Armstrong Avenue Pedestrian Bridge (CIP No.70257) & Neighborhood D South Phase 2 Package #2 Improvements (CIP No.70256)
| Agency: | City of Tustin |
|---|---|
| State: | California |
| Type of Government: | State & Local |
| NAICS Category: |
|
| Posted Date: | Jul 23, 2026 |
| Due Date: | Aug 25, 2026 |
| Solicitation No: | CIP No. 70257 and 70256 |
| Original Source: | Please Login to View Page |
| Contact information: | Please Login to View Page |
| Bid Documents: | Please Login to View Page |
Description
Project ID: CIP No. 70257 and 70256
Title: Armstrong Avenue Pedestrian Bridge (CIP No.70257) & Neighborhood D South Phase 2 Package #2 Improvements (CIP No.70256)
Addenda: 0
Release Date: 7/23/2026
Due Date: 8/25/2026
Post Information
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Summary
NOTICE IS HEREBY GIVEN that the CITY OF TUSTIN, as AGENCY, invites sealed bids for the above stated project and will receive bids for construction, materials, supplies, equipment, and/or services set forth herein, subject to all conditions outlined in the Bid Package.
Scope of Work: This work shall consist in part of furnishing all labor, materials, tools, equipment and incidentals as required by the plans, specifications and contract documents for the above stated project.
The work to be done hereunder consists of fine grading, ARHM roadway overlay, removals and adjustments, dry utilities, hardscape, landscaping and irrigation, pavement striping, signing and delineation, traffic signal installation and interconnect, street lighting, pathway lighting, and the construction of a pedestrian bridge:
- The Neighborhood D South area is generally bounded by Armstrong Ave, Warner Avenue, Airship Ave and Compass Avenue.
- The Linear Park area is generally west of Armstrong Ave and north of Airship Ave.
- Armstrong Pedestrian Bridge spans over Armstrong Avenue, southwest of Warner Avenue and north of Airship Avenue.
Background
Project Schedule (contract days): 250 Working Days
Engineer’s Estimate: $ 10 Million
Liquidated Damages: $ 6700 / Calendar Day
Bid Valid (calendar days): 60 Days
Contractor's License(s): Class A
Timeline
See Also
Project ID: pf 2306; Bid 2725 Title: Community Civic Campus: Phase 3, Fire
City of South San Francisco
Due by 12/01/2026
Bid No. 008-26/27 - Asphalt Improvement Project at Multiple Sites Notice Inviting Proposal
Glendale Unified School District
Due by 11/17/2026
Follow Mather Fueling System Repairs Active Contract Opportunity Notice ID PANNWD26P028176 Related Notice
DEPT OF DEFENSE
Due by 11/20/2026
Follow Solicitation: Construct Combat Rescue Helicopter Flight Simulator Facility at Moffett ANGB Active
DEPT OF DEFENSE
Due by 11/27/2026