This is a phased renovation to the historic Allen Fieldhouse that is located on the
University of Kansas campus. This arena is home to the Kansas Jayhawk’s men’s &
women’s basketball team. Phase 01 renovation scope primarily consists of interior
upgrades to the ticketing offices, rally house(s), and back of house spaces on first
and second floors to be completed prior to the 2023-24 basketball seasons. Phase
02 scope will include further interior upgrades and MEP upgrades, as well as
Wagnon Parrot renovations. Phase 02 will be issued at a later date. Award of Phase
01 scope does not indicate any further awards in future phases.
This bid is for MEP Early Equipment Packages.
In order for your bid to be considered it MUST be uploaded via this online ebid
system. Bids submitted around the system or via email will not be considered. Direct
all questions about submitting bids to Julie Bellucci jbellucci@ku.edu
Bid Activities
Question Deadline
ALL QUESTIONS must be submitted to KU instead of Turner Construction.
5/3/2023 12:00:00 PM (CT)
Questions requesting clarification of the Solicitation must be submitted through the University's Ionwave Questions
Tab, prior to 12:00 Noon CT on Wednesday May 3, 2023. Each question or clarification should reference the
appropriate Solicitation section.
Bid Close Date and Time
5/8/2023 2:00:00 PM (CT)
Bids are due by 2:00pm local time on Monday May 8, 2023. All proposals shall be in accordance with plans and
specifications as prepared by MultiStudio, dated 04/03/2023.
Any bids submitted directly to Turner Construction WILL NOT be considered.
ALL bids must be submitted through the KU Ionwave ebid system to be considered.
If bid documents are not uploaded to the Ionwave ebid system by the bid close date and time they WILL NOT be
accepted or considered for review.
Bid Attachments
L100151741 Early Equipment - Addend 2 Bid Questions.pdf
L100151741 Early Equipment - Addend 2 Bid Questions
L100151741 Addendum 1 - Revisions - Drawings.pdf
L100151741 Addendum 1 - Revisions - Drawings
Attachment A - 2023 0503_AFH Early Equipment Revision_ELEC.pdf
Attachment A - 2023 0503_AFH Early Equipment Revision_ELEC
View Online
View Online
View Online
Page 2 of 4 pages
Deadline: 5/8/2023 02:00 PM (CT)
L100151741 Addendum 2
Invitation to Bid_AFH_Phase 02_Early Equipment Packages.pdf
Invitation to Bid_AFH_Phase 02_Early Equipment Packages
Project Procedures Manual_AFH_Early Equipment.pdf
Project Procedures Manual_AFH_MEP Early Equipment
Section 00 - Project Bid Form - AFH.pdf
Section 00 - Project Bid Form - AFH
AFH AHU Early Equipment Specificaitons.pdf
AFH AHU Early Equipment Specifications
AFH ELEC DRAWINGS.pdf
AFH ELEC DRAWINGS
AFH ELEC Early Equipment Specifications.pdf
AFH ELEC Early Equipment Specifications
AFH M401 - MECHANICAL SCHEDULES.pdf
AFH M401 - MECHANICAL SCHEDULES
Form 36 -III REV 7-31-20 - SAMPLE.pdf
Form 36 -III REV 7-31-20 - SAMPLE
Form 166 Purchase Contract REV 07-31-20 - SAMPLE.pdf
Form 166 Purchase Contract REV 07-31-20 - SAMPLE
View Online
View Online
View Online
View Online
View Online
View Online
View Online
View Online
View Online
Page 3 of 4 pages
Deadline: 5/8/2023 02:00 PM (CT)
L100151741 Addendum 2