Attachment Preview

ADDENDUM #3
HVAC EQUIPMENT REPLACEMENT
MATHEWSON ELEMENTARY SCHOOL
ORANGE AVENUE ELEMENTARY SCHOOL
ORCHARD HILLS ELEMENTARY SCHOOL
EAST SHORE MIDDLE SCHOOL
JONATHAN LAW HIGH SCHOOL
MILFORD, CT 06460
S/P+A PROJECT NO. 23.141
DATE: February 22, 2024
The following changes to the Drawings and Project Specifications shall become a part of the Drawings
and Project Specifications; superseding previously issued Drawings and Project Specifications to the
extent modified by Addendum No. 3.
General Information/Clarifications:
RFI’s: As indicated in RFI Log, attached as part of this Addendum. (3 pages)
The bid due date is unchanged by this Addendum.
The Addendum consists of four (4) pages of 8½” x 11” text, and zero (0) sheets of 30” x 42” drawings.
End of Addendum #3
HVAC Equipment Replacement - Five Schools – Milford
Addendum #3-1
SILVER PETRUCELLI + ASSOCIATES
3190 Whitney Avenue | Hamden CT 06518
311 State Street | New London CT 06320
BID RFI LOG
Project: 5 School HVAC Replacement Project
S/P+A Project #: 23.141
RFI Deadline: 2/20/24 EOD
Bids Due: 2/27/24, 3:00 PM
RFI #
001
002
003
004
005
QUESTION
As it pertains to Jonathan Law HS, does HP-1/FCU-1 &
FCU-2 require BACnet interface to communicate with the
Jonhson Controls BMS System?
DATE
RECEIVED
02/15/24
In speaking with our Sales Engineer at Trane, the specified
alternate unit ACRTU-004 at Orchard hills is a 4TCC4024
series unit. These units are electro-mechanically controlled
and do not have an option for “factory installed controls” or a
BACnet card. They will need inputs regarding temperature
sensing, and contact closures for heat/cool, etc. Base bid
ACRTU-033 at Mathewson is also a similar unit. Please
confirm JCI controls mounted in these (2) Trane RTU’s is
the design intent.
02/15/24
The bid form has lines for alternate bids, one for each
school. Please confirm this is for an individual price for each
school inclusive of all work less any alternates.
All schools, with the exception of Jonathan Law have an
alternate for seismic curbs, however the bid form only lists
an alternate for Orchard Hills for RTU-4. Please confirm if
an updated bid form will be issued, with (4) alternates for
seismic curbs for the (4) schools requiring such.
The base bid call for existing curbs to be seismically
reinforced. As no seismic/vibration engineers are willing to
perform a delegated designed on an existing curb, on an
existing roof, please detail what is required at each curb for
reinforcement/anchorage.
02/15/24
02/15/24
02/15/24
RESPONSE
Provide a signal from the BMS for
occupied/unoccupied modes and read space
temperature from BMS.
ADDENDUM #
ISSUED
#2 Issued 2/21/24
Provide a zone controller compatible with BMS for
control of ACRTU-004 at Orchard Hills and ACRTU-
033 at Mathewson with occupied/unoccupied signal
to enable unit, and space temperature setpoint
adjustment from BMS.
#2 Issued 2/21/24
Correct. The lines are for the Base Bid Work for each
school perform separately from the others, less any
altenates.
#2 Issued 2/21/24
Will issue revised bid form. See the response to
RFI#5 below.
#2 Issued 2/21/24
The Base Bid scope for reinforcing the existing curbs
is eliminated and the Base Bid is now for the
replacement of the curbs with new seismic/wind rated
curbs .
#2 Issued 2/21/24
Page 1 of 3
SILVER PETRUCELLI + ASSOCIATES
3190 Whitney Avenue | Hamden CT 06518
311 State Street | New London CT 06320
BID RFI LOG
Project: 5 School HVAC Replacement Project
S/P+A Project #: 23.141
RFI Deadline: 2/20/24 EOD
Bids Due: 2/27/24, 3:00 PM
RFI #
006
007
008
009
010
011
012
013
014
QUESTION
DATE
RECEIVED
Add alternate 2 is for Asbestos Abatement at East Shore
Middle School. Will more information be forthcoming in
regards to the extent of Asbestos removal and a report of
findings?
02/15/24
Please confirm duct cleaning is required for each duct
system in its entirety for each RTU being replaced.
Drawing MS-ME1, OH-ME1,OA-ME1 Mech note 1
references reinforcement of existing curb for seismic loads,
which code and section is being referenced?
02/15/24
02/15/24
Same drawings as listed above- Mech note 3 bid alternate.
No roofing detail is on drawings, will this be under the steel
addendum?
02/15/24
Who is the preferred vendor for fire alarm work?
02/15/24
Are gas press fittings (Viega Mega Press) acceptable?
02/15/24
Drawing LHS-ME1- Is the mechanical contractor responsible
for roof load calculations and condenser rail design cost for
HP-1? Is there a basis of design on the roof rails?
When should we expect the structural drawings for East
Shore Middle?
Has the Prebid meeting attendance list been posted, I do
not see it on the site.
02/15/24
02/15/24
02/15/24
RESPONSE
ADDENDUM #
ISSUED
The hazardous material reports are attached to
addendum #2. The bid alternate for Asbestos
Abatement has been removed from the bid form which
is reissued with Addn #2. The Owner will arrange for
and pay for hazardous material abatement
#2 Issued 2/21/24
concurrently with the chosen contractor's job progress
at the schools. The Contractor is responsible for
coordinating their schedule with the Owner and
Abatement company so that the Contractor's progress
is not affected in any way.
Duct cleaning is required for all duct systems serving
RTUs and AHUs being replaced.
#2 Issued 2/21/24
The Base Bid scope for reinforcing the existing curbs
is eliminated and the Base Bid is now for the
replacement of the curbs with new seismic/wind rated #2 Issued 2/21/24
curbs .
Installation of the new seismic/wind rated roof curbs
shall be in accordance with manufacturer's
requirements. Attachment to structure shall be a
delegated design responsibility although no additional #2 Issued 2/21/24
structural steel is anticipated. Curbs shall be flashed
to roof and sealed to roof using materials and
methods approved by roofing manufacturer.
Notifier is the vendor. Firetech is the installing
contractor.
#2 Issued 2/21/24
No. Gas piping should be threaded Schedule 40 steel
pipe.
#2 Issued 2/21/24
Yes. Manufacturer's support rails are acceptable
providing they meet seismic and wind restriant
requirements.
#2 Issued 2/21/24
Structural drawing for East Shore will be part of
Addendum #2.
The Pre-bid meeting sign-in sheet was issued as part
of Addendum #1.
#2 Issued 2/21/24
#2 Issued 2/21/24
Page 2 of 3
SILVER PETRUCELLI + ASSOCIATES
3190 Whitney Avenue | Hamden CT 06518
311 State Street | New London CT 06320
BID RFI LOG
Project: 5 School HVAC Replacement Project
S/P+A Project #: 23.141
RFI #
QUESTION
015
Will existing structural drawings be provided?
016
What is the roofing material of each location?
017
Will an alternate bid form be provided with spaces for the
alternates?
Should modification of the doorway for ACHSS001 at
018
Jonathan Law be carried or will that be handle by the
owner?
RFI Deadline: 2/20/24 EOD
Bids Due: 2/27/24, 3:00 PM
DATE
RECEIVED
RESPONSE
ADDENDUM #
ISSUED
02/21/24
02/21/24
02/21/24
02/21/24
Existing structural drawings will not be issued during
the bid phase. There are limited structural drawings at
the MPS archives that may be available to the
contractor during construction.
#3 Issued 2/22/24
Mathewson: Membrane roof.
Orange Ave: Membrane roof.
Orchard Hills: Membrane roof except asphalt sheet
roof at location ACHVRTT 004.
Law HS: Membrane roof.
East Shore: Asphalt sheet roof.
Refer
to Addendum #2 for more roofing information.
#3 Issued 2/22/24
Yes.
#3 Issued 2/22/24
The contractor shall be responsible for demolition,
reconstruction and finishes for work required to move
equipment into the space.
#3 Issued 2/22/24
Page 3 of 3

Sign-up for a Free Trial, Government Bid Alerts

With Free Trial, you can:

You will have a full access to bids, website, and receive daily bid report via email and web.

Try One Week FREE Now

See Also

Bid Number: 3145 Bid Title: Westbrook Town Hall Roof Top Unit Replacement Category:

Town of Westbrook

Bid Due: 4/26/2026

HVAC Contractor OPEN 0 4/25/2024 5/10/2024

City of Shelton

Bid Due: 5/10/2024

21951 | EASTCONN Cooperative Ice Cream Bid 2024-2025 Ice Cream for the period

State Government of Connecticut

Bid Due: 5/03/2024

21936 | HVAC & Automation Controls - Full Service Maintenance Contract East Lyme

State Government of Connecticut

Bid Due: 4/30/2024