April 30, 2026
ADDENDUM NO. 2
TO THE CONTRACT DOCUMENTS FOR
Town of Middlebury
2026 Municipal Paving Project
Your attention is directed to the following changes in, additions to, or deletions from the Contract
Documents for the Town of Middlebury 2026 Municipal Paving Project. This complete
Addendum, including attachments, shall be included within the Contract Documents and shall
take precedence in the case of any discrepancies.
BIDDER must acknowledge receipt of all ADDENDA on the BID or may be considered non-
responsive. This Addendum consists of one (1) page.
1. Special Conditions: REMOVE Special Condition 13 – Areas of Work and Required Paving
Thicknesses and REPLACE Special Condition 13 – Areas of Work and Required Paving
Thicknesses in its entirety as follows:
“13. Areas of Work and Required Paving Thickness – The following is a list of the areas of
work and expectations for paving types and thicknesses.
PAVING SCHEDULE
Mary Hogan Parking Lot
Rec Park Sidewalk
Mary Hogan Drive
DPW North Side of Shop
Lower Plains Road
Seminary Street
South Street
Willow Drive
Compacted Depth Estimated Area (SF)
2.25 Inches
31,500
4-inches
6,050
4-inches
4,700
4-inches
11,000
2.25 Inches
68,875
2.25 Inches
49,607
1.25 Inches
71,800
2.25 Inches
11,500
Work Scope
3/4 Inch Shim and 1 1/2 Inch Top
2-inches of top, 2 - inches of top
2-1/2 Inches of Base and 1-1/2 Inches of Top
2 -1/2 Inches of Base and 1-1/2 Inches of Top
3/4 Inch Shim and 1 1/2 Inch Top
3/4 Inch Shim and 1 1/2 Inch Top
1-1/4 Inch Top
3/4 Inch Shim and 1 1/2 Inch Top
Questions During Bid Phase
QUESTION:
If you pave curb to curb the square footage for south street is incorrect?
ANSWER:
Thank you. Refer to revised table. This number was used in
calculating the total TONS of asphalt and no change needed to bid
schedule.
Town of Middlebury – 2026 Municipal Paving Project
Addendum No. 2 to the Contract Documents
Otter Creek Engineering, Inc.
April 30, 2026
Page 1 of 1
This page summarizes the opportunity, including an overview and a preview of the attached documents.
* Disclaimer: This website provides information about bids, requests for proposals (RFPs), or requests for qualifications (RFQs) for convenience only and does not serve as an official public notice. Individuals who wish to respond to or inquire about bids, RFPs, or RFQs should contact the relevant government department directly.

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now