0001 Related Notice Department/Ind. Agency
DEPT OF DEFENSE
Bid Due: 6/23/2026
Project ID: Title: 2026 Crack Seal Addenda: 0 Release Date: 6/16/2026 Due Date:
City of Cheyenne
Bid Due: 7/13/2026