Adobe Creek Transformer-21; 15 MVA LTC Replacement & Radiator Flange Repair/Regasket

Agency: City of Palo Alto
State: California
Type of Government: State & Local
NAICS Category:
  • 238210 - Electrical Contractors and Other Wiring Installation Contractors
  • 811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance
Posted Date: Mar 25, 2026
Due Date: Apr 9, 2026
Original Source: Please Login to View Page
Contact information: Please Login to View Page
Bid Documents: Please Login to View Page


Project ID:

Title: Adobe Creek Transformer-21; 15 MVA LTC Replacement & Radiator Flange Repair/Regasket

Addenda: 0

Release Date: 3/25/2026

Due Date: 4/9/2026

Follow
Adobe Creek Transformer-21; 15 MVA LTC Replacement & Radiator Flange Repair/Regasket
Invitation for Bid- Construction
Utilities
93677
Project ID: IFB197195
Release Date: Wednesday, March 25, 2026
· Due Date: Thursday, April 9, 2026 3:00pm
Posted Wednesday, March 25, 2026 10:53am
All dates & times in Pacific Time
Draft Response No Bid14 days, 20 hours, 50 minutes


Post Information

Posted At:Wed, Mar 25, 2026 10:53 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

The City is soliciting proposals from qualified and experienced vendors to perform the repair and refurbishment of a 15 MVA Allis Chalmers substation transformer equipped with a TLH‑21 on‑load tap changer (OLTC). The existing 1967 TLH‑21 OLTC is exhibiting mechanical failures that prevent proper tap changing, although initial assessments indicate that the transformer’s core and coil remain electrically sound. Additional observed deficiencies include minor oil migration between the OLTC cabinet and main tank, as well as two leaking radiator valves.

The selected contractor will be responsible for the complete replacement of the TLH‑21 OLTC with a certified remanufactured unit, full oil handling and processing for both the OLTC and main transformer tanks, and resealing of all interfaces to eliminate oil transfer. Approximately 4,348 gallons of oil will be drained from the main tank into a contractor‑provided holding tanker for later reuse, while the OLTC tank oil (approximately 760 gallons) will be drained into City‑provided containers and replaced with new transformer‑grade oil if necessary based on testing and condition. The scope also includes replacement of radiator valves and gaskets, removal and replacement of the 60 kV SMD fuse holder, pressure testing of the main tank, and execution of all required pre‑ and post‑work diagnostic testing, including power factor testing, TTR, excitation, winding resistance, SFRA, DGA, and oil quality analysis. The City of Palo Alto Utilities will dispose of any transformer oil that is not intended for reuse.

The objective of this project is to restore full mechanical functionality and dielectric reliability of the transformer and its OLTC system, prevent further degradation, and extend the operational service life of this critical distribution asset. Vendors with demonstrated expertise in OLTC replacement, transformer oil processing, and high‑voltage diagnostic testing are encouraged to submit proposals in accordance with this IFB.



Timeline

Bid Post Date:
March 25, 2026
Question and Clarifications Due Date and Time:
March 30, 2026, 1:00pm
Bid Due Date and Time:
April 9, 2026, 3:00pm
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Bid Details WD-2932 Cathodic Protection for Transmission Pipelines at Various Locations, Phase 3

San Francisco Public Utilities Commission

Bid Due: 7/09/2026

Project ID: MS26-135 Title: Qualified Sewer Lateral Pipeline Repair Contractor Addenda: 0 Release

City of Victorville

Bid Due: 7/07/2026

Project ID: Title: CALERA CREEK WATER RECYCLING PLANT - ON CALL MAINTENANCE PROJECT

City of Pacifica

Bid Due: 6/30/2026

E1909517 - Sidewalk Repair Program - Package No. 79: CTIEP Status Stage Open

City of Los Angeles

Bid Due: 7/22/2026