THE FOLLOWING QUESTIONS HAVE BEEN RECEIVED AS OF 7/15/08.
Q1. HOW MANY INCHES OF BASE ROCK ARE REQUIRED?
A1. 2 INCHES OF ROCK WITH 90% COMPACTION.
Q2. HOW MANY LIFTED AREAS ON THE SIDEWALKS AND WALKWAYS ARE IN NEED OF GRINDING?
A1. 16 AREAS HAVE BEEN COUNTED AS NEEDING GROUND.
Contractor to furnish all labor, material, transportation, supplies and supervision necessary to Construct a 4 wide x 300 long x 4 thick concrete Walkway between housing units at DDJC Sharpe Site, Lathrop, CA.
The Statement of work has been revised to incorporate the following changes...
Change 1
1. Contractor to furnish all labor, material, transportation, supplies and supervision
necessary to Construct 3 feet wide x 300 feet long x 4 inches thick concrete Walkway
between housing units:
is revised to read...
1. Contractor to furnish all labor, material, transportation, supplies and supervision
necessary to Construct 4 feet wide x 300 feet long x 4 inches thick concrete Walkway
between housing units:
Change 2
1.9 Repair side walks and walkways and cut the roots before pouring cement.
is revised to read...
1.9 Grind lifted side walks and walkways around the entire housing area.
Change 3
1.10 Construct 2 each handicap accessible ramps.
is revised to read...
1.10 Construct 3 each handicap accessible ramps.