Bid 24-051326 Stormwater Maintenance 26-27

Agency: City of High Point
State: North Carolina
Type of Government: State & Local
NAICS Category:
  • 541330 - Engineering Services
Posted Date: Jun 29, 2026
Due Date: Aug 30, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page

Description

Bid Title: Bid 24-051326 Stormwater Maintenance 26-27
Category: Bid Tabulations
Status: Open
Description:

Bid awarded to PDC Inc.Â

Publication Date/Time:
6/29/2026 12:00 AM
Closing Date/Time:
8/30/2026 11:59 PM
Related Documents:

Attachment Preview

ENGINEERS ESTIMATE PDC, INC. C&C ENVIRONMENTAL SERVICES LLC. BREECE ENTERPRISES, INC.
LINE # DOT DESCRIPTION QTY UOM UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 SP STANDARD UTILITY CREW AND EQUIPMENT 250 HR $850.00 $212,500.00 $800.00 $200,000.00 $600.00 $150,000.00 $800.00 $200,000.00
2 SP STANDARD UTILITY CREW AND EQUIPMENT (OVERTIME) 20 HR $1,000.00 $20,000.00 $900.00 $18,000.00 $775.00 $15,500.00 $800.00 $16,000.00
3 SP FLASHING ARROW PANEL, TYPE C 15 EA $300.00 $4,500.00 $125.00 $1,875.00 $1,134.00 $17,010.00 $200.00 $3,000.00
4 SP CONES/BARRELS/SKINNY DRUMS 200 EA $20.00 $4,000.00 $5.00 $1,000.00 $35.00 $7,000.00 $10.00 $2,000.00
5 SP BARRICADES TYPE III 15 EA $200.00 $3,000.00 $50.00 $750.00 $375.00 $5,625.00 $150.00 $2,250.00
6 SP WORK ZONE SIGNS (PORTABLE) 50 SF $20.00 $1,000.00 $5.00 $250.00 $50.00 $2,500.00 $15.00 $750.00
7 SP INCIDENTAL STONE BASE 80 TN $52.00 $4,160.00 $42.00 $3,360.00 $65.00 $5,200.00 $45.00 $3,600.00
8 SP CLEAN STONE NO 57 FOR TRENCH STABILIZATION 80 TN $55.00 $4,400.00 $53.00 $4,240.00 $65.00 $5,200.00 $55.00 $4,400.00
9 876 CLASS B RIP RAP 25 TN $60.00 $1,500.00 $76.00 $1,900.00 $65.00 $1,625.00 $65.00 $1,625.00
10 876 CLASS II RIP RAP 25 TN $60.00 $1,500.00 $76.00 $1,900.00 $65.00 $1,625.00 $70.00 $1,750.00
11 876 GEOTEXTILE FOR DRAINAGE 10 SY $45.00 $450.00 $35.00 $350.00 $10.00 $100.00 $30.00 $300.00
12 SP SELECT BACKFILL MATERIAL, CLASS I 80 CY $70.00 $5,600.00 $40.00 $3,200.00 $35.00 $2,800.00 $50.00 $4,000.00
13 SP TOPSOIL 20 CY $75.00 $1,500.00 $125.00 $2,500.00 $47.00 $940.00 $45.00 $900.00
14 SP PERMANENT SEEDING AND MULCHING 200 SY $10.00 $2,000.00 $2.00 $400.00 $2.25 $940.00 $5.00 $1,000.00
15 SP MATTING FOR EROSION CONTROL 100 SY $5.00 $500.00 $6.00 $600.00 $8.80 $880.00 $5.00 $500.00
16 SP TEMPORARY SAFETY FENCE 50 LF $5.00 $250.00 $4.00 $200.00 $2.45 $122.50 $3.00 $150.00
17 SP 15" RCP PIPE CULVERTS CLASS III 8 LF $34.00 $272.00 $45.00 $360.00 $75.15 $601.20 $30.00 $240.00
18 SP 18" RCP PIPE CULVERTS CLASS III 8 LF $38.00 $304.00 $50.00 $400.00 $75.00 $600.00 $35.00 $280.00
19 SP 24" RCP PIPE CULVERTS CLASS III 8 LF $65.00 $520.00 $75.00 $600.00 $100.00 $800.00 $60.00 $480.00
20 SP 30" RCP PIPE CULVERTS CLASS III 8 LF $90.00 $720.00 $90.00 $720.00 $100.00 $800.00 $85.00 $680.00
21 SP 36" RCP PIPE CULVERTS CLASS III 8 LF $125.00 $1,000.00 $125.00 $1,000.00 $150.00 $1,200.00 $120.00 $960.00
22 SP 42" RCP PIPE CULVERTS CLASS III 8 LF $175.00 $1,400.00 $155.00 $1,240.00 $175.00 $1,400.00 $155.00 $1,240.00
23 SP 48" RCP PIPE CULVERTS CLASS III 8 LF $210.00 $1,680.00 $190.00 $1,520.00 $200.00 $1,600.00 $200.00 $1,600.00
24 SP 54" RCP PIPE CULVERTS CLASS III 8 LF $340.00 $2,720.00 $285.00 $2,280.00 $325.00 $2,600.00 $285.00 $2,280.00
25 SP 60" RCP PIPE CULVERTS CLASS III 8 LF $425.00 $3,400.00 $330.00 $2,640.00 $400.00 $3,200.00 $340.00 $2,720.00
26 SP 15" RCP END SECTION 1 EA $1,150.00 $1,150.00 $1,150.00 $1,150.00 $1,350.00 $1,350.00 $1,050.00 $1,050.00
27 SP 18" RCP END SECTION 1 EA $1,300.00 $1,300.00 $1,250.00 $1,250.00 $1,500.00 $1,500.00 $1,200.00 $1,200.00
28 SP 24" RCP END SECTION 1 EA $1,650.00 $1,650.00 $1,400.00 $1,400.00 $1,625.00 $1,625.00 $1,400.00 $1,400.00
29 SP 30" RCP END SECTION 1 EA $2,000.00 $2,000.00 $1,950.00 $1,950.00 $2,250.00 $2,250.00 $1,850.00 $1,850.00
30 SP 36" RCP END SECTION 1 EA $3,000.00 $3,000.00 $2,700.00 $2,700.00 $3,125.00 $3,125.00 $2,800.00 $2,800.00
31 SP 42" RCP END SECTION 1 EA $3,600.00 $3,600.00 $3,350.00 $3,350.00 $3,950.00 $3,950.00 $3,600.00 $3,600.00
32 SP 48" RCP END SECTION 1 EA $4,000.00 $4,000.00 $4,200.00 $4,200.00 $4,700.00 $4,700.00 $4,500.00 $4,500.00
33 SP 54" RCP END SECTION 1 EA $6,000.00 $6,000.00 $100.00 $100.00 $6,025.00 $6,025.00 $1.00 $1.00
34 SP 60" RCP END SECTION 1 EA $6,750.00 $6,750.00 $100.00 $100.00 $7,725.00 $7,725.00 $1.00 $1.00
35 SP 15" POLYPROPYLENE PIPE CULVERTS 20 LF $35.00 $700.00 $30.00 $600.00 $50.00 $1,000.00 $25.00 $500.00
36 SP 18" POLYPROPYLENE PIPE CULVERTS 20 LF $42.00 $840.00 $39.00 $780.00 $50.00 $1,000.00 $35.00 $700.00
37 SP 24" POLYPROPYLENE PIPE CULVERTS 20 LF $54.00 $1,080.00 $62.00 $1,240.00 $75.00 $1,500.00 $55.00 $1,100.00
38 SP 30" POLYPROPYLENE PIPE CULVERTS 20 LF $85.00 $1,700.00 $99.00 $1,980.00 $100.00 $2,000.00 $90.00 $1,800.00
39 SP 36" POLYPROPYLENE PIPE CULVERTS 20 LF $95.00 $1,900.00 $108.00 $2,160.00 $100.00 $2,000.00 $95.00 $1,900.00
40 SP 42" POLYPROPYLENE PIPE CULVERTS 20 LF $120.00 $2,400.00 $131.00 $2,620.00 $125.00 $2,500.00 $120.00 $2,400.00
41 SP 48" POLYPROPYLENE PIPE CULVERTS 20 LF $145.00 $2,900.00 $180.00 $3,600.00 $175.00 $3,500.00 $160.00 $3,200.00
42 SP 54" POLYPROPYLENE PIPE CULVERTS 20 LF $250.00 $5,000.00 $60.00 $1,200.00 $200.00 $4,000.00 $1.00 $20.00
43 SP 60" POLYPROPYLENE PIPE CULVERTS 20 LF $290.00 $5,800.00 $297.00 $5,940.00 $275.00 $5,500.00 $250.00 $5,000.00
44 SP MISCELLANEOUS BRICK WORK 1 CY $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,400.00 $1,400.00 $1,000.00 $1,000.00
45 SP CONCRETE /FLOWABLE FILL 3 CY $450.00 $1,350.00 $300.00 $900.00 $175.00 $525.00 $350.00 $1,050.00
46 840 MASONRY DRAINAGE STRUCTURES 0-5' 4 EA $4,500.00 $18,000.00 $4,000.00 $16,000.00 $1,400.00 $5,600.00 $4,500.00 $18,000.00
47 840 MASONRY DRAINAGE STRUCTURES EXTRA DEPTH 10 LF $500.00 $5,000.00 $500.00 $5,000.00 $4,275.00 $42,750.00 $100.00 $1,000.00
48 SP MASONRY DRAINAGE STRUCTURE COHP STD DWG 411.01 1 EA $6,000.00 $6,000.00 $6,000.00 $6,000.00 $1,600.00 $1,600.00 $4,500.00 $4,500.00
49 SP MASONRY DRAINAGE STRUCTURE COHP STD DWG 411.01 EXTRA DEPTH 5 LF $450.00 $2,250.00 $400.00 $2,000.00 $75.00 $375.00 $100.00 $500.00
50 SP BRICK MASONRY CATCH BASIN CHP TYPE A 0-5' DEEP 5 EA $3,850.00 $19,250.00 $3,750.00 $18,750.00 $2,000.00 $10,000.00 $4,500.00 $22,500.00
51 SP BRICK MASONRY CATCH BASIN CHP TYPE A EXTRA DEPTH 5 LF $375.00 $1,875.00 $500.00 $2,500.00 $75.00 $375.00 $100.00 $500.00
52 840 FRAME AND GRATE STD 840.16 5 EA $650.00 $3,250.00 $675.00 $3,375.00 $840.16 $4,200.80 $650.00 $3,250.00
53 SP FLAGGERS 80 HR $60.00 $4,800.00 $45.00 $3,600.00 $20.00 $1,600.00 $35.00 $2,800.00
54 SP HAULING AND DISPOSAL OF WASTE 20 CY $60.00 $1,200.00 $35.00 $700.00 $50.00 $1,000.00 $60.00 $1,200.00
55 SP ASPHALT PLANT MIX PAVEMENT REPAIR 100 TN $700.00 $70,000.00 $180.00 $18,000.00 $95.00 $9,500.00 $675.00 $67,500.00
56 SP 2 FT - 6 INCH CONCRETE CURB AND GUTTER 75 LF $250.00 $18,750.00 $30.00 $2,250.00 $55.00 $4,125.00 $150.00 $11,250.00
57 SP 4 INCH CONCRETE FLATWORK 60 SY $225.00 $13,500.00 $50.00 $3,000.00 $550.00 $33,000.00 $150.00 $9,000.00
58 SP 6 INCH CONCRETE FLATWORK 35 SY $250.00 $8,750.00 $60.00 $2,100.00 $550.00 $19,250.00 $175.00 $6,125.00
59 SP CONCRETE CURB RAMP 3 EA $3,500.00 $10,500.00 $1,400.00 $4,200.00 $4,000.00 $12,000.00 $1,000.00 $3,000.00
$516,121.00 $376,980.00 $432,419.50 $438,902.00

BID TABULATIONS
cah ver 5/13/2026
ENGINEERS ESTIMATE PDC, INC. C&C ENVIRONMENTAL SERVICES LLC. BREECE ENTERPRISES, INC.
STORMWATER MAINTENANCE 2026 - 2027, BID 24-051326
LINE # DOT DESCRIPTION QTY UOM UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
STANDARD UTILITY CREW AND
1 SP 250 HR $850.00 $212,500.00 $800.00 $200,000.00 $600.00 $150,000.00 $800.00 $200,000.00
EQUIPMENT
STANDARD UTILITY CREW AND
2 SP 20 HR $1,000.00 $20,000.00 $900.00 $18,000.00 $775.00 $15,500.00 $800.00 $16,000.00
EQUIPMENT (OVERTIME)
3 SP FLASHING ARROW PANEL, TYPE C 15 EA $300.00 $4,500.00 $125.00 $1,875.00 $1,134.00 $17,010.00 $200.00 $3,000.00
4 SP CONES/BARRELS/SKINNY DRUMS 200 EA $20.00 $4,000.00 $5.00 $1,000.00 $35.00 $7,000.00 $10.00 $2,000.00
5 SP BARRICADES TYPE III 15 EA $200.00 $3,000.00 $50.00 $750.00 $375.00 $5,625.00 $150.00 $2,250.00
6 SP WORK ZONE SIGNS (PORTABLE) 50 SF $20.00 $1,000.00 $5.00 $250.00 $50.00 $2,500.00 $15.00 $750.00
7 SP INCIDENTAL STONE BASE 80 TN $52.00 $4,160.00 $42.00 $3,360.00 $65.00 $5,200.00 $45.00 $3,600.00
CLEAN STONE NO 57 FOR TRENCH
8 SP 80 TN $55.00 $4,400.00 $53.00 $4,240.00 $65.00 $5,200.00 $55.00 $4,400.00
STABILIZATION
9 876 CLASS B RIP RAP 25 TN $60.00 $1,500.00 $76.00 $1,900.00 $65.00 $1,625.00 $65.00 $1,625.00
10 876 CLASS II RIP RAP 25 TN $60.00 $1,500.00 $76.00 $1,900.00 $65.00 $1,625.00 $70.00 $1,750.00
11 876 GEOTEXTILE FOR DRAINAGE 10 SY $45.00 $450.00 $35.00 $350.00 $10.00 $100.00 $30.00 $300.00
12 SP SELECT BACKFILL MATERIAL, CLASS I 80 CY $70.00 $5,600.00 $40.00 $3,200.00 $35.00 $2,800.00 $50.00 $4,000.00
13 SP TOPSOIL 20 CY $75.00 $1,500.00 $125.00 $2,500.00 $47.00 $940.00 $45.00 $900.00
14 SP PERMANENT SEEDING AND MULCHING 200 SY $10.00 $2,000.00 $2.00 $400.00 $2.25 $940.00 $5.00 $1,000.00
15 SP MATTING FOR EROSION CONTROL 100 SY $5.00 $500.00 $6.00 $600.00 $8.80 $880.00 $5.00 $500.00
16 SP TEMPORARY SAFETY FENCE 50 LF $5.00 $250.00 $4.00 $200.00 $2.45 $122.50 $3.00 $150.00
17 SP 15" RCP PIPE CULVERTS CLASS III 8 LF $34.00 $272.00 $45.00 $360.00 $75.15 $601.20 $30.00 $240.00
18 SP 18" RCP PIPE CULVERTS CLASS III 8 LF $38.00 $304.00 $50.00 $400.00 $75.00 $600.00 $35.00 $280.00
19 SP 24" RCP PIPE CULVERTS CLASS III 8 LF $65.00 $520.00 $75.00 $600.00 $100.00 $800.00 $60.00 $480.00
20 SP 30" RCP PIPE CULVERTS CLASS III 8 LF $90.00 $720.00 $90.00 $720.00 $100.00 $800.00 $85.00 $680.00
21 SP 36" RCP PIPE CULVERTS CLASS III 8 LF $125.00 $1,000.00 $125.00 $1,000.00 $150.00 $1,200.00 $120.00 $960.00
22 SP 42" RCP PIPE CULVERTS CLASS III 8 LF $175.00 $1,400.00 $155.00 $1,240.00 $175.00 $1,400.00 $155.00 $1,240.00
23 SP 48" RCP PIPE CULVERTS CLASS III 8 LF $210.00 $1,680.00 $190.00 $1,520.00 $200.00 $1,600.00 $200.00 $1,600.00
24 SP 54" RCP PIPE CULVERTS CLASS III 8 LF $340.00 $2,720.00 $285.00 $2,280.00 $325.00 $2,600.00 $285.00 $2,280.00
25 SP 60" RCP PIPE CULVERTS CLASS III 8 LF $425.00 $3,400.00 $330.00 $2,640.00 $400.00 $3,200.00 $340.00 $2,720.00
26 SP 15" RCP END SECTION 1 EA $1,150.00 $1,150.00 $1,150.00 $1,150.00 $1,350.00 $1,350.00 $1,050.00 $1,050.00
27 SP 18" RCP END SECTION 1 EA $1,300.00 $1,300.00 $1,250.00 $1,250.00 $1,500.00 $1,500.00 $1,200.00 $1,200.00
28 SP 24" RCP END SECTION 1 EA $1,650.00 $1,650.00 $1,400.00 $1,400.00 $1,625.00 $1,625.00 $1,400.00 $1,400.00
29 SP 30" RCP END SECTION 1 EA $2,000.00 $2,000.00 $1,950.00 $1,950.00 $2,250.00 $2,250.00 $1,850.00 $1,850.00
30 SP 36" RCP END SECTION 1 EA $3,000.00 $3,000.00 $2,700.00 $2,700.00 $3,125.00 $3,125.00 $2,800.00 $2,800.00
31 SP 42" RCP END SECTION 1 EA $3,600.00 $3,600.00 $3,350.00 $3,350.00 $3,950.00 $3,950.00 $3,600.00 $3,600.00
32 SP 48" RCP END SECTION 1 EA $4,000.00 $4,000.00 $4,200.00 $4,200.00 $4,700.00 $4,700.00 $4,500.00 $4,500.00
33 SP 54" RCP END SECTION 1 EA $6,000.00 $6,000.00 $100.00 $100.00 $6,025.00 $6,025.00 $1.00 $1.00
34 SP 60" RCP END SECTION 1 EA $6,750.00 $6,750.00 $100.00 $100.00 $7,725.00 $7,725.00 $1.00 $1.00
35 SP 15" POLYPROPYLENE PIPE CULVERTS 20 LF $35.00 $700.00 $30.00 $600.00 $50.00 $1,000.00 $25.00 $500.00
36 SP 18" POLYPROPYLENE PIPE CULVERTS 20 LF $42.00 $840.00 $39.00 $780.00 $50.00 $1,000.00 $35.00 $700.00
37 SP 24" POLYPROPYLENE PIPE CULVERTS 20 LF $54.00 $1,080.00 $62.00 $1,240.00 $75.00 $1,500.00 $55.00 $1,100.00
38 SP 30" POLYPROPYLENE PIPE CULVERTS 20 LF $85.00 $1,700.00 $99.00 $1,980.00 $100.00 $2,000.00 $90.00 $1,800.00
39 SP 36" POLYPROPYLENE PIPE CULVERTS 20 LF $95.00 $1,900.00 $108.00 $2,160.00 $100.00 $2,000.00 $95.00 $1,900.00
40 SP 42" POLYPROPYLENE PIPE CULVERTS 20 LF $120.00 $2,400.00 $131.00 $2,620.00 $125.00 $2,500.00 $120.00 $2,400.00
41 SP 48" POLYPROPYLENE PIPE CULVERTS 20 LF $145.00 $2,900.00 $180.00 $3,600.00 $175.00 $3,500.00 $160.00 $3,200.00
42 SP 54" POLYPROPYLENE PIPE CULVERTS 20 LF $250.00 $5,000.00 $60.00 $1,200.00 $200.00 $4,000.00 $1.00 $20.00
43 SP 60" POLYPROPYLENE PIPE CULVERTS 20 LF $290.00 $5,800.00 $297.00 $5,940.00 $275.00 $5,500.00 $250.00 $5,000.00
44 SP MISCELLANEOUS BRICK WORK 1 CY $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,400.00 $1,400.00 $1,000.00 $1,000.00
45 SP CONCRETE /FLOWABLE FILL 3 CY $450.00 $1,350.00 $300.00 $900.00 $175.00 $525.00 $350.00 $1,050.00
46 840 MASONRY DRAINAGE STRUCTURES 0-5' 4 EA $4,500.00 $18,000.00 $4,000.00 $16,000.00 $1,400.00 $5,600.00 $4,500.00 $18,000.00
MASONRY DRAINAGE STRUCTURES
47 840 10 LF $500.00 $5,000.00 $500.00 $5,000.00 $4,275.00 $42,750.00 $100.00 $1,000.00
EXTRA DEPTH
MASONRY DRAINAGE STRUCTURE COHP
48 SP 1 EA $6,000.00 $6,000.00 $6,000.00 $6,000.00 $1,600.00 $1,600.00 $4,500.00 $4,500.00
STD DWG 411.01
MASONRY DRAINAGE STRUCTURE COHP
49 SP 5 LF $450.00 $2,250.00 $400.00 $2,000.00 $75.00 $375.00 $100.00 $500.00
STD DWG 411.01 EXTRA DEPTH
BRICK MASONRY CATCH BASIN CHP
50 SP 5 EA $3,850.00 $19,250.00 $3,750.00 $18,750.00 $2,000.00 $10,000.00 $4,500.00 $22,500.00
TYPE A 0-5' DEEP
BRICK MASONRY CATCH BASIN CHP
51 SP 5 LF $375.00 $1,875.00 $500.00 $2,500.00 $75.00 $375.00 $100.00 $500.00
TYPE A EXTRA DEPTH
52 840 FRAME AND GRATE STD 840.16 5 EA $650.00 $3,250.00 $675.00 $3,375.00 $840.16 $4,200.80 $650.00 $3,250.00
53 SP FLAGGERS 80 HR $60.00 $4,800.00 $45.00 $3,600.00 $20.00 $1,600.00 $35.00 $2,800.00
54 SP HAULING AND DISPOSAL OF WASTE 20 CY $60.00 $1,200.00 $35.00 $700.00 $50.00 $1,000.00 $60.00 $1,200.00
55 SP ASPHALT PLANT MIX PAVEMENT REPAIR 100 TN $700.00 $70,000.00 $180.00 $18,000.00 $95.00 $9,500.00 $675.00 $67,500.00
2 FT - 6 INCH CONCRETE CURB AND
56 SP 75 LF $250.00 $18,750.00 $30.00 $2,250.00 $55.00 $4,125.00 $150.00 $11,250.00
GUTTER
57 SP 4 INCH CONCRETE FLATWORK 60 SY $225.00 $13,500.00 $50.00 $3,000.00 $550.00 $33,000.00 $150.00 $9,000.00
58 SP 6 INCH CONCRETE FLATWORK 35 SY $250.00 $8,750.00 $60.00 $2,100.00 $550.00 $19,250.00 $175.00 $6,125.00
59 SP CONCRETE CURB RAMP 3 EA $3,500.00 $10,500.00 $1,400.00 $4,200.00 $4,000.00 $12,000.00 $1,000.00 $3,000.00
TOTALS $516,121.00 $376,980.00 $432,419.50 $438,902.00
NOTES:
1. C&C Environmental Services LLC unit pricing
math errors on LI#14 and LI#16. Italicized and
in bold.
Page 1 of 1

This page summarizes the opportunity, including an overview and a preview of the attached documents.
Get Government Bids Like This by Email Receive daily bid alerts that match your keywords, business categories, and target regions.

See Also

Solicitation Number: 332-2022-CDBG-NR-Jackson-Heights - 21-C-4032 Project Title: Sanford NC - Jackson Heights CDBG-NR

State Government of North Carolina

Due by 10/08/2026

ATTENTION ALL BIDDERS POC DIVISION 12 BID OPENING CONFERENCE LINE 092226_ATTENTIONTOBIDDERS.pdf Doc. Type:

Division of Highways

Due by 9/22/2026

Bid Title: Bid 4003-100726 Eastside Final Clarifier 4 Category: Bid Opportunities Status: Open

City of High Point

Due by 10/07/2026

Bid Number: 27-002 Bid Title: Pender County US 421 CFPUA Interconnect Category: General

County of Pender

Due by 10/22/2026

* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.