AE Vault Fire Suppression System Central Services Addendum 2

Agency: State of Vermont
State: Vermont
Type of Government: State & Local
NAICS Category:
  • 238210 - Electrical Contractors and Other Wiring Installation Contractors
  • 238220 - Plumbing, Heating, and Air-Conditioning Contractors
  • 561621 - Security Systems Services (except Locksmiths)
Posted Date: Mar 24, 2026
Due Date: Apr 3, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page
TITLE QUESTIONS DUE ANSWERS POSTED DUE DATE NO POSTING AFTER
AE Vault Fire Suppression System Central Services
Addendum 1
Addendum 2

03/17/2026 04:30PM


04/03/2026 04:30PM

Attachment Preview

VAULT FIRE SUPPRESSION SYSTEM
1078 US Route 2 CENTRAL SERVICES BUILDING
ADDENDUM # 2
State of Vermont
Department of Buildings and General Services
Office of Purchasing & Contracting
133 State Street
Montpelier, Vermont 05633-8000
March 24, 2026
TO ALL BIDDERS OF RECORD:
This Addendum consists of (2) page(s) and (4) attachments:
DFS Certificate of Fitness - 4 pages
F3 – Foundation Details – 1 page
F1 – Foundation Plan – 1 page
M7 – Pellet system & Heat Replacement – 1 page
Acknowledge receipt of this Addendum by entering its number and date on the Proposal Form. This
Addendum forms a part of the Contract Documents and modifies them as follows:
Items:
1. Date Changes:
RESPONSES DUE BY: April 3, 2026 – 4:30 PM (EST)
2. Pre-Bid Meeting Attendees:
a. Oren Guttman, MacFarland Johnson, oguttmann@mjinc.com
b. Ira Moser, BGS State of Vermont, Ira.Moser@Vermont.gov
c. David Gallison, BGS State of Vermont, David.Gallison@Vermont.gov
d. Josh Sayers, BGS State of Vermont,. Josh.Sayers@Vermont.gov
e. Rachel Onuf, VSARA State of Vermont, Rachel.Onuf@Vermont.gov
3. Questions & Answers:
a. Q: Are the temperature and humidity requirements for the eventual contractor or are
there required HVAC modifications to meet these requirements?
A: The existing equipment provides current temperature and humidity requirements.
Section 2.2.1.2.3. is no longer included as part of this RFP.
b. Q: Does the existing system need to remain operational until the new system is
operational?
A: Yes, the existing system is to remain operational until the new system is operational.
Rev 12.24.25
c. Q: Does the work need to be overseen by a Vermont Fire Protection P.E. or is a NICET
III Engineering Technician acceptable?
A: Attached are the requirements to Design, install, inspect, service, or recharge a fixed
fire extinguishing system. An NICET III Engineering Technician is acceptable.
d. Q: Development – Can the design schedule be condensed to eliminate the Design
Development phase and go straight to Construction Documents from Schematic
Design?
A: The design development phase and the construction document phase may be
combined. Therefore, construction documents can go straight from schematic design.
e. Q: Does Engineer need to provide Submittal Exchange? If so, what timeframe?
A: Submittal Exchange will not be required for this project.
f. Q: Does the State have structural drawings of the vault construction?
A: Attachments “F1 – Foundation Plan” and “F3 – Foundation Details” included with
this addendum contain original foundation and framing plans from 1988. These contain
structural information.
Additionally, a 2017 Pellet System & Heat Replacement took place at the Central Services Building
in the vault & Mezzanine area. Attachment “M7 – Pellet system & Heat Replacement” included with
this addendum contains a new mechanical plan.
END OF ADDENDUM # 2
Rev 12.24.25
Mezzanine
framing
Mezzanine
Mfeoundation
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Statewide Elevator Inspection Services Request Date: 6/5/2026 9:55:32 AM Open Date: Closing Date:

State Government of Vermont

Bid Due: 6/30/2026

Northern State Correctional Facility (NSCF) Fire Pump Replacement Request Date: 5/27/2026 12:24:39 PM

State Government of Vermont

Bid Due: 7/17/2026

Walkway Repair and Replacement Request Date: 5/24/2026 8:43:26 PM Open Date: Closing Date:

State Government of Vermont

Bid Due: 6/22/2026

Fairfield Dam Inspection Request Date: 5/4/2026 1:48:02 PM Open Date: Closing Date: 6/19/2026

State Government of Vermont

Bid Due: 6/19/2026