Building Renovation & HVAC Installation at RWP Gateway Garage Addendum 3

Agency: City of Providence
State: Rhode Island
Type of Government: State & Local
NAICS Category:
  • 236220 - Commercial and Institutional Building Construction
  • 238220 - Plumbing, Heating, and Air-Conditioning Contractors
Posted Date: Dec 19, 2025
Due Date: Dec 29, 2025
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Building Renovation & HVAC Installation at RWP Gateway Garage Addendum 3

Attachment Preview

Procurement #: 51231>
CITY OF PROVIDENCE, RHODE ISLAND
Department: Parks
RFP Title: BUILDING RENOVATIONS & HVAC INSTALLATION AT RWP GATEWAY GARAGE
Opening Date: 12/29/2025
Addendum #: 3
Issue Date: 12/18/2025
The purpose of this addendum is:
See attachments
Providence City Hall
25 Dorrance Street
Providence, RI 02903
WENDY NILSSON
Superintendent of Parks
BRETT P. SMILEY
Mayor
Addendum # 3
Building Renovations & HVAC Installation at RWP Gateway Garage
DECEMBER 18, 2025
Total Pages Including Cover (18 Pages)
Acknowledge Addenda on Bid Form
** BID DUE DATE MONDAY, DECEMBER 29, 2025 AT 2:15PM **
Attachments:
1. Addendum Cover Sheet (4 Pages)
2. Image of Existing Electrical Panel (1 Page)
3. Fire Alarm Control Panel Spec Sheet (4 Pages)
4. Metal Awning Drawing (1 Page)
5. Garage Door Lintel Photo (1 page)
6. Revised Plan Sheets (7 Pages)
Questions/Clarifications:
1. Q: Detail 1/L-2 references haunch dimensions indicating the finish grade may vary between 1 ½"
and 12". Please confirm the intended finish grade elevation for pricing purposes, or advise
where the grade transition occurs
A: See Grading Plan on sheet L-1 (#24) for finished grade adjacent to walk
2. Q: Are there are liquidated damages associated with the contract?
A: No, there will be no liquidated damages in the contract terms
3. Q: Is the existing ACT ceiling is to remain in place or be removed?
A: The existing ceiling is to be removed
4. Q: Should the existing plywood & drywall on the existing CMU walls be removed and disposed
of?
A: Yes, although the existing plywood panels will be salvaged if they are in satisfactory condition.
5. Q: Are the existing interior walls in the current storage room constructed with metal studs??
PROVIDENCE PARKS DEPARTMENT
1000 Elmwood Avenue, Providence, RI 02905
Phone: 401-680-7201
WENDY NILSSON
Superintendent of Parks
BRETT P. SMILEY
Mayor
A: No, they are wooden studs
6. Q: Please advise on the best means of access for delivering materials to the building. Should any
additional costs be included, such as temporary removal/reinstallation of fencing, site
restoration, re-loaming, etc.?
A: See question 8 on Addendum 1, contractor is responsible for restoring site to pre-construction
condition in any areas disturbed by construction or vehicles.
7. Q: Is the ceiling required to receive gypsum board fireproofing? Note A-114 mentions gypsum
fireproofing under reflected ceiling notes, but no locations are indicated on the drawings. Please
clarify.
A: No, the ceiling only receives Closed Cell Spray Foam Ceiling Insulation R-49.
8. Q: Is drywall penetration barrier mesh is required at all drywall partitions? Additionally, provide
the required gauge and preferred manufacturer.
A: Barrier Mesh is not required at any partitions, Please strike Item 3.5 in Section 09 22 16 of the
Specifications.
9. Q: Has the owner verified that the existing electrical service could support an upgrade to a 200A
main circuit breaker? Should the contractor assume the existing panel is capable of a 200A
circuit breaker and not include any additional costs to upgrading the existing panel?
A: Yes, it is rated for 225A, no upgrades to the panel are needed. (see attached photo)
10. Q: Sheet E210 (riser diagram) notes that the electrical contractor is to make secondary
connections to the new transformer. Is there an anticipated transformer being installed that the
contractor should be aware of?
A: No, this is a standard note and not specific to the project.
11. Q: Please verify whether the tilt-up doors require power. The electrical drawings do not show
circuitry at these locations.
A: No power, the doors are manual.
12. Q: Will the Owner remove all existing items currently inside the building prior to
commencement of construction?
A: Yes, all items not fixed to the walls, floor, or ceiling will be removed
13. Q: Is there any required work related to the existing exterior security camera system?
A: No.
14. Q: Does the owner require the GC to paint the exterior wood fascia as part of this project?
PROVIDENCE PARKS DEPARTMENT
1000 Elmwood Avenue, Providence, RI 02905
Phone: 401-680-7201
WENDY NILSSON
Superintendent of Parks
BRETT P. SMILEY
Mayor
A: No.
15. Q: What is the existing FACP (Fire Alarm Control Panel) make and model?
A: Upon investigation, there is no existing FACP, please carry a cost for installing a new panel.
Basis-of-design product: Fire-Lite MS-5UD-3. See attached spec sheet.
16. Q: Please provide specifications for metal awnings.
A: Basis-of-design is ‘Fortress’ Awning by Rustica, see attached product sheet.
17. Q: Is air & water testing required for new windows?
A: No.
18. Q: Is the HVAC system is fully design-build by the contractor?Which governs for bidding if there
is a conflict between H-101 and the RFP/specs.
A: HVAC is fully design-build, with H-101 provided as a framework for the design, H-101 takes
precedent over the Specs.
19. Q: Are the listed Carrier units mandatory, or basis-of-design only? If equals are allowed, please
confirm minimum capacity/efficiency requirements.
A: They are not mandatory, any substitute must match or exceed the capacity and efficiency of the
specified Carrier Units. (Efficiency 16.0 SEER2 Cooling/8.1 EER2 Heating)
20. Q: Is the HVAC system stand-alone or must it tie into an existing BMS?
A: It is a stand-alone system
21. Q: Please confirm final locations and sizes for the FC-1 access panel and return grille, and
required service clearances?
A: Locations shown are final. Required clearance between unit and service panel is 24” if
adjustments to walls are needed to accommodate this clearance, the cost will be covered by the
allowance.
22. Q: Is there any service or panel upgrade required beyond what is shown?
A: See Question 9
23. Q: For the unit price 'F&I HVAC System, complete,' define what is included (mechanical only or
also electrical, controls, patching, etc.). Also confirm how SF items (ceilings, flooring, insulation)
will be measured for changes.
A: This would include all work required to install the system, including the mechanical, electrical,
controls, & patching. the only item not included would be the concrete pad for the exterior units.
Any changes to SF materials will be calculated as the actual square footage needed +10%
PROVIDENCE PARKS DEPARTMENT
1000 Elmwood Avenue, Providence, RI 02905
Phone: 401-680-7201
WENDY NILSSON
Superintendent of Parks
BRETT P. SMILEY
Mayor
24. Q: What does the allowance amount cover?
A: The allowance covers any additions made to the project, whether it be additional quantities of
base bid items, new items requested by the owner, or alterations based on unforeseen site
conditions
25. Q: Are hazardous materials testing and abatement included in the base bid? Will any required
abatement be handled by change order or separate contract?
A: They are not included, the allowance will cover any testing or abatement required.
26. Q: Please confirm that the 10% MBE / 10% WBE are goals, not strict minimums, and that a
signed waiver plus good-faith effort keeps the bid responsive?
A: Correct
27. Q: Please list any items to be salvaged and turned over to the Owner
A: Salvaged items may include exterior doors and any undamaged interior plywood, stockpile
salvaged items for Owner to review, any unwanted items shall be disposed of by Contractor.
28. Q: Provide direction/markup indicating which existing utilities must remain active during
construction?
A: The solar array must remain active during construction, with brief interruptions acceptable
during electrical work
29. Q: Are all railings shown are included in the base bid and related unit price(s), what is the
required finish system and color?
A: Yes, railings shown are base bid, see Detail 2, Sheet L-2 for finish
30. Q: Is fire alarm work limited to device additions/relocations in the project area, or are panel
upgrades/new circuits expected?
A: All work required is covered in the notes on sheet E-120
31. Q: What is the product for sealing the concrete and how many coats are required?
A: the basis-of-design product is Prosoco LS Guard, a minimum of 2 coats should be applied
32. Q: For new door and window openings in existing walls, please confirm if steel lintels/angles are
required. If so, provide sizes, bearing, and details, and confirm whether the Engineer of Record
will design them?
A: New Steel Lintels are not specified in the Architectural drawings. Existing steel lintels are in place
over the current garage door and a 2nd door opening that was closed off. (see photo)
PROVIDENCE PARKS DEPARTMENT
1000 Elmwood Avenue, Providence, RI 02905
Phone: 401-680-7201
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Bid Description RI Public Transit Authority Bid Number: 26-19 Description The Rhode Island

State Government of Rhode Island

Bid Due: 6/10/2026

Follow Z--BLRV: ETHERNET/SECURITY INSTALL Active Contract Opportunity Notice ID 140P4326Q0030 Related Notice Department/Ind.

INTERIOR, DEPARTMENT OF THE

Bid Due: 6/08/2026

Follow Construction - NUWCDIVNPT B68 Rm 136 Renovation Project Active Contract Opportunity Notice

DEPT OF DEFENSE

Bid Due: 6/12/2026

RFQ26006538 |RIARNG - Coventry P3 HVAC Replacement The Rhode Island Army National Guard

State Government of Rhode Island

Bid Due: 6/03/2026