Cedar Creek Section 4 Pipeline Replacement and Cedar Creek Lake Pump Station Improvements
| Agency: | Tarrant Regional Water District |
|---|---|
| State: | Texas |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Aug 13, 2026 |
| Due Date: | Sep 21, 2026 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
Project ID:
Title: Cedar Creek Section 4 Pipeline Replacement and Cedar Creek Lake Pump Station Improvements
Addenda: 0
Release Date: 8/13/2026
Due Date: 9/21/2026
Post Information
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Summary
The Tarrant Regional Water District (Owner) is requesting Proposals for the construction of the following Project:
CEDAR CREEK SECTION IV PIPELINE REPLACEMENT AND CEDAR CREEK LAKE PUMP STATION IMPROVEMENTS
Background
PROJECT DESCRIPTION
The work includes demolishing approximately 780 linear feet of existing PCCP header and yard piping connecting the pump station to the current 72 inch transmission main; installing about 885 linear feet of new header and yard piping with all associated structural, mechanical, and electrical components to connect the pump station to a proposed 90 inch transmission main; installing 42,298 linear feet of 90 inch welded steel pipe from the Cedar Creek Pump Station westward to a tie-in with the existing 72 inch main approximately 2,600 feet east of the Trinity River; installing two 72 inch venturi meters with vaults and appurtenances; plugging and grouting about 507 linear feet of existing 72 inch PCCP; demolishing all electrical, safety, and instrumentation components in the former chlorine, ammonia, and caustic feed rooms; relocating the caustic feed skid to a new caustic feed room; and installing and integrating new low- and high-head caustic feed systems with the existing infrastructure. The work also includes the installation of two (2) monolithic isolation joints and all incidental work at the Ennis Booster Pump Station suction and discharge headers.
Timeline
6613 Ashby Lane, Trinidad, Texas, 75163
A guided tour of the Site will be held immediately after the pre-proposal meeting for those Offerors that are eligible to submit a Proposal for the Project.
See Also
Bid Information Type Low Bid- Formal Construction Status Issued Number 2027-0002 (Traffic Management
City of El Paso
Due by 10/07/2026
LOCAL LET MAINTENANCE CONTRACT, DUVAL CO, EMULSION Follow Solicitation Solicitation ID: 6506-34-001_1026 Status:
State Government of Texas
Due by 10/08/2026
Follow GIWW Freeport to Matagorda Maintenance Dredging Active Contract Opportunity Notice ID W912HY26BA021
DEPT OF DEFENSE
Due by 10/13/2026
Bid Information Type Request For Qualifications Status Issued Number RFQ FY26-ENG-32 (Zacate Creek
City of Laredo
Due by 10/08/2026