PIVOTAL , LLC
1515 POYDRAS STREET, SUITE 1150
NEW ORLEANS, LA. 70112
(504) 799-3653
ADDEDNDUM # 2
CHILLER REPLACEMENT @ MARY KELLER ZERVIGNON
Owner: Orleans Parish School Board (OPSB)
Program Manager: Manning Architects (Clarence Eugene III – Sr. Project Manager)
Project #: ITB23-FAC-0073
Date: 12/10/2025
Project Location: 3128 Constance Street, New Orleans, LA. 70115
POR: Pivotal Engineering LLC, Bassam Rossi Mekari, PE / 225-205-3490
I- Answers To Questions/Emails (Questions are in numerical orders,
Answers are below each question):
NONE THIS ADDENDUM
II- Substitutions Requests:
As per the front-end bid documents in section 4.3, the following guidelines shall be met:
“4.3 Substitutions:
4.3.1 The materials, products and equipment described in the Bidding Documents establish a standard
of quality, character, type, style, function, dimension, and appearance desired. Equivalent products may
be acceptable, as stated in La. R.S. 38:2212.T(2). It shall be the responsibility of the Architect/Engineer to
determine if a proposed substitution is equivalent. No substitutions shall be allowed after bidding, except
as may be provided in the Contract Documents.
4.3.2 No substitution will be considered unless written request for approval has been submitted by the
Proposer and has been received by the Architect/Engineer at least seven (7) working days prior to the deadline
for submission of Bids. (La. R.S. 38:2295.C) Each such request shall include the name of the material or
equipment for which it is to be substituted and a complete description of the proposed substitute including
model numbers, drawings, cuts, performance and test data and any other information necessary for an
evaluation. A statement setting forth any changes in other materials, equipment or work that incorporation
of the substitute would require shall be included. It shall be the responsibility of the Proposer to include
in his proposal all changes required of the Contract Documents if the proposed substitution is used. Prior
approval is given contingent upon supplier being responsible for any costs which may be necessary to
modify the space or facilities needed to accommodate the materials and equipment approved.
4.3.3 If the Architect approves any proposed substitution, such approval will be set forth in an
Addendum. Bidders shall not rely upon approvals made in any other manner.”
Page 2 of 2
Acceptable Substitutions:
Equipment
1- Chill Water Pump
2- Suction Diffuser
3- Triple Duty Valve
4- Air Separator
Manufacturer
Taco Comfort Solutions
Taco Comfort Solutions
Taco Comfort Solutions
Taco Comfort Solutions
Taco Comfort Solutions is acceptable compatible manufacturer. However, as per our
bid specs, proposed equipment must meet at a minimum the following:
1- It is contractor s responsibility to ensure that all bid documents are adhered to.
2- Specification Section 23 64 23.13 Para 3.02 discusses that proposed manufacturers shall
have a local rep within 10 miles of the job site with qualified HVAC technicians and
engineers that can service the provided equipment.
3- Equipment must be made in the USA.
4- Engineer approval does not allow specification compromises. The contractor remains
responsible for meeting all equipment specifications.
End of Addendum #2
Bassam Rossi Mekari, PE - Principal
Bassam Rossi Mekari
Pivotal Engineering