BC-21512-M Dining Hall 13kV Switch Replacement IFB
Tuesday 05/19/2026 at 11am (EST) Via Webex
June 16, 2026 by 2:00pm
INVITATION FOR BID
FOR
DINING HALL 13KV SWITCH REPLACEMENT
IFB NUMBER: BC-21512-M
ISSUED: 04/27/2026
Prospective bidders/Bidders are encouraged to regularly visit the University's Department of Procurement &
Strategic Sourcing website, e-Maryland Marketplace Advantage (eMMA) to ensure receipt of any addenda and
other updates related to this solicitation. The links to these resources are provided below:
* UMBC Bid Board - https://procurement.umbc.edu/bid-board/
* eMaryland Marketplace Advantage (eMMA) - https://emma.maryland.gov
ISSUING OFFICE
Department of Procurement & Strategic Sourcing
University of Maryland, Baltimore County
Administration Building, 7th Floor
1000 Hilltop Circle
Baltimore, MD 21250
MINORITY, WOMEN AND SMALL BUSINESSES ARE ENCOURGAGED TO RESPOND TO THIS
SOLICITATION
| Invitation for Bids | |
|---|---|
| Solicitation Number: | BC-21512-M |
| IFB Issue Date: | April 27, 2026 |
| Procurement Officer: | Nneka Miller |
| Bids are to be sent to: | Bids.qc73ydwxnweprwnb@u.box.com |
| Pre-Bid Conference: | May 19, 2026; at 11:00 AM at this link: sip:28677995409@umbc.webex.com Join Webex meeting ID: 28677995409 Password: HJtNWjcJ857 |
| Site Visit: | May 27, 2026; at 11:00 AM Review Section 3.1.4 for Site Visit details |
| Questions Due Date & Time: | June 2, 2026; on or before 2:00 PM Submit Questions to: nmiller7@umbc.edu |
| Bid Due Date & Time: | June 16, 2026; on or before 2:00 PM Local Time Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made (see Attachment 1 - No Bid Notice/Vendor Feedback Form). |
| Public Bid Opening Date, Time and Location: | June 16, 2026; at 2:45 PM Local Time at this link: sip:26309155496@umbc.webex.com Join Webex meeting ID: 26309155496 Password: f9P2w2xsTHQ |
| Minority Business Enterprise (MBE) Subcontracting Goal: | Twenty (20%) |
| Procurement Method: | A Contract will be awarded in accordance with the Competitive Sealed Bidding method under COMAR 21.05.02. |
| Contract Type: | Indefinite Quantity with Firm Fixed Prices |
| Term of Contract: | Six (6) months |
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
Key Information Sheet & Solicitation Schedule
Invitation for Bids
Solicitation Number: BC-21512-M
IFB Issue Date: April 27, 2026
Procurement Officer: Nneka Miller
Bids are to be sent to: Bids.qc73ydwxnweprwnb@u.box.com
Pre-Bid Conference: May 19, 2026; at 11:00 AM at this link:
sip:28677995409@umbc.webex.com
Join Webex meeting
ID: 28677995409
Password: HJtNWjcJ857
Site Visit: May 27, 2026; at 11:00 AM
Review Section 3.1.4 for Site Visit details
Questions Due Date & Time: June 2, 2026; on or before 2:00 PM
Submit Questions to: nmiller7@umbc.edu
Bid Due Date & Time: June 16, 2026; on or before 2:00 PM Local Time
Bidders are reminded that a completed Feedback Form is
requested if a no-bid decision is made (see Attachment 1 -
No Bid Notice/Vendor Feedback Form).
Public Bid Opening Date, Time and June 16, 2026; at 2:45 PM Local Time at this link:
Location: sip:26309155496@umbc.webex.com
Join Webex meeting
ID: 26309155496
Password: f9P2w2xsTHQ
Minority Business Enterprise (MBE) Twenty (20%)
Subcontracting Goal:
Procurement Method: A Contract will be awarded in accordance with the
Competitive Sealed Bidding method under COMAR
21.05.02.
Contract Type: Indefinite Quantity with Firm Fixed Prices
Term of Contract: Six (6) months
The University is committed to ensuring that persons with disabilities have equally effective opportunities to
participate in and benefit from the University's programs and services. Persons who may require reasonable
ADA accommodations should email the Issuing Office at nmiller7@umbc.edu at least five (5) days prior to
any meeting scheduled in connection with this solicitation.
Pa ge 2 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
NOTICE TO BIDDER/OFFEROR
To help improve the quality of bid/Proposal solicitations and to make our procurement process more responsive and
"business friendly," we ask that you provide comments and suggestions regarding the enclosed solicitation. Please
return your comments with your bid, proposal or "no bid," response, as the case may be. Thank you for your assistance.
Solicitation No.: BC-21512-M Title: Dining Hall 13kV Switch Replacement
If you have responded with a "no bid" please indicate the reasons below (check applicable boxes):
Other commitments preclude our participation at this time.
The subject of the solicitation is not something we normally provide.
We are inexperienced in the work/commodities required.
The specifications are either unclear or too restrictive (explain below).
The scope of work is beyond our current capacity.
Doing business with Maryland Government Agencies is simply too complicated (explain below).
We cannot be competitive (explain below).
Time allotted for completion of the bid/proposal response is insufficient.
Start-up time is insufficient.
Bonding/insurance requirements are prohibitive (explain below).
MBE requirements (explain below).
Bid/Proposal requirements (other than specifications or scope) are unreasonable or too risky (explain below)
Prior experience with University contracts were not profitable or otherwise unsatisfactory (explain below).
Payment schedule too slow.
Other:
Explanation: _______________________________________________________________________________________
If you have submitted a bid or proposal, but wish to offer suggestions or express concerns, please use the remarks section below:
Remarks: ___________________________________________________________________________________________________
Bidder/Offeror Name: _________________________________________________________
Contact Person: _______________________________________________
Signature: _____________________________________ Date: ___________
Address: ______________________________________________________
Email: _____________________________________________________________________________________________ Phone: ___________
Pa ge 3 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
Table of Contents
Key Information Sheet ......................................................................................................................
1. Contractor Requirements: Scope of Work .................................................................................
1.1. Summary Statement ...........................................................................................................
1.2. Background ........................................................................................................................
1.3. Minimum Qualifications ....................................................................................................
1.4. Responsibilities and Tasks .................................................................................................
1.5. Deliverables ........................................................................................................................
1.6. Optional Services ...............................................................................................................
2. Contractor Requirements: General ............................................................................................
2.1. Contract Initiation Requirements .......................................................................................
2.2. End of Contract Transition .................................................................................................
2.3. Invoicing .............................................................................................................................
2.4. Security Requirements .......................................................................................................
2.5. Problem Escalation Procedure ...........................................................................................
2.6. Substitution of Personnel ...................................................................................................
2.7. Work Orders <or Assignment of Work> ...........................................................................
3. Procurement Instructions ...........................................................................................................
3.1. Pre-Bid Conference ............................................................................................................
3.2. Questions and Addenda ......................................................................................................
3.3. Bid Due Date and Time ......................................................................................................
3.4. Multiple or Alternate Bids ..................................................................................................
3.5. Receipt, Opening and Recording of Bids ...........................................................................
3.6. Award Basis .......................................................................................................................
3.7. Tie Bids ..............................................................................................................................
3.8. Site Investigation ................................................................................................................
3.9. Duration of Bid...................................................................................................................
3.10. Modifications and Withdrawals of Bids .........................................................................
3.11. Cancellations ..................................................................................................................
3.12. Bid Acceptance ...............................................................................................................
3.13. Confidential/Proprietary Information .............................................................................
Pa ge 4 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
3.14. Incurred Expenses ...........................................................................................................
3.15. Insurance .........................................................................................................................
3.16. Bonds ..............................................................................................................................
4. Minority Business Enterprise (MBE) Utilization ......................................................................
5. General Informations for Bidders ..............................................................................................
6. Bid Instructions ........................................................................................................................
6.1. Bid Evaluation Criteria .......................................................................................................
6.2. Award Method ....................................................................................................................
7. Exhibits ........................................................................................................................................
Exhibit A: Pre-Bid Conference Request Form ..............................................................................
Exhibit B: Bidder Information Sheet ............................................................................................
Exhibit C: Bid Price Instructions and Form ..................................................................................
Exhibit D: MBE Affidavits and Forms .........................................................................................
Exhibit E: Bid Affidavit ................................................................................................................
Exhibit F: Firm Experience ...........................................................................................................
Exhibit G: Firm References ...........................................................................................................
Exhibit H: Key Personnel ..............................................................................................................
Exhibit I: Financial Stability of Bidder .........................................................................................
Exhibit J: Acknowledgement of Receipt of Addenda ...................................................................
Exhibit K: Conflict of Interest Affidavit and Disclosure ..............................................................
Exhibit L: UMBC Contract Agreement (Sample) .........................................................................
Exhibit M: Prime Contractor List of all Subcontractors ...............................................................
Pa ge 5 | 81
| The original Dining Hall 480 cabinet containing (2) original 480 breakers will be removed and disposed of by |
|---|
| the contractor |
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
1. Contractor Requirements: Scope of Work
1.1. Summary Statement
1.1.1. The University of Maryland, Baltimore County, a constituent institution of the University
System of Maryland, an agency of the state of Maryland (herein referred to as the "University"
or "UMBC"), intends to contract services for the replacement of an existing 13kV switch located at
the Dining Hall with a new switch supplied by UMBC.
SCOPE OF WORK:
A. The contractor will be responsible for carefully removing and disposing of the existing 13kv switch located in
the Dining Hall switch yard.
B. The contractor will install a new 13kV gas switch to be supplied by UMBC
C. The contractor will be responsible for procuring, supplying and installing temporary power large enough to
power three existing building loads for the duration of the project. The temporary power must be supplied
24/7 for the entire project. This may include a temporary switchboard and generator.
D. If a generator is to be used for temporary power, it shall not be less than 600kW.
E. Shutting down the building to connect temporary power may need to be done during off hours - including at
night or on a Sunday.
F. The original Dining Hall 480 cabinet containing (2) original 480 breakers will be removed and disposed of by
the contractor
G. The existing main service feed for the Dining Hall will be spliced into a concrete ground box to be installed at
grade to provide clearance of the new 13kV switch.
H. The contractor will install (4) runs of 500 mcm cable through (4) existing 4-inch conduits from the secondary
side of the existing pad mount transformer to the new ground box (to be installed by contractor) and splice
them onto the existing cable that feeds the Dining Hall.
I. The contractor will be responsible for purchasing and installing all the necessary conduits/raceways and
junction boxes for all the feeders associated with the new 13kV switch.
J. If conduit is to be used for the 13kV cable it shall be RMC.
K. All Junction boxes and boxes used as raceways shall be outdoor rated.
L. The contractor will be responsible for supplying, installing, and extending the incoming and outgoing 13kv
cable to be terminated on the new switch. This includes all splicing and terminations.
Pa ge 6 | 81
| The contractor will be responsible for ensuring the new 13kV switch is properly grounded per the 2026 NEC. |
|---|
| This may include updating the existing grounding system. |
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
M. The contractor will be responsible for contracting a third-party NETA or NICET certified medium voltage
testing company to test the new switch and all medium voltage cables, splices and terminations.
N. The contractor will be responsible for ensuring the new 13kV switch is properly grounded per the 2026 NEC.
This may include updating the existing grounding system.
O. The contractor will be responsible for installing the settings for the new switch. The settings for the new
switch gear will be supplied by UMBC.
P. The contractor will be responsible for supplying the equipment required to remove the existing switch and
installing the new switch.
Q. If a crane is used, the contractor must submit a lift plan 30 days prior to the crane arriving on campus.
R. A power outage request and MOP must be submitted to UMBC 30 days prior to the de-energizing of any
circuits during the project.
S. OCPD coordination is not the responsibility of the contractor.
T. Any damage to the landscaping due to the staging of equipment will be the responsibility of the contractor.
U. All electrical work shall be in accordance with the NEC, NETA, IEEE and NFPA 70E standards.
V. Proper PPE is required when testing energized circuits.
W. Working on energized circuits is prohibited on the UMBC campus. When working on a de-energized circuit
Lockout/tagout is required and shall be removed at the end of the workday.
X. Lockout/tagout hardware will be the responsibility of the contractor.
Y. The Contractor will notify electric shop personnel when energizing and de-energizing electrical circuits.
Z. Please reference attached photos 1-15 for images of the old and new 13kV switches, as well as associated
cables.
AA. Work must be completed within 30 days or less from the start of the project.
1.1.2. UMBC intends to make a single award as a result of this IFB. This is an Indefinite Delivery
Indefinite Quantity (IDIQ) contract. UMBC reserves the right to authorize services as may be
required during the contract period, and also, reserves the right to not authorize any services or
materials. UMBC does not guarantee a dollar amount will be met or exceeded, nor can UMBC
guarantee any minimum dollar amount to any Contractor.
1.1.3. The contract shall be in effect for 6 months unless otherwise extended, expired or terminated
pursuant to the contract.
Pa ge 7 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
1.1.4. UMBC reserves the right to extend the terms and conditions of this solicitation to any and all
other agencies within the state of Maryland as well as any other federal, state, municipal, county,
or local governmental agency under the jurisdiction of the United States and its territories. A
copy of the contract pricing and the solicitation requirements incorporated in this contract will be
supplied to requesting agencies. Each participating agency shall enter into its own contract with
the supplier. UMBC does not assume any responsibility other than to obtain pricing for the
specifications provided.
1.2. Background
Established in 1966, the University of Maryland, Baltimore County (UMBC) is one of twelve
institutions that, along with two regional centers, constitute the University System of Maryland. UMBC
is located on 482 acres with 4.2 million gross square feet and only 15 minutes from Baltimore's Inner
Harbor and 30 minutes from Washington, D.C. and five minutes from BWI Airport.
UMBC combines the emphasis on teaching found at the best liberal arts colleges with the innovation of
a research university. UMBC's students take full advantage of the educational, business, cultural, and
recreational resources of Baltimore and Washington, D.C. At UMBC, students work alongside faculty
who are leaders in their fields; think about the hard questions of society, science, and creative
expression; and then move beyond the classroom to make a difference.
UMBC is increasingly recognized as a major resource for building the State's economy and addressing
its social concerns. More than 70% of UMBC's 77,000 active alumni live and work in Maryland,
contributing significantly to the State's economic and social vitality. In Fall 2024, UMBC had 13,906
enrolled students of which 73% are minority enrollments from nearly all 50 states and 10.5% are
international enrollments from over 100 nations, creating a richly diverse student body.
Nearly seven percent of assignable space is dedicated to research laboratory facilities, a reflection of
UMBC's designation as a Doctoral University with Very High Research Activity - also known as R1 -
in the 2022 Carnegie Classification of Institutions of Higher Education, which places UMBC among
the top 146 research universities in the nation.
1.2.1. Project Goals: Install the 13kV switch and ensure it is in safe working condition.
1.2.2. Current Environment: This 13KV switch is located at the dining hall switch yard. Refer to
attached photos 1 - 15.
1.2.3. UMBC Staff and Roles
1.2.3.1. Procurement Officer: Nneka Miller, will serve as the facilitator for this procurement. All
communications regarding this solicitation shall be directed exclusively to the
Procurement Officer; nmiller7@umbc.edu.
1.2.3.2. MBE Liaison Officer: Rosetta Butler, rbutler2@umbc.edu
1.2.3.3. Project Manager: Christopher Serafin, UMBC Electric Shop Supervisor,
cserafin@umbc.edu.
Pa ge 8 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
1.2.4. UMBC Responsibilities:
1.2.4.1. UMBC will be responsible for providing the contractor with keys for the dining hall to
access the yard and building, if necessary.
1.2.4.2. UMBC will provide the Contractor with a limited number of parking permit (subject to
change based on the University's Parking Services Department policies).
1.3. Minimum Qualifications
1.3.1. The Bidder shall have 10 years' experience providing the description of services outlined in the
scope of work.
1.3.2. The Bidder shall be certified with a current Maryland Master Electrician License. As proof of
meeting this requirement, the Bidder shall provide a copy of certification with its Bid.
1.3.3. UMBC reserves the right to verify all information provided, as well as to consult any other
sources available including any person or persons associated with the references provided or the
project cited as a reference. UMBC also reserves the right to request additional references or
contact any known firm associated with the Bidder, as well as itself even if not provided as a
reference by the Bidder. References will be held in the strictest of confidence.
2. Contractor Requirements: General
2.1. Contract Initiation Requirements
2.1.1. Contractor shall schedule and hold a kickoff meeting within 10 business days of notice to
proceed date.
2.2. Invoicing
2.2.1. Payment will be made upon satisfactory completion of the project in accordance with the terms and
conditions set forth in the Contract.
2.2.2. Payments to the Contractor pursuant to the Contract shall be made no later than 30 days after
UMBC's receipt of a proper invoice from the Contractor. Each such invoice must reflect the
Contractor's federal tax identification number.
2.2.3. All fees are exclusive of applicable federal, state, local, and foreign sales, use, excise, utility,
gross receipts, value added and other taxes, tax-like charges and tax-related surcharges. UMBC
is generally exempt from such taxes and Contractor agrees not to charge UMBC for such taxes in
accordance with applicable law. UMBC will provide exemption certificates upon request.
Charges for late payment of invoices are prohibited.
2.3. Security Requirements
2.3.1. Upon request of UMBC personnel, each Contractor Personnel shall provide photo identification.
Contractor Personnel shall cooperate with UMBC site requirements, including but not limited to,
being prepared to be escorted at all times, and providing information for UMBC badge issuance.
2.3.2. Contractor shall remove any Contractor Personnel from working on the Contract where UMBC
determines, in its sole discretion, that Contractor Personnel has not adhered to the Security
requirements specified herein.
Pa ge 9 | 81
Solicitation Name: Dining Hall 13KV
Switch Replacement
Solicitation Number: BC-21512-M
2.3.3. UMBC reserves the right to request that the Contractor submit proof of employment
authorization of non-United States Citizens, prior to commencement of work under the Contract.
2.3.4. A criminal background check for each Contractor Personnel providing services onsite shall be
completed prior to providing any services under the Contract. The criminal background check is
at the Contractor's expense.
2.4. Problem Escalation Procedure
The Contractor must maintain a Problem Escalation Procedure (PEP) for both routine and emergency
situations. The PEP must state how the Contractor will address problem situations as they occur during
performance of the contract and how resolution will be communicated to UMBC.
2.5. Substitution of Personnel
2.5.1. All subcontractors shall be identified and a complete description of their role relative to the bid
shall be included in the Bidder's bid.
2.5.2. Key Personnel identified in the Bidder's bid may not be substituted, removed, or added
throughout the duration of the contract, without the prior written consent of UMBC.
2.5.3. Bidder shall demonstrate to the Project Manager's satisfaction that the proposed substitute has
qualifications at least equal to those of the Key Personnel proposed to be replaced.
3. Procurement Instructions
3.1. Pre-Bid Conference & Site Visit
3.1.1. A pre-bid conference will be held at the date, time and location indicated on the Key Information
Summary Sheet.
3.1.2. Attendance at the Conference is not mandatory, but all interested parties are encouraged to attend
in order to facilitate better preparation of their Bids. If the solicitation includes an MBE goal,
failure to attend the Conference will be taken into consideration as part of the evaluation of an
Bidder's good faith efforts if there is a waiver request.
3.1.3. The University is committed to ensuring that persons with disabilities have equally effective
opportunities to participate in and benefit from the University's programs and services. Persons
who may require reasonable ADA accommodations should contact the Issuing Office at
nmiller7@umbc.edu five (5) days prior to any meeting scheduled in connection with this
solicitation.
3.1.4. Site Visit
3.1.4.1. The site visit will be held in-person at 11:00 AM on Wednesday, May 27, 2026. Firms
shall meet the Project Manager at the dining hall switch yard. Second walk-through of project
site may be held upon request.
3.1.4.2. Attendance at this site visit is mandatory in order to submit a bid. All bidders must be
present at the designated time and location to be eligible to participate in the bid process.
Failure to attend the mandatory site visit will result in the disqualification of the bidder's
proposal.
Pa ge 10 | 81
With Free Trial, you can:
You will have a full access to bids, website, and receive daily bid report via email and web.
Follow Repair Building 3002 Fuel Cell Hangar Active Contract Opportunity Notice ID W50S6W26BA002
DEPT OF DEFENSE
Bid Due: 7/29/2026
ID: BPM058063 Title: FC0002809 Site #329 FA3 DNR- Upper Marlboro - 11704 Fenno
State Government of Maryland
Bid Due: 8/13/2026
ID: BPM057988 Title: LTR Cromwell Maintenance & Storage Facility Modernization Project (LRMP Tranche
State Government of Maryland
Bid Due: 11/12/2026
ID: BPM057970 Title: Design-Build Services for Rooftop Solar Installations Status: Open Due /
State Government of Maryland
Bid Due: 8/18/2026