Government contract and bid
About Us Sitemap Help Sign In
Construction of DOL Conference Room
Program Summary
Title: Construction of DOL Conference Room
GovCB Opps ID : ADP12227094070000834
Document Type: Combined Synopsis/Solicitation (Modified)
FSC Code: Z - Maintenance, Repair or Alteration of Real Property
Set Aside: N/A
Solicitation No.: OASAM_BOS_2008-01
Source: https://www.fbo.gov/?s=opportunity&mode=form&id=10ed6f23b469c25dda89cb32f45da72d&tab=cor...
Place of
Performance:

Posted Date:
Sep 29, 2008
Last Update: Sep 29, 2008
Due Date: Sep 30, 2008

Description
Construction of DOL Conference Room
Solicitation Number: OASAM_BOS_2008-01
Agency: Department of Labor
Office: Office of the Assistant Secretary for Administration and Management
Location: Boston
  • Print
  • Link
    Copy or Bookmark this Page

    Copy the url below for a direct link to this page.

    Bookmark this page by right-clicking here and choosing "Bookmark This Link..."

Opportunity History
Solicitation Number:
OASAM_BOS_2008-01
Notice Type:
Combined Synopsis/Solicitation
Synopsis:
Added: Sep 04, 2008 4:18 pm Modified: Sep 29, 2008 9:39 amTrack Changes
Scope of Work

1. Unless otherwise specified herein, the contractor shall provide all supplies, personnel, equipment, tools, materials, supervision, and other items or services necessary for the construction of DOL conference space, which is to be located in Room E-215 of the JFK Federal Building, 25 New Sudbury Street, Boston, MA 02203.

Project includes acquiring approximately 700 square feet from the adjacent Room 235, currently occupied by OFCCP. Please refer to attached drawing for more details.

Construction to be done includes the following:

Construct twenty-two (22) linear feet of new drywall between new conference room, and remaining OFCCP space. Prime new drywall and apply two coats of paint;

Demolish existing office walls within former OFCCP area (approximately 22 linear feet);

Re-paint entire conference room with two coats of paint;

Furnish and install one fire-rated three-foot door at masonry wall;

Repair and replace any damaged ceiling tiles;

Install carpet tiles for the renovated conference space (carpet tiles will be provided by DOL OASAM);

Furnish and install cove base in conference room and both sides of new wall.

2. Demolition and construction also includes the complete renovation of electrical and related systems and equipment as defined in this scope. Electrical renovation shall include but not be limited to the following: Service connections, panels, outlets, switches, circuits, lighting fixtures, faceplates, IT wiring, other telephone and data wiring, etc. within newly renovated conference room (exact locations to be determined).

The contractor shall provide and install the following for new DOL conference space:

Remove any electrical/data in demolished walls;

Install new secure data cabinet, including installation of four (4) data lines and four (4) phone lines from conference to LAN Room;

Install twenty (20) CAT-5 drops within new conference room;

Include power and cable for wall mount TV;

Provide sixteen (16) dimmed hi-hats;

Provide emergency lighting;

Provide and install eight (8) new receptacles (duplex wall outlets).

3. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All materials used for this contract shall be new, unless otherwise noted.

4. The contractor shall furnish in writing the names of all contractor personnel, and shall advise immediately whenever changes are made.

5. The contractor shall comply with Federal drug-free workplace and work force requirements under the Federal Acquisition Regulations.

6. Some classifications of work may require special protective gear. The contractor shall be responsible for identifying those job classifications requiring protection equipment IAW OSHA standards.

7. The U.S. Department of Labor (US DOL) requires contractor support to perform the tasks listed in this statement of work. The work shall be performed within DOL office space assignments at the John F. Kennedy Federal Building (JFK FB), 25 New Sudbury Street, Boston, Massachusetts. The JFK FB is owned and managed by the U.S. General Services Administration (US GSA).



8. All written specifications and plans submitted by the contractor must be reviewed and approved by GSA prior to the commencement of any work. This includes but is not limited to acquiring the written approval of the GSA Fire Protection Engineer and the GSA Senior Property Manager of the JFK FB.



9. All contractor staff must meet security clearance requirements as outlined by Homeland Security Presidential Directive 12 (HSPD-12) and which will be coordinated and confirmed through the U.S. Department of Homeland Security/Federal Protective Service.



10. Copies of all trade licenses for contractors working within the JFK FB must be provided for review prior to the commencement of any work.



11. Contractor shall provide to GSA, and maintain at their sole cost and expense throughout the project, the following insurance coverage: (i) Comprehensive General Liability Insurance for claims arising from bodily injury, personal injury and property damage occurring upon, in or about the government property on an occurrence basis with combined single limit coverage of not less than one million and 00/100 dollars ($1,000,000.00) per occurrence and two million and 00/100 dollars ($2,000,000.00) in the aggregate; and (ii) Workers Compensation Insurance as required by law.



12. All such insurance shall be issued by insurers duly authorized and licensed to do business in the Commonwealth of Massachusetts. All such insurance shall provide that coverage may not be canceled without twenty (20) days prior written notice to the GSA. Certificates of Insurance evidencing such insurance policies, in a form reasonably acceptable to GSA, shall be provided prior to work commencing on the project.



13. Contractor shall be liable for any damage to the building incurred as a result of the work being performed under this contract. If damage is incurred, DOL shall arrange for repair of the damage and deduct said amount from the balance due on this contract.



14. Any cost incurred by GSA as a result of this project will be the sole responsibility of the contractor.



15. Prevailing wage rates must be paid for all work performed under this award as stipulated by the Davis Bacon Act. (www.wdol.gov)



16. Prior to award, the contractor is required to have a valid registration on file at www.ccr.gov.



Addendum to Scope of Work:



Upon award of contract, contractor agrees to:



1. Complete construction within thirty (30) days;

2. Demolition will only occur during non-working hours (7pm - 6am)



WALK-THROUGH FOR INTERESTED CONTRACTORS:



A walk-through for all interested contractors will be conducted on Friday, September 19, 2008 at 10am. This walk-through will be at JFK Federal Bldg, Room E-215, Boston, MA 02203. We are located right next to Boston City Hall, on City Hall Plaza, and the public entrace for the building is located on Cambridge Street. Please call either Debra Reynolds or Gary Cowan if you require further directions. Please be advised that this is a Federal facilitiy, and you should arrive allowing sufficient time to go through security. There is very limited public parking around the building, but there are several parking garages located in the vicinity of the building.



All responsible sources may submit a quotation which, if timely received, will receive consideration. Initial posting was unclear as to deadline for receipt of quotations. Because of this, quotations may now be submitted no later than Tuesday, September 30, 2008 at 8:00am Eastern Standard Time.



Anticipated Award Date is September 30, 2008.



For additional information, contact Debra Reynolds by phone at 617-788-2848, or email at Reynolds.Debra@dol.gov.





52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)



This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer shall make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):



www.acqnet.gov



FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES



CLAUSE TITLE



52.212-01 Instructions to Offerors Commercial Items

52.212-02 Evaluation Commercial Items

52.222-06 Davis Bacon Act

52.211-10 Commencement, Prosecution, and Completion of Work

52.212-04 Contract Terms and Conditions Commercial Items

52.212-05 Contract Terms and Conditions Required to Implement Statutes Executive Orders-Commercial Items.

52.219-8 Utilization of Small Business Concerns

52.232-33 Payment by Electronic Funds Transfer-Central Contractor Registration

52.222-41 Service Contract Act of 1965, as Amended

52.236-5 Material and Workmanship

52.236-7 Permits and Responsibilities

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvement

52.236-12 Cleaning Up

52.236-15 Schedules for Construction Contracts

52.203-5 Covenant Against Contingent Fees

52.203-7 Anti-Kickback Procedures

52.216-24 Limitation of Government Liability

52.216-25 Contract Definitization

52.223-13 Certification of Toxic Chemical Release Reporting

52.223-14 Toxic Chemical Release Reporting

52.223-15 Restrictions on Certain Foreign Purchases

52.232-5 Payments under Fixed-Price Construction Contracts

52.232-27 Prompt Payment for Construction Contracts

52.233-2 Service of Protest

52.233-3 Protest after Award

52.233-4 Applicable Law for Breach of Contract Claim

52.236-28 Preparation of Proposals Construction

52.244-6 Subcontracts for Commercial Items

Please consult the list of document viewers if you cannot open a file.
Diagrams
Sensitive/Secure Package:
no
Type:
Other (Draft RFPs/RFIs, Responses to Questions, etc..)
Label:
Diagrams
Posted Date:
September 29, 2008
DEMO.pdf (47.69 Kb)
Description: Diagram of Demo
New Constr.pdf (50.72 Kb)
Description: Diagram of New Construction
Contracting Office Address:
John F. Kennedy Federal Bldg. E215
Boston, Massachusetts 02203
Place of Performance:
JFK Federal Bldg, RM E-215
25 New Sudbury Street
Boston, Massachusetts 02203
United States
Primary Point of Contact.:
Debra L. Reynolds,
Contracting Officer
Phone: 6177882848
Fax: 6177882833
Secondary Point of Contact:
Gary Cowan,
RFASO
Phone: 6177882807
Fax: 6177882833
All Files
General Information
Notice Type:
Combined Synopsis/Solicitation
Original Posted Date:
September 4, 2008
Posted Date:
September 29, 2008
Response Date:
Sep 30, 2008 8:00 am Eastern
Original Response Date:
Sep 26, 2008 11:00 am Eastern
Archiving Policy:
Automatic, 15 days after response date
Original Archive Date:
October 11, 2008
Archive Date:
October 15, 2008
Original Set Aside:
N/A
Set Aside:
N/A
Classification Code:
Z -- Maintenance, repair, and alteration of real property
NAICS Code:
238 -- Specialty Trade Contractors/238390 -- Other Building Finishing Contractors




Home - Browse By Keyword - Browse By Region - About Us - Privacy Policy - Terms of Use - Sitemap - Help
Copyright 2004 GovCB.com All rights reserved