209-4251527-012
March 2026
Riverview Land Preserve
20863 Grange Road
Riverview, Michigan 48193
2026 Spring GCCS Construction
Riverview Land Preserve
Bid No. 2560
Project No. 209-4251527-012
00010 - TABLE OF CONTENTS
FOR
RIVERVIEW LAND PRESERVE
BID 2560 - 2026 SPRING GCCS CONSTRUCTION
SECTION 00010 - TABLE OF CONTENTS
SECTION 00100 - INVITATION TO BID
SECTION 00200 - INSTRUCTIONS TO BIDDERS
SECTION 00410 - BID FORM
SECTION 00430 - BID BOND
SECTION 00451 - QUALIFICATION STATEMENT
SECTION 00510 - NOTICE OF AWARD
SECTION 00520 - AGREEMENT
SECTION 00610 - PERFORMANCE BOND
SECTION 00615 - PAYMENT BOND
SECTION 00620 - CONTRACTORS APPLICATION FOR PAYMENT
SECTION 00700 - GENERAL CONDITIONS
SECTION 00800 - SUPPLEMENTARY CONDITIONS
SECTION 00800.A - RIVERVIEW GENERAL CONDITIONS
SECTION 00800.B - RIVERVIEW ETHICS POLICY
SECTION 00800.C - CITY OF RIVERVIEW INSURANCE REQUIREMENTS
SECTION 00800.D - BIDDER CERTIFICATION OF COMPLIANCE
SECTION 00800.E - UPDATED FORM 1099 VENDORS QUESTIONAIRE
SECTION 00800.F - CONTRACTORS LIEN WAIVER AND RELEASE
DIVISION 1 - GENERAL REQUIREMENT SPECIFICATIONS
SECTION 01010 - SUMMARY OF WORK
SECTION 01025 - MEASUREMENTS AND PAYMENT
SECTION 01300 - ADMINISTRATIVE REQUIREMENTS
SECTION 01330 - SUBMITAL PROCEDURE
SECTION 01600 - PRODUCT REQUIREMENT
SECTION 01700 - EXECUTION AND CLOSEOUT REQUIREMENTS
ALTERNATE BID - MULTI YEAR CONTRACT ANNUAL CONSTRUCTION
APPENDIX A - PROJECT DRAWINGS - 2026 SPRING GCCS CONSTRUCTION
TABLE OF CONTENTS
00010 - 1
Project No. 209-4241478-012
RIVERVIEW LAND PRESERVE
BID 2560- 2026 SPRING GCCS CONSTRUCTION
SECTION 00100 - INVITATION TO BID
INVITATION TO BID
CITY OF RIVERVIEW
Sealed proposals will be received by the City Clerk, 14100 Civic Park Drive, Riverview,
Michigan until 2:00 PM, Eastern Daylight Savings Time, Thursday, April 2, 2026, at
which time and place the bids will be publicly opened and read aloud for:
BID #2560 - 2026 SPRING GCCS CONSTRUCTION
Specifications are available online with the Bid Net (formerly Michigan Inter-
governmental Trade Network ) at www.bidnetdirect.com and on the City Web site at
http://www.cityofriverview.com/departments/purchasing/invitations_to_bid.php. All bids
must be plainly marked on the envelope, " BID #2560- 2026 SPRING GCCS
CONSTRUCTION".
There will not be a pre-bid meeting, due to current restrictions. A site inspection may
be arranged by appointment and in accordance with safety measures in place at the
time.
The City of Riverview reserves the right to reject any or all bids and waive defects in
bidding in the best interest of the City.
______________________________
Jeffrey Dobek
City Manager
Publish: March 19, 2026
INVITATION TO BID
00100 - 1
Project No. 209-4251527-012
RIVERVIEW LAND PRESERVE
BID 2560 - 2026 SPRING GCCS CONSTRUCTION
SECTION 00200 - INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page
ARTICLE 1 - Defined Terms ...................................................................................................... 1
ARTICLE 2 - Copies of Bidding Documents .............................................................................. 1
ARTICLE 3 - Qualifications of Bidders ....................................................................................... 1
ARTICLE 4 - Site and Other Areas; Existing Site Conditions; Examination of Site; Owner's
Safety Program; Other Work at the Site ..................................................................................... 1
ARTICLE 5 - Bidder's Representations ..................................................................................... 3
ARTICLE 6 - Pre-Bid Conference .............................................................................................. 4
ARTICLE 7 - Interpretations and Addenda ................................................................................ 4
ARTICLE 8 - Bid Security .......................................................................................................... 4
ARTICLE 9 - Contract Times ..................................................................................................... 5
ARTICLE 10 - Liquidated Damages .......................................................................................... 5
ARTICLE 11 - Substitute and "Or-Equal" Items ......................................................................... 5
ARTICLE 12 - Subcontractors, Suppliers, and Others ............................................................... 5
ARTICLE 13 - Preparation of Bid............................................................................................... 6
ARTICLE 14 - Basis of Bid ........................................................................................................ 7
ARTICLE 15 - Submittal of Bid .................................................................................................. 7
ARTICLE 16 - Modification and Withdrawal of Bid ..................................................................... 8
ARTICLE 17 - Opening of Bids .................................................................................................. 8
ARTICLE 18 - Bids to Remain Subject to Acceptance ............................................................... 8
ARTICLE 19 - Evaluation of Bids and Award of Contract .......................................................... 8
ARTICLE 20 - Bonds and Insurance ......................................................................................... 9
ARTICLE 21 - Signing of Agreement ......................................................................................... 9
ARTICLE 22 - Sales and Use Taxes ......................................................................................... 9
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page i
Project No. 209-4251527-012
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General
Conditions and Supplementary Conditions. Additional terms used in these Instructions to
Bidders have the meanings indicated below:
A. Issuing Office - The office from which the Bidding Documents are to be issued.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the
number and format stated in the advertisement or invitation to bid.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use
of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above
terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or
confer a license for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder's qualifications to perform the Work, after submitting its Bid and
within 10 days of Owner's request, Bidder shall submit (a) written evidence establishing
its qualifications such as financial data, previous experience, and present commitments,
and (b) the following additional information:
A. Evidence of Bidder's authority to do business in the state where the Project is located.
B. Bidder's state or other contractor license number, if applicable.
C. Subcontractor and Supplier qualification information; coordinate with provisions of
Article 12 of these Instructions, "Subcontractors, Suppliers, and Others."
D. Other required information regarding qualifications
3.02 A Bidder's failure to submit required qualification information within the times indicated
may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to
seek additional pertinent information regarding Bidder's qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder's
representations and certifications.
ARTICLE 4 - SITE AND OTHER AREAS; EXISTING SITE CONDITIONS;
EXAMINATION OF SITE; OWNER'S SAFETY PROGRAM; OTHER WORK AT THE
SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-
of-way, easements, and other lands furnished by Owner for the use of the Contractor.
Any additional lands required for temporary construction facilities, construction
equipment, or storage of materials and equipment, and any access needed for such
additional lands, are to be obtained and paid for by Contractor.
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 1
Project No. 209-4251527-012
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify:
a. those reports known to Owner of explorations and tests of subsurface
conditions at or adjacent to the Site.
b. those drawings known to Owner of physical conditions relating to existing
surface or subsurface structures at the Site (except Underground Facilities).
c. reports and drawings known to Owner relating to Hazardous Environmental
Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to
any Bidder on request. These reports and drawings are not part of the Contract
Documents, but the Technical Data contained therein upon whose accuracy
Bidder is entitled to rely, as provided in the General Conditions, has been
identified and established in the Supplementary Conditions. Bidder is responsible
for any interpretation or conclusion Bidder draws from any Technical Data or any
other data, interpretations, opinions, or information contained in such reports or
shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default
definition of Technical Data set forth in Article 1 of the General Conditions will
apply.
4. Geotechnical Baseline Report: Not used.
B. Underground Facilities: Information and data shown or indicated in the Bidding
Documents with respect to existing Underground Facilities at or contiguous to the Site
are set forth in the Contract Documents and are based upon information and data
furnished to Owner and Engineer by owners of such Underground Facilities, including
Owner, or others.
C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data
furnished to prospective Bidders with respect to subsurface conditions, other physical
conditions, and Underground Facilities, and possible changes in the Bidding
Documents due to differing or unanticipated subsurface or physical conditions appear
in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning
responsibilities for the adequacy of data furnished to prospective Bidders with respect
to a Hazardous Environmental Condition at the Site, if any, and possible changes in
the Contract Documents due to any Hazardous Environmental Condition uncovered
or revealed at the Site which was not shown or indicated in the Drawings or
Specifications or identified in the Contract Documents to be within the scope of the
Work, appear in Paragraph 5.06 of the General Conditions.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours, and shall not
disturb any ongoing operations at the Site. Bidder may contact the Land Preserve
Director to arrange for a tour of the work if desired.
B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations
of Site conditions.
C. On request, and to the extent Owner has control over the Site, and schedule
permitting, the Owner will provide Bidder access to the Site to conduct such additional
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 2
Project No. 209-4251527-012
examinations, investigations, explorations, tests, and studies as Bidder deems
necessary for preparing and submitting a successful Bid. Owner will not have any
obligation to grant such access if doing so is not practical because of existing
operations, security or safety concerns, or restraints on Owner's authority regarding
the Site.
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation
and location of utilities, obtain all permits, and comply with all terms and conditions
established by Owner or by property owners or other entities controlling the Site with
respect to schedule, access, existing operations, security, liability insurance, and
applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon
completion of such explorations, investigations, tests, and studies.
4.04 Owner's Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. As the
General Conditions indicate, if an Owner safety program exists, it will be noted in the
Supplementary Conditions.
4.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification
of the general nature of other work of which Owner is aware (if any) that is to be
performed at the Site by Owner or others (such as utilities and other prime
contractors) and relates to the Work contemplated by these Bidding Documents. If
Owner is party to a written contract for such other work, then on request, Owner will
provide to each Bidder access to examine such contracts (other than portions thereof
related to price and other confidential matters), if any.
ARTICLE 5 - BIDDER'S REPRESENTATIONS
5.01 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and any data and reference
items identified in the Bidding Documents;
B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent
areas, and become familiar with and satisfy itself as to the general, local, and Site
conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy itself as to all Laws and Regulations that may affect
cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or
adjacent to the Site and all drawings of physical conditions relating to existing surface
or subsurface structures at the Site that have been identified in the Supplementary
Conditions, especially with respect to Technical Data in such reports and drawings,
and (2) reports and drawings relating to Hazardous Environmental Conditions, if any,
at or adjacent to the Site that have been identified in the Supplementary Conditions,
especially with respect to Technical Data in such reports and drawings;
E. consider the information known to Bidder itself; information commonly known to
contractors doing business in the locality of the Site; information and observations
obtained from visits to the Site; the Bidding Documents; and the Site-related reports
and drawings identified in the Bidding Documents, with respect to the effect of such
information, observations, and documents on (1) the cost, progress, and performance
of the Work; (2) the means, methods, techniques, sequences, and procedures of
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 3
Project No. 209-4251527-012
construction to be employed by Bidder; and (3) Bidder's safety precautions and
programs;
F. agree, based on the information and observations referred to in the preceding
paragraph, that at the time of submitting its Bid no further examinations,
investigations, explorations, tests, studies, or data are necessary for the
determination of its Bid for performance of the Work at the price bid and within the
times required, and in accordance with the other terms and conditions of the Bidding
Documents;
G. become aware of the general nature of the work to be performed by Owner and others
at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or
discrepancies that Bidder discovers in the Bidding Documents and confirm that the
written resolution thereof by Engineer is acceptable to Bidder;
I. determine that the Bidding Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for the performance and furnishing of the
Work; and
J. agree that the submission of a Bid will constitute an incontrovertible representation
by Bidder that Bidder has complied with every requirement of this Article, that without
exception the Bid and all prices in the Bid are premised upon performing and
furnishing the Work required by the Bidding Documents.
ARTICLE 6 - PRE-BID CONFERENCE
6.01 A pre-bid conference will not be held as stated in the invitation or advertisement to bid.
Site inspections may be arranged by appointment.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted
to Engineer in writing. Interpretations or clarifications considered necessary by Engineer
in response to such questions will be issued by Addenda delivered to all parties recorded
as having received the Bidding Documents. Questions received less than seven days prior
to the date for opening of Bids may not be answered. Only questions answered by
Addenda will be binding. Oral and other interpretations or clarifications will be without legal
effect.
7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5
percent of Bidder's maximum Bid price (determined by adding the base bid and all
alternates) and in the form of a certified check, bank money order, or a Bid bond (on the
form included in the Bidding Documents) issued by a surety meeting the requirements of
Paragraphs 6.01 and 6.02 of the General Conditions.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards
the contract to such Bidder, and such Bidder has executed the Contract Documents,
furnished the required contract security, and met the other conditions of the Notice of
Award, whereupon the Bid security will be released. If the Successful Bidder fails to
execute and deliver the Contract Documents and furnish the required contract security
within 15 days after the Notice of Award, Owner may consider Bidder to be in default,
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 4
Project No. 209-4251527-012
annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such
forfeiture shall be Owner's exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of
receiving the award may be retained by Owner until the earlier of seven days after the
Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security
furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of
receiving the award will be released within seven days after the Bid opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which the Work is to be substantially
completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone,
Substantial Completion, or completion of the Work in readiness for final payment, are set
forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND "OR-EQUAL" ITEMS
11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment
specified or described in the Bidding Documents, and those "or-equal" or substitute or
materials and equipment subsequently approved by Engineer prior to the submittal of Bids
and identified by Addendum. No item of material or equipment will be considered by
Engineer as an "or-equal" or substitute unless written request for approval has been
submitted by Bidder and has been received by Engineer at least 15 days prior to the date
for receipt of Bids. Each such request shall comply with the requirements of Paragraphs
7.04 and 7.05 of the General Conditions. The burden of proof of the merit of the proposed
item is upon Bidder. Engineer's decision of approval or disapproval of a proposed item will
be final. If Engineer approves any such proposed item, such approval will be set forth in
an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals
made in any other manner.
11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the
Contractor will furnish the materials and equipment specified or described in the Bidding
Documents, as supplemented by Addenda. Any assumptions regarding the possibility of
post-Bid approvals of "or-equal" or substitution requests are made at Bidder's sole risk.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals
or entities for the performance of the Work if required by the Bidding Documents (most
commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any
such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved
by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or
Contractor to retain any Subcontractor, Supplier, or other individual or entity against which
Contractor has reasonable objection.
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 5
Project No. 209-4251527-012
12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days
after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for
the following portions of the Work:
A. Surveyor
B. Piping
C. Electrical and electronic systems
D. Geosynthetic materials and installation
E. Stone and granular materials
F. Seeding
12.04 If requested by Owner, such list shall be accompanied by an experience statement with
pertinent information regarding similar projects and other evidence of qualification for each
such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due
investigation, has reasonable objection to any proposed Subcontractor, Supplier,
individual, or entity, Owner may, before the Notice of Award is given, request apparent
Successful Bidder to submit an acceptable substitute, in which case apparent Successful
Bidder shall submit a substitute, Bidder's Bid price will be increased (or decreased) by the
difference in cost occasioned by such substitution, and Owner may consider such price
adjustment in evaluating Bids and making the Contract award.
12.05 If apparent Successful Bidder declines to make any such substitution, Owner may award
the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors,
Suppliers, or other individuals or entities. Declining to make requested substitutions will
constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor,
Supplier, individual, or entity so listed and against which Owner or Engineer makes no
written objection prior to the giving of the Notice of Award will be deemed acceptable to
Owner and Engineer subject to subsequent revocation of such acceptance as provided in
Paragraph 7.06 of the General Conditions.
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.
Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A
Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price
item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item
is optional, and Bidder elects to not furnish pricing for such optional alternate item,
then Bidder may enter the words "No Bid" or "Not Applicable."
13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer
(whose title must appear under the signature), accompanied by evidence of authority to
sign. The corporate address and state of incorporation shall be shown.
13.03 A Bid by a limited liability company shall be executed in the name of the firm by a member
or other authorized person and accompanied by evidence of authority to sign. The state
of formation of the firm and the official address of the firm shall be shown.
13.04 A Bid by an individual shall show the Bidder's name and official address.
EJCDC(R) C-200, Suggested Instructions to Bidders for Construction Contracts.
Copyright (C) 2013 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved. Page 6
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Follow Construct Readiness Center Active Contract Opportunity Notice ID W912JB-24-B-0001 Related Notice W912JB-23-B-0001
Federal Agency
Bid Due: 1/26/2027
Follow Construct Readiness Center Active Contract Opportunity Notice ID W912JB-24-B-0001 Related Notice W912JB-23-B-0001
Federal Agency
Bid Due: 1/26/2027
Description: BUREAU OF CONSTRUCTION CODES - 9 STICKERS Department: Technology, Management and Budget
State of Michigan
Bid Due: 8/04/2026
BID # BID DOCUMENTS OPEN BID DATE & TIME BID DESCRIPTION Buyer 8903
Washtenaw County
Bid Due: 8/24/2026