Description
Berths 49-51 Outer Harbor Cruise Terminal Development
| Status |
|
Stage
Open
|
|
Posted
9/9/2025
|
|
Bid Due
10/23/2025, 02:45 PM PDT
|
|
Partner
No |
| Contact |
|
Organization
City of Los Angeles
|
|
Department
Harbor Department, Port of Los Angeles
|
|
Name
Jill De Montagnac
|
|
Email
Email
jdemontagnac@portla.org
|
|
Phone
|
|
Technical Assistance Deadline
|
- Summary
- More Tabs
Opportunity ID
Organization
225023
City of Los Angeles
Category
Bid Method
Type
Construction
Whole Item
RFB - Request For Bid
Description
Project consists of the construction of a new Los Angeles Department of Water and Power (LADWP) 34.5 kV Industrial Station, new 34.5 kV switchgear, new 18
MVA transformer equipped with Automatic Load Tap Change (ALTC) to
automatically adjust the necessary transformer tap changes under load, new 11 kV AMP switchgear, 2 new 11 kV wharf AMP outlets, and a 11 kV AMP mobile
cable management for cruise ships connections. In addition, this Project requires the extension of a new LADWP 34.5 kV circuit through the existing LADWP underground conduit (from 22nd Street to Berth 49 along Miner Street). Project also includes Berths 49 - 50 wharf structural AMP, landside structural AMP support, Berths 49 - 50 concrete wharf repairs, furnish and install hybrid fender backing panel including steel pipe piles and timber piles, new foam-filled fendering system, new utilities including water lines and sewer connections, customer requested civil improvements to improve pedestrian and vehicular access, safety, and security for the cruise customers and operations, and site removals. E/E: $53,800,000 - $59,500,000
MVA transformer equipped with Automatic Load Tap Change (ALTC) to
automatically adjust the necessary transformer tap changes under load, new 11 kV AMP switchgear, 2 new 11 kV wharf AMP outlets, and a 11 kV AMP mobile
cable management for cruise ships connections. In addition, this Project requires the extension of a new LADWP 34.5 kV circuit through the existing LADWP underground conduit (from 22nd Street to Berth 49 along Miner Street). Project also includes Berths 49 - 50 wharf structural AMP, landside structural AMP support, Berths 49 - 50 concrete wharf repairs, furnish and install hybrid fender backing panel including steel pipe piles and timber piles, new foam-filled fendering system, new utilities including water lines and sewer connections, customer requested civil improvements to improve pedestrian and vehicular access, safety, and security for the cruise customers and operations, and site removals. E/E: $53,800,000 - $59,500,000
Proposal Submission Method
Links
Compliance Document List
Please login to find compliance document list
| Prime NAICS | Industry |
| 561730: Landscaping Services | Administrative and Support and Waste Management and Remediation Services |
| 237110: Water and Sewer Line and Related Structures Construction | Construction |
| 237130: Power and Communication Line and Related Structures Construction | Construction |
| 237990: Other Heavy and Civil Engineering Construction | Construction |
| 238110: Poured Concrete Foundation and Structure Contractors | Construction |
| 238120: Structural Steel and Precast Concrete Contractors | Construction |
| 238210: Electrical Contractors | Construction |
| 238910: Site Preparation Contractors | Construction |
| 238990: All Other Specialty Trade Contractors | Construction |
| Sub NAICS | Industry |
Meetings
| Date | Location | Description |
|
9/23/2025, 09:00 AM PDT
|
Microsoft Teams:
Microsoft Teams |
Pre-Bid Virtual Meeting
Matters relating to the submittal of bids and other contents of Specifications shall be discussed. A job site walk inside the facilities shall be available for Bidders after the scheduled pre-bid conference.
|
Documents
| Name | Uploaded | Size |
| 2815 NIB cover letter | 9/9/2025, 03:31 PM PDT | 658.2 kB |
Get Government Bids Like This by Email
Receive daily bid alerts that match your keywords, business categories, and target regions.
See Also
Bid Details WD-2919 8-and12--Inch Ductile Iron Water Main Replacement and Rehab, Sewer Replacement
San Francisco Public Utilities Commission
Due by 9/24/2026
Bid Title: Request for Proposal (RFP) for Playground Surface Replacement at Pinehurst Park
City of Chino Hills
Due by 10/01/2026
Follow Construct Pad & Sit-Up Bars at North Gate Track Active Contract Opportunity
DEPT OF DEFENSE
Due by 9/24/2026
Project ID: 4724 Title: B.T. Collins Youth Detention Facility - Replace Obsolete HVAC
Sacramento County
Due by 10/22/2026
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.